Construction Staging Area - 160 Front Street West (Simcoe Street) Underground Tunnel
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2021-06-24 · Toronto and East York Community Council · adopted
As filed
The Toronto and East York Community Council: 1. Authorized the closure of the east sidewalk, west sidewalk and all of Simcoe Street, between Front Street West and a point 70 metres north, from, August 20, 2021 to January 30, 2023. 2. Authorized the closure of the eastbound curb lane on Wellington Street West between Simcoe Street and John Street, from, August 20, 2021 to January 30, 2023. 3. Designated Wellington Street West, between Simcoe Street and John Street as one-way for westbound traffic only at all times.
Show the rest of As filed, 2,231 more characters as filed
4. Prohibited southbound left turns and northbound right turns at all times, at the intersection of John Street and Wellington Street West. 5. Directed the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 6. Directed the applicant to ensure that the existing sidewalks and/or any proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 7. Directed the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 8. Directed the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 9. Directed the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 10. Directed the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 11. Directed the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 12. Directed the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 13. Directed that Simcoe Street, Wellington Street West and John Street be returned to its pre-construction traffic regulations when the project is complete.
On the agenda
As the city filed it
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. PCL Constructors Canada Incorporated, is constructing an underground pedestrian tunnel under Simcoe Street that will connect 160 Front Street West to 200 Front Street West as part of the new building being constructed at 160 Front Street West (also known as 156-174 Front Street West and 43-51 Simcoe Street).
Show the rest of As the city filed it, 1,454 more characters as filed
In order to facilitate the construction of the underground tunnel, Simcoe Street between Front Street West and Wellington Street West will be closed to vehicular traffic. Transportation Services is requesting authorization to close the entire roadway of Simcoe Street including the east side and west side sidewalks, between Front Street West and a point 70 metres north, for a period of 17 months (i.e., August 20, 2021 to January 30, 2023) to accommodate the construction of the underground tunnel. Pedestrian movements on the east side of Simcoe Street will be restricted and pedestrians will be directed to a pedestrian walkway, located on private property, on the west side of Simcoe Street. Traffic lanes on Simcoe Street, abutting the site, will be restricted. However, bike lanes for both northbound and southbound cyclists will be maintained at all times throughout the project. In addition, it is recommended that the eastbound curb lane on Wellington Street West, between Simcoe Street and John Street be closed for a period of 17 months (i.e., August 20, 2021 to January 30, 2023). This closure was deemed the most appropriate way to ensure eastbound vehicles do not become trapped at the intersection of Simcoe Street and Wellington Street West due to the closure, the existing one-way southbound operation of Simcoe Street north of Wellington Street West, and the one-way westbound operation of Wellington Street West east of Simcoe Street.
Staff recommended
The Acting Director, Traffic Management, Transportation Services, recommends that: 1. Toronto and East York Community Council authorize the closure of the east sidewalk, west sidewalk and all of Simcoe Street, between Front Street West and a point 70 metres north, from, August 20, 2021 to January 30, 2023. 2. Toronto and East York Community Council authorize the closure of the eastbound curb lane on Wellington Street West between Simcoe Street and John Street, from, August 20, 2021 to January 30, 2023.
Show the rest of Staff recommended, 2,778 more characters as filed
3. Toronto and East York Community Council designate Wellington Street West, between Simcoe Street and John Street as one-way for westbound traffic only at all times. 4. Toronto and East York Community Council prohibit southbound left turns and northbound right turns at all times, at the intersection of John Street and Wellington Street West. 5. Toronto and East York Community Council direct the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 6. Toronto and East York Community Council direct the applicant to ensure that the existing sidewalks and/or any proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 7. Toronto and East York Community Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 8. Toronto and East York Community Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 9. Toronto and East York Community Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 10. Toronto and East York Community Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 11. Toronto and East York Community Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 12. Toronto and East York Community Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 13. Toronto and East York Community Council direct that Simcoe Street, Wellington Street West and John Street be returned to its pre-construction traffic regulations when the project is complete.
On the record
More from this meeting
- Permanent Closure of the Public Lane at the Rear of 2104-2110 Yonge StreetFiled record
- Naming of a Private Drive for a Development at 23 Spadina AvenueFiled record
- Naming of an existing Public Lane south of Mansfield Avenue, extending between Manning Avenue and Claremont StreetFiled record
- 33-49 Avenue Road and 136-148 Yorkville Avenue - Zoning Amendment Application - Final ReportFiled record
- 316-320 Dupont Street - Zoning Amendment Application - Final ReportFiled record
- 73 Queen's Park Crescent East - Official Plan and Zoning Amendment Application - Final ReportFiled record