The decision
2021-05-05 · Toronto City Council · adopted
As filed
City Council on May 5 and 6, 2021, adopted the following: 1. City Council approve the proposed demolition of an existing Unrated building and the construction of the new building on lands known municipally as 10 Elm Avenue, in accordance with Section 42 of the Ontario Heritage Act, substantially in accordance with the plans and drawings prepared by MacLennan Jaunkalns Miller Architects, dated May 29, 2020 and the Heritage Impact Assessment prepared by ERA Architects dated February 9, 2021 and filed with the Senior Manager, Heritage Planning, Urban Design, City Planning, subject to the following conditions: a.
Show the rest of As filed, 2,380 more characters as filed
prior to the final Site Plan Approval for the property at 10 Elm Avenue, the owner shall: 1. provide a detailed Conservation Plan prepared by a qualified heritage consultant that is consistent with the conservation strategy set out in the Heritage Impact Assessment dated February 9, 2021, prepared by ERA Architects Inc., to the satisfaction of the Senior Manager, Heritage Planning, Urban Design, City Planning; 2. provide final site drawings substantially in accordance with the approved Conservation Plan required in Part 1.a.1. above to the satisfaction of the Senior Manager, Heritage Planning, Urban Design, City Planning; and 3. provide a Letter of Credit, including provision for upwards indexing, in a form and amount and from a bank satisfactory to the Senior Manager, Heritage Planning, Urban Design, City Planning, to secure all work included in the approved Conservation Plan; b. prior to the issuance of any permit for all or any part of the property at 10 Elm Avenue, including a heritage permit or a building permit, but excluding permits for repairs and maintenance and usual and minor works for the existing heritage building as are acceptable to the Senior Manager, Heritage Planning, Urban Design, City Planning, the owner shall: 1. provide final building permit drawings, including notes and specifications for the conservation and protective measures keyed to the approved Conservation Plan required in Part 1.a.1. above including a description of materials and finishes, to be prepared by the project architect and a qualified heritage consultant to the satisfaction of the Senior Manager, Heritage Planning, Urban Design, City Planning, consistent with the plans and elevations submitted by the applicant and prepared by MacLennan Jaunkalns Miller Architects, dated May 29, 2020 and the Heritage Impact Assessment prepared by ERA Architects Inc., dated February 9, 2021; and c. prior to the release of the Letter of Credit, as required in Part 1.a.3. above the owner shall: 1. provide a letter of substantial completion prepared and signed by a qualified heritage consultant confirming that the required conservation work has been completed in accordance with the approved Conservation Plan and that an appropriate standard of conservation has been maintained, all to the satisfaction of the Senior Manager, Heritage Planning, Urban Design, City Planning.
On the agenda
As the city filed it
This report recommends that City Council approve the demolition of an "Unrated" structure in the South Rosedale Heritage Conservation District (SRHCD) and approve the design of the replacement building in accordance with Section 42 (1) of the Ontario Heritage Act. The building proposed for demolition is a performing arts centre for the private elementary and secondary school known as Branksome Hall at 10 Elm Avenue. The proposed replacement building is a four-storey "Innovation Centre and Studio Theatre".
Show the rest of As the city filed it, 996 more characters as filed
The South Rosedale Heritage Conservation District Study allows for the demolition of "Unrated" buildings provided the replacements comply with the SRHCD Study guidelines for new buildings and comply with the Zoning By-law. The proposed building meets the general intent of the South Rosedale HCD Study's guidelines. It has been designed to transition from the school's contemporary Athletic and Wellness Centre on the other side of Mount Pleasant Road to the heritage buildings on the east side of Mount Pleasant Road and is considered to be compatible with its context within this part of the South Rosedale Heritage Conservation District. The proposal also includes the repair and restoration of the adjacent "Category B" building known as Hollydene. The subject application also requires approval under the Planning Act (Minor Variance and Site Plan Control) and therefore the recommendations in this report relate solely to approvals required under the provisions of the Ontario Heritage Act.
Staff recommended
The Senior Manager, Heritage Planning, Urban Design, City Planning recommends that: 1. City Council approve the proposed demolition of an existing Unrated building and the construction of the new building on lands known municipally as 10 Elm Avenue, in accordance with Section 42 of the Ontario Heritage Act, substantially in accordance with the plans and drawings prepared by MacLennan Jaunkalns Miller Architects, dated May 29, 2020 and the Heritage Impact Assessment prepared by ERA Architects dated February 9, 2021 and filed with the Senior Manager, Heritage Planning, subject to the following conditions: a.
