Construction Staging Area Time Extension - Davenport Road - 128 Hazelton Avenue
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2019-03-27 · Toronto City Council · adopted
As filed
City Council on March 27 and 28, 2019, adopted the following: 1. City Council approve the continuation of the closure of the sidewalk and a portion of the eastbound curb lane on the south side of Davenport Road, between Hazelton Avenue and a point 35 metres west and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane, from March 27, 2019 to April 30, 2020. 2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
Show the rest of As filed, 1,455 more characters as filed
3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 4. City Council direct the applicant to continue sweeping the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe. 5. City Council direct the applicant to continue pressure washing the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 6. City Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night. 7. City Council direct the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 8. City Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 9. City Council direct that Davenport Road be returned to its pre-construction traffic and parking regulations when the project is complete.
On the agenda
As the city filed it
As the Toronto Transit Commission operates a transit service on Davenport Road, City Council approval of this report is required. Clark Construction Management is constructing a 9-storey condominium building at 128 Hazelton Avenue. The site is located in the south-west corner of Davenport Road and Hazelton Avenue. The sidewalk and a portion of the eastbound lane on the south side of Davenport Road fronting the site are currently closed to accommodate construction staging operations for the development.
Show the rest of As the city filed it, 373 more characters as filed
City Council, at its meeting on January 31 and February 1, 2018, approved the subject construction staging area on Davenport Road, from February 7, 2018 to February 7, 2019. A time extension of the construction staging area on Davenport Road for an additional 13 months (i.e. from March 27, 2019 to April 30, 2020), in order to complete the construction of the development.
Staff recommended
The Acting Director, Traffic Management, Transportation Services recommends that: 1. City Council approve the continuation of the closure of the sidewalk and a portion of the eastbound curb lane on the south side of Davenport Road, between Hazelton Avenue and a point 35 metres west and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane, from March 27, 2019 to April 30, 2020.
Show the rest of Staff recommended, 1,693 more characters as filed
2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 4. City Council direct the applicant to continue sweeping the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe. 5. City Council direct the applicant to continue pressure washing the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 6. City Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night. 7. City Council direct the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 8. City Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 9. City Council direct that Davenport Road be returned to its pre-construction traffic and parking regulations when the project is complete.
Considered
2019-03-19 · Toronto and East York Community Council · adopted
Decision as filed
The Toronto and East York Community Council recommends that: 1. City Council approve the continuation of the closure of the sidewalk and a portion of the eastbound curb lane on the south side of Davenport Road, between Hazelton Avenue and a point 35 metres west and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane, from March 27, 2019 to April 30, 2020. 2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
Show the rest of Decision as filed, 1,455 more characters as filed
3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 4. City Council direct the applicant to continue sweeping the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe. 5. City Council direct the applicant to continue pressure washing the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 6. City Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night. 7. City Council direct the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 8. City Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 9. City Council direct that Davenport Road be returned to its pre-construction traffic and parking regulations when the project is complete.
2019-03-27 · Toronto City Council · adopted
On the record
More from this meeting
- Naming of an Existing Public Lane Located East of Gladstone Avenue, Extending Between Argyle Street and Cross Street.Filed record
- Naming of an Existing Public Lane North of Davenport Road, Extending Between Regal Road and Oakwood AvenueFiled record
- Naming of an Existing Public Lane North of St. Clair Avenue West, Extending Between Nairn Avenue and Earlscourt AvenueFiled record
- Naming of an Existing Public Lane Located East of Bathurst Street, Extending Northerly from Nassau StreetFiled record
- Naming of an Existing Public Lane South of College Street, Extending Between Manning Avenue and Euclid AvenueFiled record
- Naming of an Existing Public Lane Located East of Manning Avenue, Extending Southerly from London Street to William Oliphant LaneFiled record