The filed record
2022 Rate Supported Budgets - Toronto Parking Authority
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2021-12-15 · Toronto City Council · adopted
As filed
City Council on December 15, 16 and 17, 2021, adopted the following: Operating and Capital Budgets 1. City Council approve the 2022 Operating Budget for Toronto Parking Authority of $105.9 million gross, $120.3 million revenue and ($14.4 million) net for the following services: Service: Gross Expenditures ($000s) Revenue ($000s) Net Expenditures ($000s) On-Street Parking 10,256.7 45,793.2 (35,536.5) Off-Street Parking 85,235.1 66,389.6 18,845.5 Bike Share 10,407.9 8,118.4 2,289.5 Total Program Budget 105,899.7 120,301.2 (14,401.4) 2.
Show the rest of As filed, 2,265 more characters as filed
City Council approve the 2022 staff complement for Toronto Parking Authority of 326.5 operating positions. 3. City Council approve 2022 Capital Budget for Toronto Parking Authority with cash flows and future year commitments totaling $132.6 million as detailed by project in Appendix 6a to the 2022 Staff Recommended Capital and Operating Budget Notes - Toronto Parking Authority. 4. City Council approve the 2023-2031 Capital Plan for Toronto Parking Authority totalling $68.9 million in project estimates as detailed by project in Appendix 6b to the 2022 Staff Recommended Capital and Operating Budget Notes - Toronto Parking Authority. 5. City Council direct the Chief Financial Officer and Treasurer, in consultation with the President, Toronto Parking Authority, to report to the Budget Committee on an updated Income Sharing Renewal Agreement no later than December 31, 2022. 6. City Council request that all sub-projects with third party financing be approved conditionally, subject to the receipt of such financing in 2022 and if such funding is not forthcoming, their priority and funding be reassessed by City Council relative to other City-financed priorities and needs. Service Levels 7. City Council approve the 2022 service levels for Toronto Parking Authority as outlined in Appendix 1 to the report (November 3, 2021) from the President, Toronto Parking Authority. 8. City Council direct that Confidential Attachment 1 to the report (September 10, 2021) from the President, Toronto Parking Authority remain confidential in its entirety as it pertains to personal matters about identifiable individuals, including municipal or local board employees, and labour relations or employee negotiations, and the security of property belonging to the City or one of its agencies or corporations. Confidential Attachment 1 to the report (September 10, 2021) from the President, Toronto Parking Authority remains confidential in its entirety in accordance with the provisions of the City of Toronto Act, 2006, as it pertains to personal matters about identifiable individuals, including municipal or local board employees, and labour relations or employee negotiations, and the security of property belonging to the City or one of its agencies or corporations.
On the agenda
As the city filed it
This report provides the recommended 2022 Service Levels for Toronto Parking Authority in comparison to service levels planned and achieved from 2019 to 2021. Service levels have historically been presented in the Budget Notes for each Program/Agency for review by Budget Committee and approval by City Council. Beginning in 2020, as part of the budget modernization project, service levels were provided in a separate document
Show the rest of As the city filed it, 190 more characters as filed
in an effort to deliver a more efficient and simplified budget process that will create greater opportunities for public participation through inclusive and outcome focused budget materials.
Staff recommended
The Budget Committee recommends that: Operating and Capital Budgets 1. City Council approve the 2022 Operating Budget for Toronto Parking Authority of $105.9 million gross, $120.3 million revenue and ($14.4 million) net for the following services: Service: Gross Expenditures ($000s) Revenue ($000s) Net Expenditures ($000s) On-Street Parking 10,256.7 45,793.2 (35,536.5) Off-Street Parking 85,235.1 66,389.6 18,845.5 Bike Share 10,407.9 8,118.4 2,289.5 Total Program Budget 105,899.7 120,301.2 (14,401.4) 2.
