Closure of Don Valley Parkway Ramps at Eglinton Avenue East
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2019-06-18 · Toronto City Council · adopted
As filed
City Council on June 18 and 19, 2019, adopted the following: 1. City Council amend City of Toronto Municipal Code Chapter 937, Temporary Closing of Highways, to delegate to the General Manager, Transportation Services the authority to temporarily close to vehicular traffic each of the Don Valley Parkway southbound off-ramp to Eglinton Avenue East, the Eglinton Avenue East westbound on-ramp to the Don Valley Parkway southbound, the Eglinton Avenue East westbound on-ramp to the Don Valley Parkway northbound, the Eglinton Avenue East eastbound on-ramp to the Don Valley Parkway southbound, the Eglinton Avenue East eastbound on-ramp to the Don Valley Parkway northbound and the Don Valley Parkway northbound off-ramp to Eglinton Avenue East, from 11:00 p.m.
Show the rest of As filed, 652 more characters as filed
on Friday to 5:00 a.m. on Monday for up to and including four weekends between June 20, 2019 to December 31, 2019, to facilitate the installation of electrical infrastructure and road paving for the purposes of the Eglinton Crosstown Light Rail Transit project. 2. City Council exempt the General Manager, Transportation Services, in carrying out the authority under Part 1 above, from Section 937-5 of City of Toronto Municipal Code Chapter 937, Temporary Closing of Highways, the requirement to notify the local Ward Councillor of the pending closure and the requirement to report on the proposed closure if so requested by the local Ward Councillor.
On the agenda
As the city filed it
The purpose of this letter is to seek approval to authorize the General Manager, Transportation Services, to temporarily close the Don Valley Parkway (DVP) ramps at Eglinton Avenue East for a period of up to four weekends between June 20, 2019 to December 31, 2019 to facilitate the installation of electrical infrastructure and roadway paving for the Eglinton Crosstown Light Rail Transit project. The annual DVP spring maintenance closure is planned on May 25-27, 2019.
Show the rest of As the city filed it, 347 more characters as filed
Crosslinx Transit Solutions (CTS) is planning to utilize the City maintenance closure to perform the work, thus avoiding the need for an additional weekend closure of the DVP ramps. However, in the event of cancellation of the City maintenance closure, or inclement weather, additional closure of the ramps will be required to accomplish the work.
Staff recommended
Deputy Mayor Denzil Minnan-Wong requests that the Infrastructure and Environment Committee recommend that: 1. City Council amend City of Toronto Municipal Code Chapter 937, Temporary Closing of Highways, to delegate to the General Manager, Transportation Services, the authority to temporarily close to vehicular traffic each of the Don Valley Parkway southbound off-ramp to Eglinton Avenue East, the Eglinton Avenue East westbound on-ramp to the Don Valley Parkway southbound, the Eglinton Avenue East westbound on-ramp to the Don Valley Parkway northbound, the Eglinton Avenue East eastbound on-ramp to the Don Valley Parkway southbound, the Eglinton Avenue East eastbound on-ramp to the Don Valley Parkway northbound and the Don Valley Parkway northbound off-ramp to Eglinton Avenue East, from 11:00 p.m.
Show the rest of Staff recommended, 662 more characters as filed
on Friday to 5:00 a.m. on Monday for up to and including four weekends between June 20, 2019 to December 31, 2019, to facilitate the installation of electrical infrastructure and road paving for the purposes of the Eglinton Crosstown Light Rail Transit project. 2. City Council exempt the General Manager, Transportation Services, in carrying out her authority under Recommendation 1 above, from Section 937-5 of City of Toronto Municipal Code Chapter 937, Temporary Closing of Highways, the requirement to notify the local Ward Councillor of the pending closure and the requirement to report on the proposed closure if so requested by the local Ward Councillor.
Considered
2019-05-23 · Infrastructure and Environment Committee · adopted
Decision as filed
The Infrastructure and Environment Committee recommends that: 1. City Council amend City of Toronto Municipal Code Chapter 937, Temporary Closing of Highways, to delegate to the General Manager, Transportation Services, the authority to temporarily close to vehicular traffic each of the Don Valley Parkway southbound off-ramp to Eglinton Avenue East, the Eglinton Avenue East westbound on-ramp to the Don Valley Parkway southbound, the Eglinton Avenue East westbound on-ramp to the Don Valley Parkway northbound, the Eglinton Avenue East eastbound on-ramp to the Don Valley Parkway southbound, the Eglinton Avenue East eastbound on-ramp to the Don Valley Parkway northbound and the Don Valley Parkway northbound off-ramp to Eglinton Avenue East, from 11:00 p.m.
Show the rest of Decision as filed, 662 more characters as filed
on Friday to 5:00 a.m. on Monday for up to and including four weekends between June 20, 2019 to December 31, 2019, to facilitate the installation of electrical infrastructure and road paving for the purposes of the Eglinton Crosstown Light Rail Transit project. 2. City Council exempt the General Manager, Transportation Services, in carrying out the authority under Recommendation 1 above, from Section 937-5 of City of Toronto Municipal Code Chapter 937, Temporary Closing of Highways, the requirement to notify the local Ward Councillor of the pending closure and the requirement to report on the proposed closure if so requested by the local Ward Councillor.
2019-06-18 · Toronto City Council · adopted
On the record
More from this meeting
- Contract Award of Negotiable Request for Proposal Number 4204-19-5019 for the Construction of Watermains and Amendment to Purchase Orders Number 6045918 and 6046025 for Engineering Services for Detailed DesignFiled record
- Amendment to Purchase Order Number 6025318 for Headworks and Odour Control Upgrades at the Highland Creek Treatment Plant with AECOM Canada Ltd.Filed record
- Contract Award for Purchase of Equipment for the Biosolids Master Plan Implementation at the Highland Creek Wastewater Treatment Plant, Request for Proposal Number 9117-18-7202Filed record
- Contract Award for Tender Call Number 54-2019 for the Rehabilitation of Four Bridges over the Don Valley ParkwayFiled record