The Public GalleryToronto

Executive Committee · 2022-07-12 · 2022.EX34.15

The filed record

Capital Variance Report for the Four Months Ended April 30, 2022

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2022-07-19 · Toronto City Council · amended

As filed

City Council on July 19, 20, 21 and 22, 2022, adopted the following: 1. City Council approve in-year budget adjustments to the 2022-2031 Approved Capital Budget and Plan as detailed in Appendix 4 to the report (June 27, 2022) from the Chief Financial Officer and Treasurer. 2. City Council amend the 2022-2031 Approved Capital Budget and Plan for Parks, Forestry and Recreation for the Bellbury Park Improvements sub-project in the Park Development project by: a.

Show the rest of As filed, 1,962 more characters as filed

increasing the total project cost by $156,000 from $300,000 to $456,000, with cash flow funding in 2022, fully funded by Section 42 Above 5 percent Cash-in-lieu generated from the following developments in proximity to the site, for the purpose of awarding a contract for improvements to Bellbury Park; and Development Location Internal Order Account (XR2213) Amount ($) 2775 Don Mills Road 4200677 $2,965.38 1 Marowyne Drive 4201369 $10.17 11-21 Allenbury Gardens 4201501 $153,024.45 Total $156,000.00 b. accelerating the cash flow commitments of $270,000 in 2024 to 2022, with funding from the Section 42 Above 5 percent Cash-in-lieu generated from 1 Adra Villaway (Source Account: XR2213- 4201357), for a total amended 2022 cash flow of $426,000 for improvements to Bellbury Park to proceed in 2022. 3. City Council amend the 2022-20231 Approved Capital Budget and Plan for Parks, Forestry and Recreation's for the Clydesdale Tennis Clubhouse Improvement sub-project in the Outdoor Recreation Centres project, in the amount of $618,000, by increasing the total project cost from $582,000 to $1,200,000, with cash flow commitments in 2023, fully funded from the following sources that have been received and are eligible for improvements to the Tennis Clubhouse in Clydesdale Park: $324,000 from Section 42 First 5 percent North District Parkland Development Cash-in-lieu Reserve Fund (XR2207) and $294,000 from the two Section 42 Above 5 percent Cash-in-lieu sources noted in the chart below: Development Location Internal Order Account (XR2213) Amount ($) 2205 Sheppard Avenue East 4200136 $263,846.32 2135 Sheppard Avenue East 4201066 $30,153.68 Total $294,000.00 4. City Council increase the 2022 Capital Budget for the Toronto Transit Commission by $3.152 million gross and $0 debt to undertake the Kennedy Station Infrastructure Relocation capital project for the Scarborough Subway Extension, with the total project cost to be fully funded by Metrolinx.

The vote

Adopt Item as Amended · Carried, 20-0

Absent (5)Cynthia Lai, Denzil Minnan-Wong, John Tory, Josh Matlow, Paula Fletcher
The whole record, all 25 members

Every name opens that member’s record.

On the agenda

As the city filed it

The purpose of this report is to provide City Council with the City of Toronto capital spending for the four month period ended April 30, 2022, as well as projected expenditures to December 31, 2022. Furthermore, this report seeks Council's approval for in-year budget adjustments to the 2022 Approved Capital Budget and Plan. Table 1 below summarizes the City's 2022 actual capital expenditures compared with the 2022 approved capital budget for the period ended April 30, 2022 as well as the projected expenditures by December 31, 2022.

