The decision
2020-10-27 · Toronto City Council · amended
As filed
City Council on October 27, 28 and 30, 2020, adopted the following: 1. City Council request the General Manager, Transportation Services, to consider and explore including, as part of either the 2021 update to the cycling network plan, the COVID-19 pandemic cycling network expansion response plan or potentially as part of the YongeTOmorrow process, a temporary protected bikeway along Yonge Street or parallel routes from
Show the rest of As filed, 396 more characters as filed
Bloor Street to north of Lawrence Avenue in conjunction with on-street patios, road safety and traffic-calming measures, and other streetscape improvements identified through consultation with local businesses and community groups, following the complete streets approach applied to Danforth Avenue, with implementation by the second quarter of 2021, and iteration and evaluation throughout 2021.
The vote
Adopt Item as Amended · Carried, 19-3
The whole record, all 25 members
- Ana BailãoFor
- Anthony PerruzzaFor
- Brad BradfordFor
- Cynthia LaiFor
- Denzil Minnan-WongAgainst
- Frances NunziataFor
- Gary CrawfordFor
- Gord PerksFor
- James PasternakFor
- Jaye RobinsonAbsent
- Jennifer McKelvieFor
- Joe CressyAbsent
- John FilionFor
- John ToryAbsent
- Josh MatlowFor
- Kristyn Wong-TamFor
- Mark GrimesFor
- Michael FordAgainst
- Michael ThompsonFor
- Mike ColleFor
- Mike LaytonFor
- Paul AinslieFor
- Paula FletcherFor
- Shelley CarrollFor
- Stephen HolydayAgainst
Every name opens that member’s record.
On the agenda
As the city filed it
The ActiveTO initiative has played a vital role in Toronto's recovery and rebuild process, providing city residents of all ages and abilities with new, temporary and permanent, bikeways, which allow them to enjoy fresh air, obtain healthy exercise, and safely get around the city. The benefit of these cycling facilities must now be expanded to reach other parts of the city. "Our streets are going to look different in many
Show the rest of As the city filed it, 962 more characters as filed
places in the post-COVID world...we will need more bike infrastructure," said Mayor John Tory when launching the ActiveTO initiative, which is "going to mean more business for shop owners, it's going to mean that we're going to take some of the pressure off our transit system and protect the health of the city." Building a resilient city not only means providing clean and safe transportation alternatives during the current pandemic but achieving existing city policies, including the Vision Zero Road Safety Plan, the Cycling Network Plan, TransformTO's climate mitigation plan through the reduction of short trips travelled by car, as well as the City's equity and public health initiatives. Given the aforementioned policy goals, the need to accommodate active transportation during the COVID-19 pandemic, and the strong local community support, it is crucial that we prioritize a temporary bikeway along Yonge Street in Midtown, aligned with TTC's Line 1.
Staff recommended
Councillor Colle recommends that: 1. The Infrastructure and Environment Committee request the General Manager, Transportation Services, to include, as part of either the 2021 update to the cycling network plan or COVID-19 pandemic cycling network expansion response plan, a temporary protected bikeway along Yonge Street from south of St. Clair Avenue to north of Lawrence Avenue in conjunction with on-street patios, road
Show the rest of Staff recommended, 312 more characters as filed
safety and traffic-calming measures, and other streetscape improvements identified through consultation with local businesses and community groups, following the complete streets approach applied to Danforth Avenue, with implementation by the second quarter of 2021, and iteration and evaluation throughout 2021.
Considered
2020-09-17 · Infrastructure and Environment Committee · amended
Decision as filed
The Infrastructure and Environment Committee recommends that: 1. City Council request the General Manager, Transportation Services, to consider and explore including, as part of either the 2021 update to the cycling network plan, the COVID-19 pandemic cycling network expansion response plan or potentially as part of the YongeTOmorrow process, a temporary protected bikeway along Yonge Street from south of St. Clair Avenue
Show the rest of Decision as filed, 383 more characters as filed
to north of Lawrence Avenue in conjunction with on-street patios, road safety and traffic-calming measures, and other streetscape improvements identified through consultation with local businesses and community groups, following the complete streets approach applied to Danforth Avenue, with implementation by the second quarter of 2021, and iteration and evaluation throughout 2021.
2020-09-30 · Toronto City Council · deferred
Decision as filed
City Council on September 30, October 1 and 2, 2020 deferred consideration of Item IE15.11 to the October 27 and 28, 2020 meeting of City Council.
2020-10-27 · Toronto City Council · amended
On the record
More from this meeting
- Amendment to Purchase Order Number 6047050 with AECOM Canada Limited for the Construction of the King-Liberty Pedestrian / Cyclist Bridge over the Metrolinx Rail CorridorFiled record
- Amendment to a Non-Competitive Bridge Contract with Sidan Traffic Control Services Limited for the Provision of Traffic Control EquipmentFiled record
- Sewers and Water Supply By-laws 2019 Compliance and Enforcement Annual ReportFiled record
- Transition of Toronto's Blue Box Program to Extended Producer ResponsibilityFiled record
- Impact of COVID-19 on Waste Collection and Litter in Greenspaces and ParksFiled record
- Non-Competitive Bridge Contracts for the Provision of Arboricultural Services in the City of TorontoFiled record