The filed record
Expropriation of Properties for the Extension of Beecroft Road - Stage 1
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2022-06-15 · Toronto City Council · adopted
As filed
City Council on June 15 and 16, 2022, adopted the following: 1. City Council authorize the Executive Director, Corporate Real Estate Management, or their designate, to continue negotiations to acquire the Project Requirements, and, as Approving Authority, authorize the initiation of the expropriation proceedings for the Project Requirements for the purposes of constructing the Project and related ancillary works. 2. City
Show the rest of As filed, 447 more characters as filed
Council authorize the Executive Director, Corporate Real Estate Management, or their designate, to serve and publish the Notices of Application for Approval to Expropriate the Project Requirements, to forward to the Ontario Land Tribunal any requests for inquiries received, to attend to the hearing(s) to present the City of Toronto's position, and to report the recommendations of the Ontario Land Tribunal to City Council for its consideration.
On the agenda
As the city filed it
This report seeks authority to initiate expropriation proceedings to acquire fee simple interests from the properties municipally known as 2 Greenview Avenue, 4 Greenview Avenue, 6 Greenview Avenue, 18 Greenview Avenue, 22 Greenview Avenue, 24 Greenview Avenue, 36 Hendon Avenue, 38 Hendon Avenue, 41 Hendon Avenue and 5754 Yonge Street as set out in Appendix A and shown in the sketches set out at Appendix B (the "Project Requirements"), for the purpose of constructing the Beecroft Extension Project (the "Project").
Show the rest of As the city filed it, 1,060 more characters as filed
This is the first stage of the expropriation process. Should City Council adopt the recommendations in this report, City staff may serve and publish the Notice of Application for Approval to Expropriate on each registered owner. Owners, as defined in the Expropriations Act (the "Act"), will have 30 days to request a hearing into whether the City's proposed taking is fair, sound and reasonably necessary. City staff may report back to City Council with a Stage 2 Report, providing details on property values and other costs, and if a hearing is requested, the report of the Ontario Land Tribunal. The proposed expropriation would only be effected, after adoption by City Council as approving authority as defined in the Act ("Approving Authority") of the Stage 2 report, by registration of expropriation plans, which would then be followed by the service of notices as required by the Act. Before the City can take possession of the expropriated Project Requirements, offers of compensation based on appraisal reports must be served on each registered owner.
Staff recommended
The Executive Director, Corporate Real Estate Management recommends that: 1. City Council authorize the Executive Director, Corporate Real Estate Management, or their designate, to continue negotiations to acquire the Project Requirements, and, as Approving Authority, authorize the initiation of the expropriation proceedings for the Project Requirements for the purposes of constructing the Project and related ancillary works.
Show the rest of Staff recommended, 455 more characters as filed
2. City Council authorize the Executive Director, Corporate Real Estate Management, or their designate, to serve and publish the Notices of Application for Approval to Expropriate the Project Requirements, to forward to the Ontario Land Tribunal any requests for inquiries received, to attend to the hearing(s) to present the City of Toronto's position, and to report the recommendations of the Ontario Land Tribunal to City Council for its consideration.
Considered
2022-06-07 · General Government and Licensing Committee · adopted
Decision as filed
The General Government and Licensing Committee recommends that: 1. City Council authorize the Executive Director, Corporate Real Estate Management, or their designate, to continue negotiations to acquire the Project Requirements, and, as Approving Authority, authorize the initiation of the expropriation proceedings for the Project Requirements for the purposes of constructing the Project and related ancillary works. 2.
Show the rest of Decision as filed, 452 more characters as filed
City Council authorize the Executive Director, Corporate Real Estate Management, or their designate, to serve and publish the Notices of Application for Approval to Expropriate the Project Requirements, to forward to the Ontario Land Tribunal any requests for inquiries received, to attend to the hearing(s) to present the City of Toronto's position, and to report the recommendations of the Ontario Land Tribunal to City Council for its consideration.
2022-06-15 · Toronto City Council · adopted
On the record
More from this meeting
- Presentation on Annual Update on OMERS as it Relates to the City's Employer ContributionsFiled record
- Annual Update on Ontario Municipal Employees’ Retirement System as it relates to the City's Employer ContributionsFiled record
- Amendments to Retainer Agreement Purchase Order 6035311 with Osler, Hoskin & Harcourt LLP for Legal Services Related to Pension and Benefits IssuesFiled record
- Toronto Fire Department Superannuation and Benefit Fund - Funding Valuation Report as at December 31, 2021Filed record
- Administrative Penalty System - 2021 ActivityFiled record
- 2021 Annual Report Parking Enforcement Unit - Parking Ticket IssuanceFiled record