Award of Ariba Document Number 3448368603 to CH2M Hill Canada Limited and Stantec Consulting Limited for Professional Engineering Services for Phase 5 of the Basement Flooding Protection Program

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2023-03-29 · Toronto City Council · amended

As filed

City Council on March 29, 30 and 31, 2023, adopted the following: 1. City Council, in accordance with Section 195-8.4A of the Toronto Municipal Code Chapter 195, Purchasing By-Law, authorize the Chief Engineer and Executive Director, Engineering and Construction Services to negotiate and enter into an agreement with CH2M Hill Canada Limited, being the highest overall scoring Supplier meeting the requirements of Ariba Document Number 3448368603 to provide program management, preliminary and detailed design, construction administration and post construction services for Phase 5 of the Basement Flooding Protection Program Bundle 1 Assignments, in the total amount of $41,348,551 net of all applicable taxes ($42,076,285 net of Harmonized Sales Tax recoveries) as follows: a.

Show the rest of As filed, 2,936 more characters as filed

program management, in an amount not to exceed $10,090,986 net of all applicable taxes and charges ($10,268,587 net of Harmonized Sales Tax recoveries), including labour, disbursements, provisional allowances and contingency amounts; b. preliminary and detailed design, in an amount not to exceed $11,832,727 net of all applicable taxes and charges ($12,040,983 net of Harmonized Sales Tax recoveries), including labour, disbursements, provisional allowances and contingency amounts; c. construction administration, in an amount not to exceed $19,118,338 net of all applicable taxes and charges ($19,454,820 net of Harmonized Sales Tax recoveries), including labour, disbursements, provisional allowances and contingency amounts; and d. post construction services, in an amount not to exceed $306,500 net of all applicable taxes and charges ($311,894 net of Harmonized Sales Tax recoveries), including labour, disbursements, provisional allowances and contingency amounts. 2. City Council, in accordance with Section 195-8.4A of the Toronto Municipal Code Chapter 195, Purchasing By-Law, authorize the Chief Engineer and Executive Director, Engineering and Construction Services to negotiate and enter into an agreement with Stantec Consulting Limited, being the next highest overall scoring supplier meeting the requirements of Ariba Document Number 3448368603 to provide program management, preliminary and detailed design, construction administration and post construction services for Phase 5 of the Basement Flooding Protection Program Bundle 2 Assignments, in the total amount of $43,768,591 net of all applicable taxes ($44,538,918 net of Harmonized Sales Tax recoveries) as follows: a. program management, in an amount not to exceed $11,343,493 net of all applicable taxes and charges ($11,543,138 net of Harmonized Sales Tax recoveries), including labour, disbursements, provisional allowances and contingency amounts; b. preliminary and detailed design, in an amount not to exceed $11,046,265 net of all applicable taxes and charges ($11,240,680 net of Harmonized Sales Tax recoveries), including labour, disbursements, provisional allowances and contingency amounts; c. construction administration, in an amount not to exceed $21,088,833 net of all applicable taxes and charges ($21,459,996 net of Harmonized Sales Tax recoveries), including labour, disbursements, provisional allowances and contingency amounts; and d. post construction services, in an amount not to exceed $290,000 net of all applicable taxes and charges ($295,104 net of Harmonized Sales Tax recoveries), including labour, disbursements, provisional allowances and contingency amounts, all in accordance with the terms and conditions as set out in the Request for Proposal and any other terms and conditions satisfactory to the Chief Engineer and Executive Director, Engineering and Construction Services, and in a form satisfactory to the City Solicitor.

The vote

Without Recommendations · Carried, 4-1

Against (1)Stephen Holyday
Absent (1)Lily Cheng
The whole record, all 6 members

Every name opens that member’s record.

