294-298 Sherbourne Street - Official Plan Amendment, Zoning Amendment Applications - Request for Direction Report
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2022-03-09 · Toronto City Council · adopted
As filed
City Council on March 9, 2022, adopted the following: 1. City Council direct the City Solicitor and appropriate City staff to attend the Ontario Land Tribunal in opposition to the Official Plan Amendment and Zoning By-law Amendment appeals for the lands at 294-298 Sherbourne Street and to continue discussions with the owner in an attempt to resolve outstanding issues. 2. In the event that the Ontario Land Tribunal allows the appeals in whole or in part, City Council authorize the City Solicitor to request that the issuance of any final Order(s) be withheld until such time as the City Solicitor advises that: a.
Show the rest of As filed, 1,107 more characters as filed
the proposed Official Plan and Zoning By-law Amendments are in a final form satisfactory to the Chief Planner and Executive Director, City Planning and the City Solicitor; b. the Ontario Land Tribunal has been advised by the City Solicitor that the Functional Servicing Report, Stormwater Management Report, Hydrogeological Report and Groundwater Report has been completed to the satisfaction of the Executive Director Engineering and Construction Services; and c. the owner has entered into the appropriate agreement(s) with the City for the design, construction and financial securities for any improvements to the municipal infrastructure, in connection with a Functional Servicing Report as accepted by the City's Executive Director, Engineering and Construction Services should such Director determine that improvements to such infrastructure are required, to support the development, all to the satisfaction of the Executive Director of Engineering and Construction Services. 3. City Council authorize the City Solicitor and City staff to take any necessary steps to implement City Council's decision.
On the agenda
As the city filed it
On July 2, 2021, Official Plan and Zoning By-law Amendment application were submitted to permit a 10-storey residential building within a protected Neighbourhoods land use designation and within a designated Heritage Conservation District at 294-298 Sherbourne Street. The Official Plan and Zoning By-law Amendment application were deemed complete on September 13, 2021. On January 14, 2022, the applicant appealed the applications to the Ontario Land Tribunal (OLT) due to Council not making a decision within the 120-day time frame under the Planning Act.
Show the rest of As the city filed it, 225 more characters as filed
This report recommends that the City Solicitor with the appropriate City staff attend the OLT hearing to oppose the application in its current form and to continue discussions with the applicant to resolve outstanding issues.
Staff recommended
The City Planning Division recommends that: 1. City Council direct the City Solicitor and appropriate City staff to attend the Ontario Land Tribunal in opposition to the Official Plan Amendment and Zoning By-law Amendment appeals for the lands at 294-298 Sherbourne Street and to continue discussions with the owner in an attempt to resolve outstanding issues. 2. In the event that the Ontario Land Tribunal allows the appeals in whole or in part, City Council authorize the City Solicitor to request that the issuance of any final Order(s) be withheld until such time as the City Solicitor advises that: a.
Show the rest of Staff recommended, 1,106 more characters as filed
the proposed Official Plan and Zoning By-law Amendments are in a final form satisfactory to the Chief Planner and Executive Director, City Planning and the City Solicitor; b. The Ontario Land Tribunal has been advised by the City Solicitor that the Functional Servicing Report, Stormwater Management Report, Hydrogeological Report and Groundwater Report has been completed to the satisfaction of the Executive Director Engineering and Construction Services; c. The owner has entered into the appropriate agreement(s) with the City for the design, construction and financial securities for any improvements to the municipal infrastructure, in connection with a Functional Servicing Report as accepted by the City's Executive Director Engineering and Construction Services should such Director determine that improvements to such infrastructure are required, to support the development, all to the satisfaction of the Executive Director of Engineering and Construction Services; and 3. City Council authorize the City Solicitor and City staff to take any necessary steps to implement City Council's decision.
Considered
2022-02-16 · Toronto and East York Community Council · adopted
Decision as filed
The Toronto and East York Community Council recommends that: 1. City Council direct the City Solicitor and appropriate City staff to attend the Ontario Land Tribunal in opposition to the Official Plan Amendment and Zoning By-law Amendment appeals for the lands at 294-298 Sherbourne Street and to continue discussions with the owner in an attempt to resolve outstanding issues. 2. In the event that the Ontario Land Tribunal allows the appeals in whole or in part, City Council authorize the City Solicitor to request that the issuance of any final Order(s) be withheld until such time as the City Solicitor advises that: a.
Show the rest of Decision as filed, 1,108 more characters as filed
the proposed Official Plan and Zoning By-law Amendments are in a final form satisfactory to the Chief Planner and Executive Director, City Planning and the City Solicitor; b. The Ontario Land Tribunal has been advised by the City Solicitor that the Functional Servicing Report, Stormwater Management Report, Hydrogeological Report and Groundwater Report has been completed to the satisfaction of the Executive Director Engineering and Construction Services; c. The owner has entered into the appropriate agreement(s) with the City for the design, construction and financial securities for any improvements to the municipal infrastructure, in connection with a Functional Servicing Report as accepted by the City's Executive Director Engineering and Construction Services should such Director determine that improvements to such infrastructure are required, to support the development, all to the satisfaction of the Executive Director of Engineering and Construction Services; and 3. City Council authorize the City Solicitor and City staff to take any necessary steps to implement the above recommendations.
2022-03-09 · Toronto City Council · adopted
On the record
More from this meeting
- Naming of an existing Public Lane north of Dundas Street West, extending between Dovercourt Road and Coolmine RoadFiled record
- Naming of an existing Public Lane north of Gerrard Street East, extending easterly from Leslie StreetFiled record
- Permanent Closure of a Stratified Parcel of Public Lane Located to the West of 375 Queen Street WestFiled record
- 340-376R Dufferin Street and 2 Melbourne Avenue -Official Plan Amendment and Zoning By-law Amendment Application - Final ReportFiled record
- 72 Perth Avenue - Zoning Amendment Application - Final ReportFiled record
- 287 Davenport Road and 141, 143 and 145 Bedford Road - Rental Housing Demolition Application - Final ReportFiled record