Capital Project Management Process Review

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2021-06-16 · Board of Governors of Exhibition Place · adopted

As filed

The Board of Governors of Exhibition Place: 1. Received the report (June 2, 2021) from the Chief Executive Officer, Exhibition Place for information.

On the agenda

As the city filed it

In 2020, the Board engaged the City of Toronto Internal Audit to perform a review of the Capital Project Management Process. This operational review was part of the Boards overall risk assessment of operations, and covered the 2020 capital work plan. The Internal Audit Report from 2020 is attached as Appendix B to this report along with the highlights of the review and summarizes issues of the engagement, the auditor's suggestions and recommendations.

Show the rest of As the city filed it, 393 more characters as filed

Management has provided responses to the audit findings which will help to improve the overall accounting and internal control procedures. As part of the Boards continuing annual process to ensure that management actions have been effectively implemented staff will report back to the Board on the status of the recommendations (Appendix A) from City Internal Audit in the preceding year 2020.

Staff recommended

The Chief Executive Officer, Exhibition Place recommends that the Board: 1. Receive this report for information.