Construction Staging Area Time Extension - 462 Eastern Avenue

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2022-04-21 · Toronto and East York Community Council · adopted

As filed

The Toronto and East York Community Council: 1. Authorized the continuation of the closure of the north sidewalk and westbound curb lane of Eastern Avenue, from the west side of Logan Avenue to the east side of Booth Ave, from April 22, 2022 to September 1, 2022. 2. Authorized the continuation of the closure of the west sidewalk and a 3 metre-wide portion of the southbound lane on Logan Avenue from Eastern Avenue to a point 90 metres further north, from April 22, 2022 to September 1, 2022.

Show the rest of As filed, 2,765 more characters as filed

3. Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 4. Directed the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 5. Directed the applicant to continue sweeping the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe. 6. Directed the applicant to continue to pressure wash the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 7. Directed the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night. 8. Directed the applicant to continue to establish a Construction Liaison Committee made up of local residents and business owners to the satisfaction of the local Councillor, that the Committee is to meet weekly at the beginning of construction, and that minutes of the meetings are forwarded to the Local Councillor. 9. Directed the applicant to consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 10. Directed the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 11. Directed the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 12. Directed the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 13. Directed the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 14. Directed that Eastern Avenue and Logan Avenue be returned to its pre-construction traffic and parking regulations when the project is complete.

On the agenda

As the city filed it

This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. 462 Developments Inc. is building an eight-storey condominium with a total of 286 units at 462 Eastern Ave. The site is located on the north side of Eastern Avenue, between Logan Avenue and Booth Avenue. The north sidewalk and westbound curb lane of Eastern Avenue, from the west side of Logan Avenue to the east side of Booth Ave, are closed to accommodate construction staging operations for the development.

Show the rest of As the city filed it, 894 more characters as filed

In addition, the west sidewalk and a portion of the southbound lane on Logan Avenue is closed, from Eastern Avenue to a point 90 metres north. Toronto and East York Community Council, at its meeting on December 3, 2019, approved the construction staging areas on Eastern Avenue and Logan Avenue from December 2, 2019 to March 31, 2022. The developer has requested an extension of the duration of the construction staging areas on Eastern Avenue and Logan Avenue, in order to complete the construction of the development. Based on the information provided by the developer, the site has experienced a number of construction delays due to COVID-19 and inclement weather. Transportation Services is requesting authorization to extend the duration of the construction staging areas on Eastern Avenue and Logan Avenue until September 1, 2022 in order to complete the construction of the development.

Staff recommended

The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council authorize the continuation of the closure of the north sidewalk and westbound curb lane of Eastern Avenue, from the west side of Logan Avenue to the east side of Booth Ave, from April 22, 2022 to September 1, 2022. 2. Toronto and East York Community Council authorize the continuation of the closure of the west sidewalk and a 3 metre-wide portion of the southbound lane on Logan Avenue from Eastern Avenue to a point 90 metres further north, from April 22, 2022 to September 1, 2022.

Show the rest of Staff recommended, 3,221 more characters as filed

3. Toronto and East York Community Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 4. Toronto and East York Community Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 5. Toronto and East York Community Council direct the applicant to continue sweeping the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe. 6. Toronto and East York Community Council direct the applicant to continue to pressure wash the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 7. Toronto and East York Community Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night. 8. Toronto and East York Community Council direct the applicant to continue to establish a Construction Liaison Committee made up of local residents and business owners to the satisfaction of the local Councillor, that the Committee is to meet weekly at the beginning of construction, and that minutes of the meetings are forwarded to the Local Councillor. 9. Toronto and East York Community Council direct the applicant to consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 10. Toronto and East York Community Council direct the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 11. Toronto and East York Community Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 12. Toronto and East York Community Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 13. Toronto and East York Community Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 14. Toronto and East York Community Council direct that Eastern Avenue and Logan Avenue be returned to its pre-construction traffic and parking regulations when the project is complete.