Construction Staging Area Time Extension - 4 Avenue Road

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2019-10-29 · Toronto City Council · amended

As filed

City Council on October 29 and 30, 2019, adopted the following: 1. City Council authorize the closure of the sidewalk on the west side of Avenue Road, between Bloor Street West and Prince Arthur Avenue, from October 30, 2019 to January 31, 2020. 2. City Council direct that the previously-approved stopping prohibition in effect at all times on the on the west side of Avenue Road, between a point 17.5 metres north of Bloor Street West and Prince Arthur Avenue, remain in force until the end of the project.

Show the rest of As filed, 649 more characters as filed

3. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 4. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 5. City Council direct that Avenue Road be returned to its pre-construction traffic and parking regulations when the project is complete.

On the agenda

As the city filed it

As the Toronto Transit Commission (TTC) operates a transit service on Avenue Road, City Council approval of this report is required. PCL Constructors Canada Incorporated is redeveloping the existing Park Hyatt hotel at 4 Avenue Road, located in the north-west corner of Avenue Road and Bloor Street West. City Council, previously approved a closure of the west sidewalk and a 2.9 metre wide portion of the southbound curb lane on Avenue Road, between a point 54.8 metres north of Bloor Street West and a point 56.4 metres further north and the provision of a temporary pedestrian walkway within the closed lane, from November 1, 2018 to May 30, 2019.

Show the rest of As the city filed it, 955 more characters as filed

Based on a secondary review of the Traffic Management Plan and site logistics, the applicant has reduced the footprint of the previously-approved construction staging area, thus avoiding the need for a long term lane closure of the southbound curb lane on Avenue Road. As a result, the southbound curb lane on Avenue Road is temporarily closed, daily, during the off-peak periods (9:30 a.m. to 7:00 p.m.), to facilitate construction staging operations. A temporary pedestrian walkway is not provided on the west side of Avenue Road. Transportation Services is requesting authorization to close the sidewalk on the west side of Avenue Road, between Bloor Street West and Prince Arthur Avenue for a period of nine months (i.e. October 30, 2019 to July 31, 2020). The closure of the sidewalk will restrict pedestrian movements along the subject section of Avenue Road. This will mitigate impacts to southbound traffic movements during the morning peak hours.

Staff recommended

The Acting Director, Traffic Management, Transportation Services, recommends that: 1. City Council authorize the closure of the sidewalk on the west side of Avenue Road, between Bloor Street West and Prince Arthur Avenue, from October 30, 2019 to July 31, 2020. 2. City Council direct to authorize that the previously-approved stopping prohibition in effect at all times on the on the west side of Avenue Road, between a point 17.5 metres north of Bloor Street West and Prince Arthur Avenue, to remain enforced until the end of the project.

Show the rest of Staff recommended, 649 more characters as filed

3. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 4. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 5. City Council direct that Avenue Road be returned to its pre-construction traffic and parking regulations when the project is complete.