The filed record
Cummer Station - Response to Council Motions
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2023-12-13 · Toronto City Council · amended
As filed
City Council on December 13, 14 and 15, 2023, adopted the following: 1. City Council forward Attachment 1 of the report (November 21, 2023) from the Chief Planner and Executive Director, City Planning, and the Executive Director, Transit Expansion to the Province of Ontario and request the Province to reconsider funding the delivery of Cummer Station as part of the Yonge North Subway Extension project. 2. City Council request the Province of Ontario to: a.
Show the rest of As filed, 428 more characters as filed
formally respond to "The Case For Cummer Station" (November 2023) prepared by Toronto's Chief Planner and Executive Director, City Planning, and the Executive Director, Transit Expansion; b. include Cummer Station in the Metrolinx stage gate design process; and c. receive the letter attached to this Motion from community organizations and council representatives advocating for the fully funded construction of Cummer Station.
The vote
Amend Item · Carried, 20-0
The whole record, all 26 members
- Alejandra BravoFor
- Amber MorleyFor
- Anthony PerruzzaAbsent
- Ausma MalikFor
- Brad BradfordFor
- Chris MoiseFor
- Dianne SaxeFor
- Frances NunziataFor
- Gord PerksFor
- Jamaal MyersFor
- James PasternakAbsent
- Jaye RobinsonAbsent
- Jennifer McKelvieFor
- Jon BurnsideFor
- Josh MatlowFor
- Lily ChengFor
- Michael ThompsonAbsent
- Mike ColleFor
- Nick MantasFor
- Olivia ChowFor
- Parthi KandavelFor
- Paul AinslieAbsent
- Paula FletcherFor
- Shelley CarrollFor
- Stephen HolydayFor
- Vincent CrisantiAbsent
Every name opens that member’s record.
On the agenda
As the city filed it
This report responds to a number of motions from City Council regarding a potential future subway station at Yonge Street and Cummer/Drewry Avenues (i.e., Cummer Station) as part of the Yonge North Subway Extension (YNSE). Originally planned as part of the Province of Ontario's YNSE project, Cummer Station and another station at Royal Orchard Road in the City of Markham were descoped by Metrolinx following the completion of their Initial Business Case analysis and prior to the further planning and design of the project.
Show the rest of As the city filed it, 731 more characters as filed
However, Metrolinx later agreed to deliver Royal Orchard Station despite its poorer performance relative to Cummer Station. At present Cummer Station remains out of scope for the YNSE. City staff were directed through MM11.19 Last Chance to Urge Province to Build Cummer Station for the Future of North York, to prepare a business case for Cummer Station which will form the basis for another request to the Province to include Cummer Station in the YNSE's base scope. As such, City staff have developed the preliminary business case included in Attachment 1 to this report. EX5.3 Update on Metrolinx Subways Program - Second Quarter 2023 also included motions related to Cummer Station. This report also responds to these motions.
Staff recommended
The Chief Planner and Executive Director, City Planning, and the Executive Director, Transit Expansion recommend that: 1. City Council forward Attachment 1 of this report (The Case for Cummer Station) to the Province of Ontario and request the Province reconsider funding the delivery of Cummer Station as part of the Yonge North Subway Extension (YNSE) project. 2. City Council direct the Chief Planner and Executive Director,
Show the rest of Staff recommended, 421 more characters as filed
City Planning to engage with the Province to explore how Transit Oriented Communities (TOCs) could be leveraged in the vicinity of Cummer Station as a partial funding tool to offset the capital cost of delivering the station as part of the YNSE and report on the progress of these explorations through the next status report on TOCs, recognizing that the value of TOC contributions as outlined in this report are limited.
Considered
2023-12-05 · Executive Committee · forwarded without recommendation
Decision as filed
The Executive Committee forwards the Item to City Council without recommendation.
Clerk’s note
The Executive Committee directed the Chief Planner and Executive Director, City Planning, and the Executive Director, Transit Expansion, in consultation with the Chief Financial Officer and Treasurer, to report to the December 13, 14 and 15, 2023 meeting of City Council on the potential funding sources for $70 million to cover the cost of designing the construction of headwalls and the necessary utility relocations to
Show the rest of Clerk’s note, 225 more characters as filed
protect for a future Cummer Station and include the headwall installation in the current Yonge North Subway Extension Tunnel Request For Proposal, while continuing to advocate for the province to fund the full implementation.
2023-12-13 · Toronto City Council · amended
On the record
More from this meeting
- Memorandum of Understanding between the City of Toronto and the Toronto and Region Conservation AuthorityFiled record
- Advancing Generational Transformation of Toronto's Housing System - Aligning Housing Mandates and Strategic EffortsFiled record
- 2024 Tax and Rate Supported Interim Operating and Capital Spending AuthoritiesFiled record
- 2024 Interim Water and Wastewater Consumption Rates and Service FeesFiled record
- 2024 Interim Solid Waste Management Services Rates and FeesFiled record
- 2022 Development Charge Deferred Revenue Activity and BalancesFiled record