The filed record
Seeking Provincial Funding for the Construction of Riverine Flood Mitigation for the Rockcliffe-Smythe Area - by Councillor Frances Nunziata, seconded by Mayor John Tory
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2022-04-06 · Toronto City Council · adopted
As filed
City Council on April 6 and 7, 2022 adopted the following: 1. City Council direct the City Manager to review opportunities and initiate a request for funding from the Province along with funding from the Federal government, to support the recommendations identified in the Rockcliffe Riverine Flood Mitigation Environmental Assessment Project. 2. City Council request the General Manager, Transportation Services and the
Show the rest of As filed, 419 more characters as filed
General Manager, Toronto Water to work with the Chief Executive Officer, Toronto and Region Conservation Authority to finalize an implementation phasing plan to optimize the order in which each infrastructure component as part of the preferred Rockcliffe Riverine Flood Mitigation Project solution should be built, subject to available funding and the completion of the Municipal Class Environmental Assessment process.
The vote
Adopt Item · Carried, 25-0
The whole record, all 26 members
- Ana BailãoFor
- Anthony PerruzzaFor
- Brad BradfordFor
- Cynthia LaiAbsent
- Denzil Minnan-WongFor
- Frances NunziataFor
- Gary CrawfordFor
- Gord PerksFor
- James PasternakFor
- Jaye RobinsonFor
- Jennifer McKelvieFor
- Joe CressyFor
- John FilionFor
- John ToryFor
- Josh MatlowFor
- Kristyn Wong-TamFor
- Mark GrimesFor
- Michael FordFor
- Michael ThompsonFor
- Mike ColleFor
- Mike LaytonFor
- Nick MantasFor
- Paul AinslieFor
- Paula FletcherFor
- Shelley CarrollFor
- Stephen HolydayFor
Every name opens that member’s record.
On the agenda
As the city filed it
The Rockcliffe-Smythe area is located in Ward 5 (York South-Weston) and is the most flood vulnerable area in the Toronto and Region Conservation Authority's jurisdiction. There are hundreds of buildings within the regulatory floodplain of Black Creek and Lavender Creek; many of these properties experience frequent surface and basement flooding during severe storms. This is a result of riverine flooding and the overloading of the City of Toronto's urban drainage system.
Show the rest of As the city filed it, 2,193 more characters as filed
The City of Toronto, in partnership with the Toronto and Region Conservation Authority, is working to implement a flood mitigation strategy for the area adjacent to Black Creek through the Rockcliffe Riverine Flood Mitigation Project Municipal Class Environmental Assessment launched on January 21, 2021 and currently underway. On March 1, 2022 the City and the Toronto and Region Conservation Authority held the second of two Public Information Centres for the Rockcliffe Riverine Flood Mitigation Project Environmental Assessment. At the Public Information Centres, the City and the Toronto and Region Conservation Authority provided an update on the project, the preferred solution, alternative design concepts, and project next steps. The preferred solution involves significant infrastructure investment to modify the Black Creek and Lavender Creek Channels, construct a new flood protection wall, road realignment as well as several bridge replacements. If approved, the entire project would be constructed in phases over an anticipated 10-year timeframe with an estimated cost of approximately $371 million. Community members expressed an urgent need for the project to be fully funded in order for construction to proceed and reduce the risk of flooding in this area, and better adapt to a changing climate. Councillor Nunziata has championed the Rockcliffe Riverine Flood Mitigation Project with support from Mayor John Tory. The City has applied for approximately $148 Million from the Federal Disaster Mitigation Adaptation Fund for this project and to-date has received commitment for approximately $19 million from the Federal government through this fund. Later this year, the City anticipates hearing back on additional Federal Disaster Mitigation Adaptation Fund funding applications. The Honourable Ahmed Hussen, Federal Member of Parliament for York South Weston has expressed support for opportunities for additional funding commitment from the Federal government for this project. Given the scale of the project investment needed and the priority of this project, this motion asks that Council direct the City Manager to seek funding support from the Provincial government.
Staff recommended
Councillor Frances Nunziata, seconded by Mayor John Tory, recommends that: 1. City Council direct the City Manager to review opportunities and initiate a request for funding from the Province along with funding from the Federal government, to support the recommendations identified in the Rockcliffe Riverine Flood Mitigation Environmental Assessment Project. 2. City Council request the General Manager, Transportation Services
Show the rest of Staff recommended, 427 more characters as filed
and the General Manager, Toronto Water to work with the Chief Executive Officer, Toronto and Region Conservation Authority to finalize an implementation phasing plan to optimize the order in which each infrastructure component as part of the preferred Rockcliffe Riverine Flood Mitigation Project solution should be built, subject to available funding and the completion of the Municipal Class Environmental Assessment process.
On the record
More from this meeting
- Introduction and Enactment of General Bills and Confirming BillsFiled record
- Transmittal of Toronto Transit Commission Update on Cross-Boundary Service IntegrationFiled record
- Supporting the Bloor-Yorkville Business Improvement Area Purchase of New Seating in the Village of Yorkville Park - by Councillor Mike Layton, seconded by Councillor Kristyn Wong-TamFiled record
- Call to OrderFiled record
- Office of the Integrity Commissioner - 2021 Annual ReportFiled record
- Authorization to enter into a Licence Agreement with The Neighbourhood Group Community Services and Aki Wiidookaagewin (Earth Helpers) at Paul Martel Park - by Councillor Mike Layton, seconded by Councillor Kristyn Wong-TamFiled record