The Public GalleryToronto

Infrastructure and Environment Committee · 2020-07-09 · 2020.IE14.5

The filed record

Authority to Negotiate and Enter into an Agreement for the Construction of Water Works along Lower Jarvis Street with Aecon Construction and Materials Limited

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2020-07-28 · Toronto City Council · adopted

As filed

City Council on July 28 and 29, 2020, adopted the following: 1. City Council authorize the Chief Engineer and Executive Director of Engineering and Construction Services and/or designate to negotiate and enter into an appropriate form of agreement with Aecon, the current contractor of the F.G. Gardiner Expressway Rehabilitation Project: Section 1 - Jarvis Street to Cherry Street (Contract 18ECS-TI-01GE), to deliver the

Show the rest of As filed, 1,474 more characters as filed

Water Works based on the terms and conditions set out in Confidential Attachment 1 to the report (June 24, 2020) from the Chief Engineer and Executive Director, Engineering and Construction Services and the Chief Procurement Officer and on terms satisfactory to the Chief Engineer and Executive Director of Engineering and Construction Services and each in a form satisfactory to the City Solicitor. 2. City Council direct that Confidential Attachment 1 to the report (June 24, 2020) from the Chief Engineer and Executive Director, Engineering and Construction Services and the Chief Procurement Officer remain confidential in its entirety as it relates to commercial or financial information that belongs to the City and has potential monetary value, and it involves a position, plan or procedure, criteria or instruction to be applied to any negotiation carried on, or to be carried on by or on behalf of the City. Confidential Attachment 1 to the report (June 24, 2020) from the Chief Engineer and Executive Director, Engineering and Construction Services and the Chief Procurement Officer remains confidential in its entirety in accordance with the provisions of the City of Toronto Act, 2006, as it relates to commercial or financial information that belongs to the City and has potential monetary value, and it involves a position, plan or procedure, criteria or instruction to be applied to any negotiation carried on, or to be carried on by or on behalf of the City.

On the agenda

As the city filed it

The purpose of this report is to request authority to negotiate and enter into a new or amending agreement with Aecon Construction and Materials Limited (Aecon), the contractor for the F.G. Gardiner Expressway Rehabilitation Project: Section 1 - Jarvis Street to Cherry Street (Contract No. 18ECS-TI-01GE), to construct a new sanitary sewer and watermain (Water Works) along Lower Jarvis Street, intersecting Aecon's Gardiner Expressway construction work zone.

Show the rest of As the city filed it, 923 more characters as filed

The terms and conditions of the proposed agreement are set out in Confidential Attachment 1 of the report. These Water Works involve the upgrading of the existing sanitary sewer along Lower Jarvis Street from south of Lake Shore Boulevard to north of the Metrolinx Lakeshore East Corridor bridge over Lower Jarvis Street; and the replacement of the existing 90 year old cast iron watermain, which is in poor condition, along Lower Jarvis Street, from The Esplanade to Queen's Quay. Undertaking this work now will ensure that adequate sanitary sewer capacity will be in place by mid-2021, to support the new development in the East Bayfront Waterfront Community; and given the major traffic disruption resulting from this construction undertaking this work now aligns with the City's objective of accelerating construction, where possible, to take advantage of the lower traffic volumes as a result of the COVID-19 pandemic.

Staff recommended

The Chief Engineer and Executive Director, Engineering and Construction Services and the Chief Procurement Officer recommend that: 1. City Council direct that the information in Confidential Attachment 1 to this report remain confidential in its entirety as it relates to commercial or financial information that belongs to the City and has potential monetary value, and it involves a position, plan or procedure, criteria or instruction to be applied to any negotiation carried on, or to be carried on by or on behalf of the City.

Show the rest of Staff recommended, 629 more characters as filed

2. City Council authorize the Chief Engineer and Executive Director of Engineering and Construction Services and/or designate to negotiate and enter into an appropriate form of agreement with Aecon, the current contractor of the F.G. Gardiner Expressway Rehabilitation Project: Section 1 - Jarvis Street to Cherry Street (Contract No. 18ECS-TI-01GE), to deliver the Water Works based on the terms and conditions set out in Confidential Attachment 1 of the report and on terms satisfactory to the Chief Engineer and Executive Director of Engineering and Construction Services and each in a form satisfactory to the City Solicitor.

Considered

  • 2020-07-09 · Infrastructure and Environment Committee · adopted

    Decision as filed

    The Infrastructure and Environment Committee recommends that: 1. City Council direct that the information in Confidential Attachment 1 to the report (June 24, 2020) from the Chief Engineer and Executive Director, Engineering and Construction Services and the Chief Procurement Officer remain confidential in its entirety as it relates to commercial or financial information that belongs to the City and has potential monetary value, and it involves a position, plan or procedure, criteria or instruction to be applied to any negotiation carried on, or to be carried on by or on behalf of the City.

    Show the rest of Decision as filed, 765 more characters as filed

    2. City Council authorize the Chief Engineer and Executive Director of Engineering and Construction Services and/or designate to negotiate and enter into an appropriate form of agreement with Aecon, the current contractor of the F.G. Gardiner Expressway Rehabilitation Project: Section 1 - Jarvis Street to Cherry Street (Contract No. 18ECS-TI-01GE), to deliver the Water Works based on the terms and conditions set out in Confidential Attachment 1 to the report (June 24, 2020) from the Chief Engineer and Executive Director, Engineering and Construction Services and the Chief Procurement Officer and on terms satisfactory to the Chief Engineer and Executive Director of Engineering and Construction Services and each in a form satisfactory to the City Solicitor.

  • 2020-07-28 · Toronto City Council · adopted

On the record

The item as the City filed it

More from this meeting

The whole meeting