Show the rest of As the city filed it, 4,543 more characters as filed

Table 1 : Capital Variance Summary Table 1 Corporate Capital Variance Summary for the Period Ended April 30, 2022 2022 Approved Budget* 2022 4M Actual Expenditures 2022 Projected YE Expenditures $M $M % $M % City Operations 2,089 243 11.6% 1,555 74.4% Agencies 1,851 255 13.8% 1,562 84.4% Tax Supported: 3,940 497 12.6% 3,117 79.1% Rate Supported: 1,555 171 11.0% 1,282 82.4% TOTAL 5,495 669 12.2% 4,400 80.1% * Note: Includes 2021 carry forward funding The City's actual capital spending in the first four months is $668.8 million or 12.2% of the approved capital budget of the year. The projected spending rate of the year is 80.1% by year-end. Both the year-to-date spending and the year-end projection reflect the capital spending impacts resulting from paused 2022 capital projects, pending confirmation of full 2022 COVID-19 support funding from the federal and provincial governments, to ensure the City maintains a balanced 2022 Operating Budget while addressing the financial impacts continuing to arise from the pandemic. Potential impact from the inter-governmental funding shortfall The City continues to actively engage with Federal and Provincial counterparts at all levels to secure continued COVID-19 funding support. From March 2020 to year-end 2021, the City has benefited from nearly $2.9 billion in COVID-19 related emergency funding commitments from the federal and provincial governments, with additional estimated $525 million in funding support in 2022.The remaining 2022 COVID-19 related funding gap is currently estimated to be $875 million, however the gap decreases to $815 million if the City receives the continued full reimbursement of public health costs. In the event that continued COVID-19 funding is not forthcoming or adequate to fully address the financial impacts arising from the pandemic, the City's capital program will be materially impacted. In such case, a draw of up to $515 million from the City's COVID-19 Backstop and a $300 million reduction to the 2022 Capital Budget would be required to ensure the City maintains a balanced 2022 Operating Budget while addressing the financial impacts continuing to arise from the pandemic. Delays in receiving funding commitments will continue to impact the City's ability to award and deliver capital projects in 2022. Programs and Agencies have already begun preparing for the potential reduction to their capital budgets, and at this stage have identified or committed a total of $260 million of projects that are either paused or can be reduced as a result of 2022 underspending. Below are the main areas with the largest reductions accommodated (see appendix 6): - TTC plans to reduce a total of $87.0 million, and is in the process of compiling a final list of capital projects which will be directly impacted, based on the $241.7 million in total projected 2022 underspending as detailed in Appendix 5. - Transportation Services has identified $87.0 million in 2022 projected underspending based on paused capital projects, mainly impacting transportation infrastructure rehabilitation projects. Projected underspending by project is detailed in Appendix 6. - Corporate Real Estate Management has identified $34.2 million in reductions on capital projects, mainly impacting state of good repair projects across various locations. - Parks, Forestry and Recreation has identified $27.7 million in reductions on capital projects, mainly impacting park site rehabilitation and state of good repair projects for various buildings and structures. High inflation and global supply chain challenges continue to increase the cost escalation on capital project delivery. As well, a steep rise in prevailing interest rates has been increasing capital financing costs for new debt issuances. With the increasing financial pressure added to the uncertainty of the intergovernmental funding commitments, the projected spend rate continues to be impacted in 2022. Despite the challenges mentioned, the City will continue to plan annual capital projects in line with both affordability and achievability, based on the historical actual capacity and in consideration of emerging challenges such as inflationary impacts and supply chain disruptions. The strategy is to build on improvements experienced to date and improve the capital spend rate in future years; fully utilizing approved funding and enabling any excess funding capacity to support additional capital priorities, while promoting realistic capacity to spend in light of external factors and challenges.

Staff recommended

The Chief Financial Officer and Treasurer recommends that: 1. City Council approve in-year budget adjustments to the 2022-2031 Approved Capital Budget and Plan as detailed in Appendix 4.

Considered

  • 2022-07-12 · Executive Committee · adopted

    Decision as filed

    The Executive Committee recommends that: 1. City Council approve in-year budget adjustments to the 2022-2031 Approved Capital Budget and Plan as detailed in Appendix 4 to the report (June 27, 2022) from the Chief Financial Officer and Treasurer.

  • 2022-07-19 · Toronto City Council · amended

On the record

The item as the City filed it

More from this meeting

The whole meeting