Construction Staging Area - Time Extension - Port Lands Flood Protection - Cherry Street Temporary Diversion Road

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2022-05-11 · Toronto City Council · adopted

As filed

City Council on May 11 and 12, 2022, adopted the following: 1. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic on the west sidewalk and two southbound lanes on Cherry Street between a point 55 metres south of Commissioners Street and a point 393.5 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project.

Show the rest of As filed, 1,312 more characters as filed

2. City Council authorize the continuation of the temporary closure to pedestrian traffic on the east sidewalk on Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 3. City Council authorize the continuation of the temporary closure to pedestrian and cycling traffic Martin Goodman Trail on the east side of Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 4. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic each of the north boulevard and the 5.5 metre wide portion of the westbound lane on Polson Street, between Cherry Street and a point 83.5 metres west, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 5. City Council direct that Waterfront Toronto continue to be responsible for all costs incurred with respect to road repairs and traffic signage modifications.

On the agenda

As the city filed it

As the Toronto Transit Commission (TTC) operates a transit service on Cherry Street, City Council approval of this report is required. As part of the Port Lands Flood Protection Project and Enabling Infrastructure Project, Waterfront Toronto has undertaken the construction of the Cherry Street re-alignment, between Lake Shore Boulevard East and Polson Street. A construction staging area has been set-up on the west side of Cherry Street and the north side of Polson Street.

Show the rest of As the city filed it, 1,343 more characters as filed

In addition, a temporary detour (diversion) roadway has been fully constructed within the existing northbound lanes, east boulevard on Cherry Street, and within the additional lands on the east side of Cherry Street (leased from City of Toronto Economic Development Corporation) to accommodate northbound and southbound traffic around the construction staging area. City Council, at its meeting on May 28, 2020, authorized the subject construction staging area on Cherry Street, from June 29, 2020 to February 28, 2022. At the time, Waterfront Toronto indicated they would require the construction staging area for a total of 34 months. At its meetings on February 2, 2022, City Council subsequently authorized extending the duration of the construction staging area until May 31, 2022. Waterfront Toronto has requested an extension of the duration of the construction staging area on Cherry Street, in order to complete the construction of the Cherry Street re-alignment. Based on the information provided by Waterfront Toronto, the site has experienced additional construction delays due to dewatering challenges. Transportation Services is requesting authorization to extend the duration of the construction staging area and temporary detour (diversion) roadway until July 31, 2022 in order to complete the construction of the re-alignment.

Staff recommended

The Director, Traffic Management, Transportation Services recommends that: 1. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic on the west sidewalk and two southbound lanes on Cherry Street between a point 55 metres south of Commissioners Street and a point 393.5 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project.

Show the rest of Staff recommended, 1,312 more characters as filed

2. City Council authorize the continuation of the temporary closure to pedestrian traffic on the east sidewalk on Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 3. City Council authorize the continuation of the temporary closure to pedestrian and cycling traffic Martin Goodman Trail on the east side of Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 4. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic each of the north boulevard and the 5.5 metre wide portion of the westbound lane on Polson Street, between Cherry Street and a point 83.5 metres west, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 5. City Council direct that Waterfront Toronto continue to be responsible for all costs incurred with respect to road repairs and traffic signage modifications.

Considered

  • 2022-04-21 · Toronto and East York Community Council · adopted

    Decision as filed

    The Toronto and East York Community Council: 1. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic on the west sidewalk and two southbound lanes on Cherry Street between a point 55 metres south of Commissioners Street and a point 393.5 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project.

    Show the rest of Decision as filed, 1,312 more characters as filed

    2. City Council authorize the continuation of the temporary closure to pedestrian traffic on the east sidewalk on Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 3. City Council authorize the continuation of the temporary closure to pedestrian and cycling traffic Martin Goodman Trail on the east side of Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 4. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic each of the north boulevard and the 5.5 metre wide portion of the westbound lane on Polson Street, between Cherry Street and a point 83.5 metres west, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 5. City Council direct that Waterfront Toronto continue to be responsible for all costs incurred with respect to road repairs and traffic signage modifications.

  • 2022-05-11 · Toronto City Council · adopted