Toronto Zoo Community Conservation Campus - Project Budget and Design Fee Increase
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2021-10-07 · Board of Management of the Toronto Zoo · adopted
As filed
The Board of Management of the Toronto Zoo: 1. Approved an increase in the construction budget for the Community Conservation Campus from $18 million to $28 million with the understanding that the additional budget will be supported through the existing 10-year capital plan, the Toronto Zoo Wildlife Conservancy and external funding partners. 2. Approved an increase in the contract value with Zeidler Architect Inc., of
Show the rest of As filed, 362 more characters as filed
$1,25 million to a total of up to $2,85 million to including fees, disbursements, 10 percent contingency and all applicable taxes to covers the additional design fees associated with a higher construction budget, as well as the design fees to revise the scope to accommodate potential partners, future opportunities and new learnings gained thought the pandemic.
On the agenda
As the city filed it
This report recommends increasing the scope of architectural, engineering and contract administration services for the Front Entrance and Welcome Area Project Toronto Zoo Community Conservation Campus.
Staff recommended
The Chief Executive Officer recommends that: 1. The Board of Management approve an increase in the construction budget for the Community Conservation Campus from $18 million to $28 million with the understanding that the additional budget will be supported through the existing 10-year capital plan, the Toronto Zoo Wildlife Conservancy and external funding partners. 2. The Board of Management approve an increase in the
Show the rest of Staff recommended, 409 more characters as filed
contract value with Zeidler Architect Inc., of $1,25 million to a total of up to $2,85 million to including fees, disbursements, 10 percent contingency and all applicable taxes to covers the additional design fees associated with a higher construction budget, as well as the design fees to revise the scope to accommodate potential partners, future opportunities and new learnings gained thought the pandemic.
On the record
More from this meeting
- Animal Welfare PresentationFiled record
- Toronto Zoo and COVID-19 UpdateFiled record
- Attendance and Revenue - August 2021Filed record
- 2021 Six-Month Health and Safety StatusFiled record
- 2021 Six-Month Guest SafetyFiled record
- 2020 Environmental InitiativesFiled record