Construction Staging Area Time Extension and Traffic Amendments - 524 Oakwood Avenue

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2022-02-16 · Toronto and East York Community Council · adopted

As filed

The Toronto and East York Community Councilt: 1. Authorized the continuation of the closure of a portion of the public laneway, between Eleanor Avenue and a point 31.5 metres south, from February 17, 2022 to July 31, 2022. 2. Authorized the implementation of two-way traffic operations on Amherst Avenue, between Oakwood Avenue and the lane first west of Oakwood Avenue, from February 17, 2022 to July 31, 2022. 3. Prohibited stopping at all times on the north side of Amherst Avenue, between Oakwood Avenue and the lane first west of Oakwood Avenue.

Show the rest of As filed, 1,522 more characters as filed

4. Directed the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 5. Directed the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 6. Directed the applicant to continue providing a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 7. Directed the applicant to continue providing a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 8. Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 9. Directed that the public laneway and Amherst Avenue be returned to pre-construction traffic and parking regulations when the project is complete.

On the agenda

As the city filed it

This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. The Dalton Company Ltd. is renovating the existing community arts centre (Nia Centre for the Arts Incorporated) at 524 Oakwood Avenue. A portion of the north-south public laneway at the north end of the site is currently closed to accommodate construction staging operations for the renovations.

Show the rest of As the city filed it, 1,031 more characters as filed

Toronto and East York Community Council, at its meeting on December 2, 2020, authorized the subject construction staging area from January 4, 2021 to August 31, 2021. Transportation Services is requesting authorization to extend the duration of the construction staging area on the public laneway for an additional five months, from February 17, 2022 to July 31, 2022, to allow for the construction of the development to be completed. It should be noted that during the lapse in approval period, the site has been operating under a monthly Street Occupation Permit. The developer has requested an extension of the duration of the construction staging area on the public laneway, as the site has experienced a number of construction delays. Additionally, authorization is requested to temporarily convert a section of Amherst Avenue from one-way eastbound traffic operations to two-way traffic operations. This will allow property owners impacted by the subject laneway closure to access the east-west portion of the public laneway.

Staff recommended

The Director, Traffic Management, Transportation Services, recommends that: 1. Toronto and East York Community Council authorize the continuation of the closure of a portion of the public laneway, between Eleanor Avenue and a point 31.5 metres south, from February 17, 2022 to July 31, 2022. 2. Toronto and East York Community Council authorize the implementation of two-way traffic operations on Amherst Avenue, between Oakwood Avenue and the lane first west of Oakwood Avenue, from February 17, 2022 to July 31, 2022.

Show the rest of Staff recommended, 1,927 more characters as filed

3. Toronto and East York Community Council prohibit stopping at all times on the north side of Amherst Avenue, between Oakwood Avenue and the lane first west of Oakwood Avenue. 4. Toronto and East York Community Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 5. Toronto and East York Community Council direct the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 6. Toronto and East York Community Council direct the applicant to continue providing a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 7. Toronto and East York Community Council direct the applicant to continue providing a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 8. Toronto and East York Community Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 9. Toronto and East York Community Council direct that the public laneway and Amherst Avenue be returned to pre-construction traffic and parking regulations when the project is complete.