Construction Staging Area Time Extension - Hazelton Avenue - 128 Hazelton Avenue

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2019-10-10 · Toronto and East York Community Council · adopted

As filed

The Toronto and East York Community Council: 1. Authorized the continuation of the closure of the west sidewalk and a 2.6 metre wide portion of the northbound lane on Hazelton Avenue, between Davenport Road and a point 32 metres south, from November 1, 2019 April 30, 2020. 2. Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

Show the rest of As filed, 393 more characters as filed

3. Directed the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 4. Directed that Hazelton Avenue be returned to its pre-construction traffic and parking regulations when the project is complete.

On the agenda

As the city filed it

This staff report is about a matter that Community Council has delegated authority to make a final decision, provided that it is not amended so that it varies with City policy or by-laws. Clark Construction Management is constructing a 9-storey condominium building at 128 Hazelton Avenue. The site is located in the south-west corner of Davenport Road and Hazelton Avenue. Construction staging areas for the development have been set up on the south side of Davenport Road and the west side of Hazelton Avenue.

Show the rest of As the city filed it, 672 more characters as filed

Toronto and East York Community Council, at its meeting on January 16, 2018, approved the subject construction staging area on Hazelton Avenue, from February 7, 2018 to October 31, 2019. Transportation Services is requesting approval to extend the duration of the construction staging area on Hazelton Avenue for an additional six months - i.e. from November 1, 2019 to April 30, 2020 - in order to complete the construction of the development. The developer has requested an extension of the duration of the construction staging area on Hazleton Avenue, as the site has experienced a number of construction delays due ground water contamination and site logistics issues.

Staff recommended

The Acting Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council authorize the continuation of the closure of the west sidewalk and a 2.6 metre wide portion of the northbound lane on Hazelton Avenue, between Davenport Road and a point 32 metres south, from November 1, 2019 April 30, 2020. 2. Toronto and East York Community Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

Show the rest of Staff recommended, 469 more characters as filed

3. Toronto and East York Community Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 4. Toronto and East York Community Council direct that Hazelton Avenue be returned to its pre-construction traffic and parking regulations when the project is complete.