Construction Staging Area Time Extension - 2360 Yonge Street
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2019-02-26 · Toronto City Council · adopted
As filed
City Council on February 26, 2019, adopted the following: 1. City Council approve the continuation of the closure of the west sidewalk and 1.7 metres of the southbound curb lane on Yonge Street, from Helendale Avenue to a point 58 metres south of Helendale Avenue, from March 1, 2019 until February 1, 2020. 2. City Council direct that Yonge Street be returned to its pre-construction parking and traffic regulations when the project is completed.
On the agenda
As the city filed it
As the Toronto Transit Commission (TTC) operates bus service on Yonge Street, City Council approval of this report is required. Lifetime Developments is constructing a 29-storey condominium at 2360 Yonge Street. The site is bounded by Yonge Street to the east, Helendale Avenue to the north and existing developments to the west and south. The developer has received approval from City Council to occupy the west sidewalk and 1.7 metres of the southbound curb lane on Yonge Street, from Helendale Avenue to a point 58 metres south, until February 1, 2019.
Show the rest of As the city filed it, 387 more characters as filed
The developer has also received approval from North York Community Council to occupy the south sidewalk and full roadway on Helendale Avenue, from Yonge Street to a point 27 metres west of Yonge Street, until July 5, 2019. Transportation Services is requesting City Council approval to extend the duration of the existing construction staging area on Yonge Street until February 1, 2020.
Staff recommended
The Acting Director, Traffic Management, Transportation Services recommends that: 1. City Council approve the continuation of the closure of the west sidewalk and 1.7 metres of the southbound curb lane on Yonge Street, from Helendale Avenue to a point 58 metres south of Helendale Avenue, from March 1, 2019 until February 1, 2020. 2. City Council direct that Yonge Street be returned to its pre-construction parking and traffic regulations when the project is completed.
Considered
2019-02-14 · North York Community Council · adopted
Decision as filed
North York Community Council recommends that: 1. City Council approve the continuation of the closure of the west sidewalk and 1.7 metres of the southbound curb lane on Yonge Street, from Helendale Avenue to a point 58 metres south of Helendale Avenue, from March 1, 2019 until February 1, 2020. 2. City Council direct that Yonge Street be returned to its pre-construction parking and traffic regulations when the project is completed.
2019-02-26 · Toronto City Council · adopted
On the record
More from this meeting
- Final Report - Official Plan Amendment and Zoning By-law Amendment Applications - 30 Tippett Road (South Lands)Filed record
- Final Report - Official Plan and Zoning By-law Amendment Application and Rental Housing Demolition Applications - 15-21 Holmes AvenueFiled record
- Request for Interim Direction Report - Zoning By-law Amendment Application - 25 Fisherville RoadFiled record
- Request for Direction Report - Zoning By-law Amendment Application - 2450 Victoria Park AvenueFiled record
- Request for Directions Report - Official Plan Amendment and Zoning By-law Amendment Applications - 2600 Don Mills RoadFiled record
- Preliminary Report - Official Plan and Zoning By-law Amendment Applications - 1304, 1306 and 1308 Wilson AvenueFiled record