Construction Staging Area - TTC Easier Access Program - Donlands Station (Phase 1a and 1b)
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2020-09-30 · Toronto City Council · adopted
As filed
City Council on September 30, October 1 and 2, 2020, adopted the following: 1. City Council authorize the closure of the north sidewalk on Strathmore Boulevard, from a point from a point 13 metres west of Donlands Avenue to a point 24 metres further west, from October 2, 2020 to December 31, 2020. 2. City Council authorize the closure of a 2 metre wide portion of the westbound curb lane on Strathmore Boulevard, from a point 13 metres west of Donlands Avenue to a point 24 metres further west, from October 2, 2020 to December 31, 2020.
Show the rest of As filed, 2,977 more characters as filed
3. City Council rescind the existing parking prohibition in effect at all times on the north side Strathmore Boulevard, between Donlands Avenue and a point 45 metres west. 4. City Council prohibit stopping at all times on the north side of Strathmore Boulevard, between Donlands Avenue and a point 45 metres west. 5. City Council rescind the existing maximum one-hour parking regulation in effect from 10:00 a.m. to 6:00 p.m., on the south side of Strathmore Boulevard, between Donlands Avenue and point 52 metres west. 6. City Council prohibit stopping at all times on the south side of Strathmore Boulevard, between Donlands Avenue and a point 52 metres west. 7. City Council direct the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 8. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 9. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 10. City Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 11. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 12. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 13. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 14. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 15. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 16. City Council direct that Strathmore Boulevard be returned to pre-construction traffic and parking regulations when the project is complete.
On the agenda
As the city filed it
As the Toronto Transit Commission (TTC) operates a transit service on Strathmore Boulevard, City Council approval of this report is required. Donlands Station, located on the southwest corner of Donlands Avenue and Strathmore Boulevard, is being modernized to accommodate one at-grade elevator and one below-grade elevator at the main station. In addition, a second entrance/exit is also being added to the station that will be located on the east side of Dewhurst Boulevard south of Strathmore Boulevard, as part of the TTC's Easier Access Program and Second Exit Program.
Show the rest of As the city filed it, 1,190 more characters as filed
Construction of the development will be undertaken in several phases. This report deals with matters related to Phase 1a and 1b of the construction only. Transportation Services is requesting authorization to close a portion of the north sidewalk and a 2 metre wide portion of the westbound curb lane on Strathmore Boulevard from a point 13 metres west of Donlands Avenue and a point 24 metres further west, for a period of three months (i.e., October 2, 2020 to December 31, 2020), to accommodate construction staging operations in Phase 1a. During Phase 1b, the sidewalk and lane closure implemented during Phase 1a will be removed and Strathmore Boulevard will be returned its previous lane configuration. Although no long duration closures are proposed with Phase 1b and the majority of work being completed can be accommodated without encroaching onto the municipal right-of-way, portions on the south sidewalk on Strathmore Boulevard and east sidewalk on Dewhurst Boulevard are proposed to be removed and temporary decking will be used within these areas when construction activities are not taking place. It is anticipated that this phase of the project will be completed April 2021.
Staff recommended
The Acting Director, Traffic Management, Transportation Services, recommends that: 1. City Council authorize the closure of the north sidewalk on Strathmore Boulevard, from a point from a point 13 metres west of Donlands Avenue to a point 24 metres further west, from October 2, 2020 to December 31, 2020. 2. City Council authorize the closure of a 2 metre wide portion of the westbound curb lane on Strathmore Boulevard, from a point 13 metres west of Donlands Avenue to a point 24 metres further west, from October 2, 2020 to December 31, 2020.
Show the rest of Staff recommended, 2,967 more characters as filed
3. City Council rescind the existing parking prohibition in effect at all times on the north side Strathmore Boulevard, between Donlands Avenue and a point 45 metres west. 4. City Council prohibit stopping at all times on the north side of Strathmore Boulevard, between Donlands Avenue and a point 45 metres west. 5. City Council rescind the existing maximum one-hour parking regulation in effect from 10:00 a.m. to 6:00 p.m., on the south side of Strathmore Boulevard, between Donlands Avenue and point 52 metres west. 6. City Council prohibit stopping at all times on the south side of Strathmore Boulevard, between Donlands Avenue and a point 52 metres west. 7 City Council direct the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 8. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 9. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 10. City Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 11. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 12. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 13 City Council the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 14. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 15. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 16 City Council direct that Strathmore Boulevard be returned to pre-construction traffic and parking regulations when the project is complete.
Considered
2020-09-16 · Toronto and East York Community Council · adopted
Decision as filed
The Toronto and East York Community Council recommends that: 1. City Council authorize the closure of the north sidewalk on Strathmore Boulevard, from a point from a point 13 metres west of Donlands Avenue to a point 24 metres further west, from October 2, 2020 to December 31, 2020. 2. City Council authorize the closure of a 2 metre wide portion of the westbound curb lane on Strathmore Boulevard, from a point 13 metres west of Donlands Avenue to a point 24 metres further west, from October 2, 2020 to December 31, 2020.
Show the rest of Decision as filed, 2,978 more characters as filed
3. City Council rescind the existing parking prohibition in effect at all times on the north side Strathmore Boulevard, between Donlands Avenue and a point 45 metres west. 4. City Council prohibit stopping at all times on the north side of Strathmore Boulevard, between Donlands Avenue and a point 45 metres west. 5. City Council rescind the existing maximum one-hour parking regulation in effect from 10:00 a.m. to 6:00 p.m., on the south side of Strathmore Boulevard, between Donlands Avenue and point 52 metres west. 6. City Council prohibit stopping at all times on the south side of Strathmore Boulevard, between Donlands Avenue and a point 52 metres west. 7. City Council direct the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 8. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 9. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 10. City Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 11. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 12. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 13. City Council directe the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 14. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 15. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 16. City Council direct that Strathmore Boulevard be returned to pre-construction traffic and parking regulations when the project is complete.
2020-09-30 · Toronto City Council · adopted
On the record
More from this meeting
- Naming of an existing Public Lane north of Barton Avenue, extending between Pendrith Lane and Willowvale LaneFiled record
- Naming of an existing Public Lane west of Spadina Road, extending between Bantry Avenue and Heath Street WestFiled record
- 64-86 Bathurst Street - Zoning Amendment and Rental Housing Demolition Applications - Final ReportFiled record
- 125 The Esplanade - City Initiated Rezoning, Extension of Temporary Use By-law - Final ReportFiled record
- 117-119 St. George Street - Zoning Amendment Application - Final ReportFiled record
- 176-178 Front Street East and 33 Sherbourne Street - Zoning Amendment Application - Final ReportFiled record