Show the rest of Staff recommended, 2,217 more characters as filed
That prior to the final Site Plan Approval for the property at 10 Elm Avenue, the owner shall: 1. Provide a detailed Conservation Plan prepared by a qualified heritage consultant that is consistent with the conservation strategy set out in the Heritage Impact Assessment dated February 9, 2021, prepared by ERA Architects Inc., to the satisfaction of the Senior Manager, Heritage Planning. 2. Provide final site drawings substantially in accordance with the approved Conservation Plan required in Recommendation 1.a.1 to the satisfaction of the Senior Manager, Heritage Planning. 3. Provide a Letter of Credit, including provision for upwards indexing, in a form and amount and from a bank satisfactory to the Senior Manager, Heritage Planning to secure all work included in the approved Conservation Plan. b. That prior to the issuance of any permit for all or any part of the property at 10 Elm Avenue, including a heritage permit or a building permit, but excluding permits for repairs and maintenance and usual and minor works for the existing heritage building as are acceptable to the Senior Manager, Heritage Planning, the owner shall: 1. Provide final building permit drawings, including notes and specifications for the conservation and protective measures keyed to the approved Conservation Plan required in Recommendation 1.a.1. including a description of materials and finishes, to be prepared by the project architect and a qualified heritage consultant to the satisfaction of the Senior Manager, Heritage Planning, consistent with the plans and elevations submitted by the applicant and prepared by MacLennan Jaunkalns Miller Architects, dated May 29, 2020 and the Heritage Impact Assessment prepared by ERA Architects, dated February 9, 2021. c. That prior to the release of the Letter of Credit, as required in recommendation 1.a.3 the owner shall: 1. Provide a letter of substantial completion prepared and signed by a qualified heritage consultant confirming that the required conservation work has been completed in accordance with the approved Conservation Plan and that an appropriate standard of conservation has been maintained, all to the satisfaction of the Senior Manager, Heritage Planning.
Considered
2021-04-21 · Toronto and East York Community Council · adopted
Decision as filed
The Toronto and East York Community Council recommends that: 1. City Council approve the proposed demolition of an existing Unrated building and the construction of the new building on lands known municipally as 10 Elm Avenue, in accordance with Section 42 of the Ontario Heritage Act, substantially in accordance with the plans and drawings prepared by MacLennan Jaunkalns Miller Architects, dated May 29, 2020 and the Heritage Impact Assessment prepared by ERA Architects dated February 9, 2021 and filed with the Senior Manager, Heritage Planning, Urban Design, City Planning subject to the following conditions: a.
Show the rest of Decision as filed, 2,415 more characters as filed
That prior to the final Site Plan Approval for the property at 10 Elm Avenue, the owner shall: 1. Provide a detailed Conservation Plan prepared by a qualified heritage consultant that is consistent with the conservation strategy set out in the Heritage Impact Assessment dated February 9, 2021, prepared by ERA Architects Inc., to the satisfaction of the Senior Manager, Heritage Planning, Urban Design, City Planning. 2. Provide final site drawings substantially in accordance with the approved Conservation Plan required in Recommendation 1.a.1 above to the satisfaction of the Senior Manager, Heritage Planning, Urban Design, City Planning. 3. Provide a Letter of Credit, including provision for upwards indexing, in a form and amount and from a bank satisfactory to the Senior Manager, Heritage Planning, Urban Design, City Planning, to secure all work included in the approved Conservation Plan. b. That prior to the issuance of any permit for all or any part of the property at 10 Elm Avenue, including a heritage permit or a building permit, but excluding permits for repairs and maintenance and usual and minor works for the existing heritage building as are acceptable to the Senior Manager, Heritage Planning, Urban Design, City Planning, the owner shall: 1. Provide final building permit drawings, including notes and specifications for the conservation and protective measures keyed to the approved Conservation Plan required in Recommendation 1.a.1. above including a description of materials and finishes, to be prepared by the project architect and a qualified heritage consultant to the satisfaction of the Senior Manager, Heritage Planning, Urban Design, City Planning, consistent with the plans and elevations submitted by the applicant and prepared by MacLennan Jaunkalns Miller Architects, dated May 29, 2020 and the Heritage Impact Assessment prepared by ERA Architects Inc., dated February 9, 2021. c. That prior to the release of the Letter of Credit, as required in Recommendation 1.a.3 above the owner shall: 1. Provide a letter of substantial completion prepared and signed by a qualified heritage consultant confirming that the required conservation work has been completed in accordance with the approved Conservation Plan and that an appropriate standard of conservation has been maintained, all to the satisfaction of the Senior Manager, Heritage Planning, Urban Design, City Planning.
2021-05-05 · Toronto City Council · adopted
On the record
More from this meeting
- Permanent Closure to Vehicular Traffic, the North-South Public Lane west of Augusta Avenue, between Richmond Street West and Queen Street WestFiled record
- Naming of an existing Public Lane located west of Salem Avenue, south of Shanly StreetFiled record
- Naming of an existing Public Lane in the Block bounded by Harbord Street, Montrose Avenue and Crawford StreetFiled record
- 646-648 Dufferin Street and 1-3 Boland Lane - Official Plan Amendment and Zoning Amendment Application - Final ReportFiled record
- 1494-1502 Dundas Street West - Zoning Amendment Final ReportFiled record
- 40-56 Harbord Street - Official Plan and Zoning Amendment Application - Final ReportFiled record