Show the rest of Staff recommended, 1,805 more characters as filed
City Council approve the 2022 staff complement for Toronto Parking Authority of 326.5 operating positions. 3. City Council approve 2022 Capital Budget for Toronto Parking Authority with cash flows and future year commitments totaling $132.6 million as detailed by project in Appendix 6a to the 2022 Staff Recommended Capital and Operating Budget Notes - Toronto Parking Authority. 4. City Council approve the 2023-2031 Capital Plan for Toronto Parking Authority totalling $68.9 million in project estimates as detailed by project in Appendix 6b to the 2022 Staff Recommended Capital and Operating Budget Notes - Toronto Parking Authority. 5. City Council direct the Chief Financial Officer and Treasurer, in consultation with the President of Toronto Parking Authority, to report to the Budget Committee on an updated Income Sharing Renewal Agreement no later than December 31, 2022. 6. City Council request that all sub-projects with third party financing be approved conditionally, subject to the receipt of such financing in 2022 and if such funding is not forthcoming, their priority and funding be reassessed by City Council relative to other City-financed priorities and needs. Service Levels 7. City Council approve the 2022 service levels for Toronto Parking Authority as outlined in Appendix 1 to the report (November 3, 2021) from the President, Toronto Parking Authority. 8. City Council direct that Confidential Attachment 1 to the report (September 10, 2021) from the President, Toronto Parking Authority remain confidential in its entirety, as it pertains to personal matters about identifiable individuals, including municipal or local board employees, and labour relations or employee negotiations, and the security of property belonging to the City or one of its agencies or corporations.
Considered
2021-12-07 · Executive Committee · adopted
Decision as filed
The Executive Committee recommends that: Operating and Capital Budgets 1. City Council approve the 2022 Operating Budget for Toronto Parking Authority of $105.9 million gross, $120.3 million revenue and ($14.4 million) net for the following services: Service: Gross Expenditures ($000s) Revenue ($000s) Net Expenditures ($000s) On-Street Parking 10,256.7 45,793.2 (35,536.5) Off-Street Parking 85,235.1 66,389.6 18,845.5 Bike Share 10,407.9 8,118.4 2,289.5 Total Program Budget 105,899.7 120,301.2 (14,401.4) 2.
Show the rest of Decision as filed, 1,802 more characters as filed
City Council approve the 2022 staff complement for Toronto Parking Authority of 326.5 operating positions. 3. City Council approve 2022 Capital Budget for Toronto Parking Authority with cash flows and future year commitments totaling $132.6 million as detailed by project in Appendix 6a to the 2022 Staff Recommended Capital and Operating Budget Notes - Toronto Parking Authority. 4. City Council approve the 2023-2031 Capital Plan for Toronto Parking Authority totalling $68.9 million in project estimates as detailed by project in Appendix 6b to the 2022 Staff Recommended Capital and Operating Budget Notes - Toronto Parking Authority. 5. City Council direct the Chief Financial Officer and Treasurer, in consultation with the President, Toronto Parking Authority, to report to the Budget Committee on an updated Income Sharing Renewal Agreement no later than December 31, 2022. 6. City Council request that all sub-projects with third party financing be approved conditionally, subject to the receipt of such financing in 2022 and if such funding is not forthcoming, their priority and funding be reassessed by City Council relative to other City-financed priorities and needs. Service Levels 7. City Council approve the 2022 service levels for Toronto Parking Authority as outlined in Appendix 1 to the report (November 3, 2021) from the President, Toronto Parking Authority. 8. City Council direct that Confidential Attachment 1 to the report (September 10, 2021) from the President, Toronto Parking Authority remain confidential in its entirety as it pertains to personal matters about identifiable individuals, including municipal or local board employees, and labour relations or employee negotiations, and the security of property belonging to the City or one of its agencies or corporations.
2021-12-15 · Toronto City Council · adopted
On the record
More from this meeting
- Toronto Hydro Climate Action Plan and Next StepsFiled record
- Final Tax Design and Steps to Implement a Vacant Home Tax in TorontoFiled record
- 2022 Tax Supported Interim Operating and Capital Budget EstimatesFiled record
- City of Toronto Investment Report for the six month period ending June 30, 2021Filed record
- Property Taxes: 2022 Interim Levy By-LawFiled record