Toronto Water 2018 Year End Capital Budget and 2019-2028 Capital Plan Adjustments

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2019-04-15 · Budget Committee · adopted

As filed

The Budget Committee recommends that: 1. City Council authorize the reallocation of 2018 cashflows within Toronto Water's approved 2018 Capital Budget and 2019-2027 Capital Plan in the amount of $77.299 million, for acceleration and deferral of projects, as presented in Schedule A (Parts A and B) to the report (April 1, 2019) from the General Manager, Toronto Water, with a zero Budget impact. 2. City Council authorize the reallocation of 2019, 2020 and 2021 cashflows within Toronto Water's approved 2019 Capital Budget and 2020-2028 Capital Plan in the amount of $77.299 million, for acceleration and deferral of projects, as presented in Schedule A (Parts A and B) to the report (April 1, 2019) from the General Manager, Toronto Water, with a zero Budget impact.

Show the rest of As filed, 439 more characters as filed

3. City Council authorize the reallocation of 2018 cashflows and project costs in Toronto Water's approved 2018 Capital Budget and 2019-2027 Capital Plan in the amount of $5.827 million from projects that have been completed or awarded under budget to those requiring additional funding in the same amount as presented in Schedule A (Part C) to the report (April 1, 2019) from the General Manager, Toronto Water, with a zero Budget impact.

On the agenda

As the city filed it

This report requests City Council's authority to amend Toronto Water's Approved 2018 Capital Budget by adjusting project costs and cash flows to align with year-end expenditures and project progress. The adjustments will have a zero dollar impact on the 2018 Capital Budget. This report requests City Council's authority to amend Toronto Water's Approved 2019 Capital Budget and 2020-2028 Capital Plan by adjusting project costs and cash flows contained within the Budget and Plan, respectively, to align the 2019 Capital Budget with the final 2018 capital expenditures and project progress.

Show the rest of As the city filed it, 216 more characters as filed

The adjustments will have a zero dollar impact on the 2019 Capital Budget and 2020-2028 Capital Plan and will align the budget and plan with Toronto Water's capital project delivery schedule and program requirements.

Staff recommended

The General Manger, Toronto Water recommends that: 1. City Council authorize the reallocation of 2018 cashflows within Toronto Water's approved 2018 Capital Budget and 2019-2027 Capital Plan in the amount of $77.299 million, for acceleration and deferral of projects, as presented in Schedule A (Part A and B), with a zero Budget impact. 2. City Council authorize the reallocation of 2019, 2020 and 2021 cashflows within Toronto Water's approved 2019 Capital Budget and 2020-2028 Capital Plan in the amount of $77.299 million, for acceleration and deferral of projects, as presented in Schedule A (Part A and B), with a zero Budget impact.

Show the rest of Staff recommended, 369 more characters as filed

3. City Council authorize the reallocation of 2018 cashflows and project costs in Toronto Water's approved 2018 Capital Budget and 2019-2027 Capital Plan in the amount of $5.827 million from projects that have been completed or awarded under budget to those requiring additional funding in the same amount as presented in Schedule A (Part C), with a zero Budget impact.

    On the record