Construction Staging Area Time Extension - 1327 Queen Street East

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2020-02-26 · Toronto City Council · adopted

As filed

City Council on February 26, 2020, adopted the following: 1. City Council authorize the continuation of the closure of the south sidewalk and eastbound curb lane on Queen Street East, between Laing Street and a point 83 metres east and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane, from February 28, 2020 to September 30, 2020. 2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

Show the rest of As filed, 416 more characters as filed

3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at the applicant's sole cost, to the satisfaction of the Ward Councillor. 4. City Council direct that Queen Street East be returned to its pre-construction traffic regulations when the project is completed.

On the agenda

As the city filed it

As the Toronto Transit Commission (TTC) operates a transit service on Queen Street East, City Council approval of this report is required. Rockport (Queen & Leslie) Inc. is constructing an eight-storey mixed use development at 1327 Queen Street East. The sidewalk and a portion of the eastbound curb lane on the south side of Queen Street East fronting the site are currently closed to accommodate construction staging operations for the development.

Show the rest of As the city filed it, 808 more characters as filed

City Council, at its meeting on January 31 and February 1, 2018, authorized the subject construction staging area from March 1, 2018 to October 31, 2019. Transportation Services is requesting authorization to extend the construction staging area on Queen Street East for an additional seven months (i.e. from February 28, 2020 to September 30, 2020), in order to complete the construction of the development. It should be noted that during the lapse in approval period, the site has been operating under a monthly Street Occupation Permit. The developer has requested an extension of the duration of the construction staging area on Queen Street East, as the site has experienced a number of construction delays due to continual flooding of the site, inclement weather and multiple redesigns of the building.

Staff recommended

The Acting Director, Traffic Management, Transportation Services, recommends that: 1. City Council authorize the continuation of the closure of the south sidewalk and eastbound curb lane on Queen Street East, between Laing Street and a point 83 metres east and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane, from February 28, 2020 to September 30, 2020. 2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

Show the rest of Staff recommended, 405 more characters as filed

3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor 4. City Council direct that Queen Street East be returned to its pre-construction traffic regulations when the project is completed.

Considered

  • 2020-02-05 · Toronto and East York Community Council · adopted

    Decision as filed

    The Toronto and East York Community Council recommends that: 1. City Council authorize the continuation of the closure of the south sidewalk and eastbound curb lane on Queen Street East, between Laing Street and a point 83 metres east and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane, from February 28, 2020 to September 30, 2020. 2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

    Show the rest of Decision as filed, 405 more characters as filed

    3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor 4. City Council direct that Queen Street East be returned to its pre-construction traffic regulations when the project is completed.

  • 2020-02-26 · Toronto City Council · adopted

On the record

The item as the City filed it

More from this meeting