The filed record
Construction Staging Area - 25 Cordova Avenue and 60 Central Park Roadway
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2022-07-19 · Toronto City Council · adopted
As filed
City Council on July 19, 20, 21 and 22, 2022, adopted the following: 1. City Council authorize the closure of the east sidewalk and the northbound curb lane on Cordova Avenue, between Central Park Roadway and a point 104 metres further north and provision of a temporary pedestrian walkway within the closed portion of the northbound curb lane, from July 20, 2022 to April 30, 2025. 2. City Council authorize the closure of a 9.4 metre wide portion of the north side boulevard on Central Park Roadway, between Cordova Avenue and a point 63 metres further east and provision of a temporary pedestrian walkway within the closed portion of the boulevard, from July 20, 2022 to April 30, 2025.
Show the rest of As filed, 3,929 more characters as filed
3. City Council rescind the existing no parking prohibition in effect all times on the east side of Cordova Avenue, between Central Park Roadway (west intersection) and a point 104 metres northwest. 4. City Council rescind the existing no parking prohibition in effect all times on the north side of Central Park Roadway, between Cordova Avenue (west intersection) and a point 63 metres east. 5. City Council rescind the existing stopping prohibition in effect from 8:00 a.m. to 5:00 p.m., Monday to Friday, on the east side of Cordova Avenue, between Central Park Roadway (west intersection) and a point 61 metres northwest. 6. City Council prohibit stopping at all times on the east side of Cordova Avenue, between Central Park Roadway (west intersection) and a point 104 metres northwest. 7. City Council prohibit stopping at all times on the north side of Central Park Roadway, between Cordova Avenue (west intersection) and a point 63 metres east. 8. City Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 9. City Council direct the applicant to construct (as per the City's engineer approved specifications) and maintain a fully covered, protected and unobstructed walkway, compliant with the Accessibility for Ontarians with Disabilities Act, for all pedestrians, including for those with mobility devices for the entire duration of the construction staging area permit. 10. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 11. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 12. City Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 13. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 14. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 15. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 16. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 17. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 18. City Council direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes. 19. City Council direct that Cordova Avenue and Central Park Roadway be returned to their pre-construction traffic and parking regulations when the project is complete.
On the agenda
As the city filed it
As the Toronto Transit Commission (TTC) operates a transit service on Cordova Avenue, City Council approval of this report is required. Deltera Inc. is constructing 20-storey and 27-storey residential condominium buildings at 25 Cordova Avenue and 60 Central Park Roadway, respectively (previously known municipally as 15-19 Cordova Avenue). The site is located at the north-east corner of Cordova Avenue and Central Park Roadway.
Show the rest of As the city filed it, 327 more characters as filed
Transportation Services is requesting approval to close the east sidewalk and a portion of the northbound curb lane on Cordova Avenue and a portion of the boulevard allowance on the north side of Central Park Roadway for a period of 34 months, from July 20, 2022 to April 30, 2025 to facilitate construction staging operations.
Staff recommended
The Director, Traffic Management, Transportation Services, recommends that: 1. City Council authorize the closure of the east sidewalk and the northbound curb lane on Cordova Avenue, between Central Park Roadway and a point 104 metres further north and provision of a temporary pedestrian walkway within the closed portion of the northbound curb lane, from July 20, 2022 to April 30, 2025. 2. City Council authorize the closure of a 9.4 metre wide portion of the north side boulevard on Central Park Roadway, between Cordova Avenue and a point 63 metres further east and provision of a temporary pedestrian walkway within the closed portion of the boulevard, from July 20, 2022 to April 30, 2025.
