The filed record
Toronto Water 2020 Capital Budget and 2021-2029 Capital Plan Adjustments
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2020-10-27 · Toronto City Council · adopted
As filed
City Council on October 27, 28 and 30, 2020, adopted the following: 1. City Council authorize the reallocation of cashflows within the Toronto Water Approved 2020 Capital Budget and 2021-2029 Capital Plan in the amount of $52.234 million, for acceleration and deferral of projects, as presented in Schedule A (Part A and B) to the report (September 24, 2020) from the General Manager, Toronto Water with a zero Budget impact.
Show the rest of As filed, 440 more characters as filed
2. City Council authorize the reallocation of project costs and cashflows in the Toronto Water Approved 2020 Capital Budget and 2021-2029 Capital Plan in the amount of $6.169 million from projects that have been awarded under budget or completed to those requiring additional funding in the same amount as presented in Schedule A (Part C) to the report (September 24, 2020) from the General Manager, Toronto Water with a zero Budget impact.
On the agenda
As the city filed it
This report requests City Council's authority to amend Toronto Water's Approved 2020 Capital Budget and 2021-2029 Capital Plan by adjusting project cash flows contained within the Budget and Plan, respectively, to align forecasted project accelerations and deferrals. Additional reallocations to project cashflows and project costs are requested where additional project costs exceed the current approved cashflow. These reallocations will allow Toronto Water to continue to deliver projects within its capital plan.
Show the rest of As the city filed it, 216 more characters as filed
The adjustments will have a zero dollar impact on the 2020 Capital Budget and 2021-2029 Capital Plan and will align the budget and plan with Toronto Water's capital project delivery schedule and program requirements.
Staff recommended
The Budget Committee recommends that: 1. City Council authorize the reallocation of cashflows within the Toronto Water approved 2020 Capital Budget and 2021-2029 Capital Plan in the amount of $52.234 million, for acceleration and deferral of projects, as presented in Schedule A (Part A and B) to the report (September 24, 2020) from the General Manager, Toronto Water, with a zero Budget impact. 2. City Council authorize
Show the rest of Staff recommended, 415 more characters as filed
the reallocation of project costs and cashflows in the Toronto Water approved 2020 Capital Budget and 2021-2029 Capital Plan in the amount of $6.169 million from projects that have been awarded under budget or completed to those requiring additional funding in the same amount as presented in Schedule A (Part C) to the report (September 24, 2020) from the General Manager, Toronto Water, with a zero Budget impact.
Considered
2020-10-21 · Executive Committee · adopted
Decision as filed
The Executive Committee recommends that: 1. City Council authorize the reallocation of cashflows within the Toronto Water Approved 2020 Capital Budget and 2021-2029 Capital Plan in the amount of $52.234 million, for acceleration and deferral of projects, as presented in Schedule A (Part A and B) to the report (September 24, 2020) from the General Manager, Toronto Water with a zero Budget impact. 2. City Council authorize
Show the rest of Decision as filed, 414 more characters as filed
the reallocation of project costs and cashflows in the Toronto Water Approved 2020 Capital Budget and 2021-2029 Capital Plan in the amount of $6.169 million from projects that have been awarded under budget or completed to those requiring additional funding in the same amount as presented in Schedule A (Part C) to the report (September 24, 2020) from the General Manager, Toronto Water with a zero Budget impact.
2020-10-27 · Toronto City Council · adopted
On the record
More from this meeting
- Towards Recovery and Building a Renewed TorontoFiled record
- Implementing Tenants First: 2020 Action UpdatesFiled record
- Update on Nathan Phillips Square Bike StationFiled record
- Drone Safety in the City of TorontoFiled record
- CD6.6 TO Prosperity - Interim Poverty Reduction StrategyFiled record
- Federation of Canadian Municipalities (FCM) Cyber Security UpdateFiled record