On the agenda

As the city filed it

The purpose of this report is to advise of the results of Request for Proposal, Ariba Document Number 3448368603, Contract Number RFP‑22ECS‑LU‑02FP, for professional engineering services associated with program management, preliminary and detailed design, construction administration and post construction services for Phase 5 of the Basement Flooding Protection Program, and request the authority to enter

Show the rest of As the city filed it, 416 more characters as filed

into agreements with CH2M Hill Canada Limited, in the amount of $41,348,551 net of all applicable taxes and charges ($42,076,285 net of HST recoveries) and Stantec Consulting Limited, in the amount of $43,768,591 net of all applicable taxes and charges ($44,538,918 net of HST recoveries), respectively, for a combined total of $85,117,142 net of all applicable taxes and charges ($86,615,203 net of HST recoveries).

Staff recommended

The Chief Engineer and Executive Director, Engineering and Construction Services and the Chief Procurement Officer, Purchasing and Materials Management recommend that: 1. The General Government Committee, in accordance with Section 195-8.4A of the Toronto Municipal Code Chapter 195 (Purchasing By-Law), grant authority to the Chief Engineer and Executive Director, Engineering and Construction Services to negotiate and

Show the rest of Staff recommended, 3,286 more characters as filed

enter into an agreement with CH2M Hill Canada Limited, being the highest overall scoring Supplier meeting the requirements of Ariba Document Number 3448368603 to provide program management, preliminary and detailed design, construction administration and post construction services for Phase 5 of the Basement Flooding Protection Program Bundle 1 Assignments, in the total amount of $41,348,551 net of all applicable taxes ($42,076,285 net of HST recoveries) as follows: a) Program management, in an amount not to exceed $10,090,986 net of all applicable taxes and charges ($10,268,587 net of HST recoveries), including labour, disbursements, provisional allowances and contingency amounts; b) Preliminary and detailed design, in an amount not to exceed $11,832,727 net of all applicable taxes and charges ($12,040,983 net of HST recoveries), including labour, disbursements, provisional allowances and contingency amounts; c) Construction administration, in an amount not to exceed $19,118,338 net of all applicable taxes and charges ($19,454,820 net of HST recoveries), including labour, disbursements, provisional allowances and contingency amounts; and d) Post construction services, in an amount not to exceed $306,500 net of all applicable taxes and charges ($311,894 net of HST recoveries), including labour, disbursements, provisional allowances and contingency amounts. 2. The General Government Committee, in accordance with Section 195-8.4A of the Toronto Municipal Code Chapter 195 (Purchasing By-Law), grant authority to the Chief Engineer and Executive Director, Engineering and Construction Services to negotiate and enter into an agreement with Stantec Consulting Limited, being the next highest overall scoring supplier meeting the requirements of Ariba Document Number 3448368603 to provide program management, preliminary and detailed design, construction administration and post construction services for Phase 5 of the Basement Flooding Protection Program Bundle 2 Assignments, in the total amount of $43,768,591 net of all applicable taxes ($44,538,918 net of HST recoveries) as follows: a) Program management, in an amount not to exceed $11,343,493 net of all applicable taxes and charges ($11,543,138 net of HST recoveries), including labour, disbursements, provisional allowances and contingency amounts; b) Preliminary and detailed design, in an amount not to exceed $11,046,265 net of all applicable taxes and charges ($11,240,680 net of HST recoveries), including labour, disbursements, provisional allowances and contingency amounts; c) Construction administration, in an amount not to exceed $21,088,833 net of all applicable taxes and charges ($21,459,996 net of HST recoveries), including labour, disbursements, provisional allowances and contingency amounts; and d) Post construction services, in an amount not to exceed $290,000 net of all applicable taxes and charges ($295,104 net of HST recoveries), including labour, disbursements, provisional allowances and contingency amounts. All in accordance with the terms and conditions as set out in the Request for Proposal and any other terms and conditions satisfactory to the Chief Engineer and Executive Director, Engineering and Construction Services and in a form satisfactory to the City Solicitor.

Considered

On the record

The item as the City filed it

More from this meeting

The whole meeting