Show the rest of Staff recommended, 3,918 more characters as filed
3. City Council rescind the existing no parking prohibition in effect all times on the east side of Cordova Avenue between Central Park Roadway (west intersection) and a point 104 metres northwest. 4. City Council rescind the existing no parking prohibition in effect all times on the north side of Central Park Roadway between Cordova Avenue (west intersection) and a point 63 metres east. 5. City Council rescind the existing stopping prohibition in effect from 8:00 a.m. to 5:00 p.m., Monday to Friday, on the east side of Cordova Avenue between Central Park Roadway (west intersection) and a point 61 metres northwest. 6. City Council prohibit stopping at all times on the east side of Cordova Avenue, between Central Park Roadway (west intersection) and a point 104 metres northwest. 7. City Council prohibit stopping at all times on the north side of Central Park Roadway, between Cordova Avenue (west intersection) and a point 63 metres east. 8. City Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 9. City Council direct the applicant to construct (as per the City's engineer approved specifications) and maintain a fully covered, protected and unobstructed walkway, compliant with the Accessibility for Ontarians with Disabilities Act, for all pedestrians, including for those with mobility devices for the entire duration of the construction staging area permit. 10. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 11. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 12. City Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 13. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 14. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 15. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 16. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 17. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 18. City Council direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes. 19. City Council direct that Cordova Avenue and Central Park Roadway be returned to their pre-construction traffic and parking regulations when the project is complete.
Considered
2022-06-27 · Etobicoke York Community Council · adopted
Decision as filed
The Etobicoke York Community Council recommends that: 1. City Council authorize the closure of the east sidewalk and the northbound curb lane on Cordova Avenue, between Central Park Roadway and a point 104 metres further north and provision of a temporary pedestrian walkway within the closed portion of the northbound curb lane, from July 20, 2022 to April 30, 2025. 2. City Council authorize the closure of a 9.4 metre wide portion of the north side boulevard on Central Park Roadway, between Cordova Avenue and a point 63 metres further east and provision of a temporary pedestrian walkway within the closed portion of the boulevard, from July 20, 2022 to April 30, 2025.
Show the rest of Decision as filed, 3,918 more characters as filed
3. City Council rescind the existing no parking prohibition in effect all times on the east side of Cordova Avenue between Central Park Roadway (west intersection) and a point 104 metres northwest. 4. City Council rescind the existing no parking prohibition in effect all times on the north side of Central Park Roadway between Cordova Avenue (west intersection) and a point 63 metres east. 5. City Council rescind the existing stopping prohibition in effect from 8:00 a.m. to 5:00 p.m., Monday to Friday, on the east side of Cordova Avenue between Central Park Roadway (west intersection) and a point 61 metres northwest. 6. City Council prohibit stopping at all times on the east side of Cordova Avenue, between Central Park Roadway (west intersection) and a point 104 metres northwest. 7. City Council prohibit stopping at all times on the north side of Central Park Roadway, between Cordova Avenue (west intersection) and a point 63 metres east. 8. City Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 9. City Council direct the applicant to construct (as per the City's engineer approved specifications) and maintain a fully covered, protected and unobstructed walkway, compliant with the Accessibility for Ontarians with Disabilities Act, for all pedestrians, including for those with mobility devices for the entire duration of the construction staging area permit. 10. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 11. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 12. City Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 13. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 14. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 15. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 16. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 17. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 18. City Council direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes. 19. City Council direct that Cordova Avenue and Central Park Roadway be returned to their pre-construction traffic and parking regulations when the project is complete.
2022-07-19 · Toronto City Council · adopted
On the record
More from this meeting
- 36 and 38 Fieldway Road - Zoning By-law Amendment Application - Final ReportFiled record
- 63 and 73 Widdicombe Hill Boulevard - Zoning By-law Amendment Application - Final ReportFiled record
- 801 The Queensway - Zoning By-law Amendment Application - Final ReportFiled record
- 900 to 940 The East Mall - Official Plan and Zoning By-law Amendment Applications - Final ReportFiled record
- 1956-1986 Weston Road and 1-5 Little Avenue - Official Plan, Zoning By-law Amendment and Rental Housing Demolition Applications - Final ReportFiled record
- Alteration to Heritage Properties and Authority to Enter into a Heritage Easement Agreement - 1974-1978 Weston Road, 1984-1986 Weston Road and 3-5 Little AvenueFiled record