North York Community Council · 2023-02-22 · 2023.NY3.3

The filed record

2 - 20 Glazebrook Avenue - Zoning By-law Amendment Application - Appeal Report

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2023-03-29 · Toronto City Council · adopted

As filed

City Council on March 29, 30 and 31, 2023, adopted the following: 1. City Council direct the City Solicitor and appropriate City staff to attend the Ontario Land Tribunal in opposition to the current Application regarding the Zoning By-law Amendment appeal for the lands at 2 - 20 Glazebrook Avenue. 2. In the event that the Ontario Land Tribunal allows the appeals in whole or in part, City Council authorize the City Solicitor to request that the issuance of any final Orders be withheld until such time as the City Solicitor advises that: a.

Show the rest of As filed, 2,863 more characters as filed

the final form and content of the draft Zoning By-law is to the satisfaction of the City Solicitor and the Chief Planner and Executive Director, City Planning; b. the owner has satisfactorily addressed the Engineering and Construction Services matters in the Engineering and Construction Services Memorandum dated September 7, 2022, or as may be updated, in response to further submissions filed by the Owner, all to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services; c. the owner has submitted a revised Travel Demand Management Plan acceptable to, and to the satisfaction of the Chief Planner and Executive Director, City Planning and the General Manager, Transportation Services and that such matters arising from such study be secured if required; d. the owner has submitted a Methane Gas Investigation Report acceptable to, and to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services, and that such matters arising from such study be secured if required; e. the owner has satisfactorily addressed matters from the Urban Forestry memorandum dated September 13, 2022, including the submission of a Public Utilities Plan and Soil Volumes Plan, or as may be updated, in response to further submissions filed by the Owner, all to the satisfaction of Urban Forestry; and f. the owner has submitted an updated complete Toronto Green Standards Checklist and Statistics Template, to the satisfaction of the Chief Planner and Executive Director, City Planning. 3. Should it be determined that upgrades are required to the infrastructure to support the development according to the accepted Functional Servicing Report and/or the Transportation Impact Study or that mitigation is required per the Subsurface Investigation, City Council direct the City Solicitor and appropriate City staff to request that a Holding provision (H) be included in the final form of the site-specific Zoning By-law Amendment, not to be lifted until such time as the owner has made satisfactory arrangements, including entering into appropriate agreement(s) with the City for required mitigation, as well as the design and construction of any improvements to the municipal infrastructure and the provision of financial securities to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services and the General Manager, Transportation Services; 4. City Council authorize the City Solicitor and appropriate City staff to continue discussions with the applicant to address outstanding issues, including but not limited to those outlined in the report (January 11, 2023) from the Director, Community Planning, North York District. 5. City Council authorize the City Solicitor and City staff to take any necessary steps to implement City Council's decision.

On the agenda

As the city filed it

On July 14, 2022, an application to amend the Zoning By-law was submitted to permit a 34-storey (109.9 metres to top of roof) mixed-use building with 434 dwellings units and a total gross floor area of 29,600 square metres at 2-20 Glazebrook Avenue. On December 8, 2022, the applicant appealed the Zoning By-law Amendment application to the Ontario Land Tribunal due to Council not making a decision within the time frame prescribed in the Planning Act.

Show the rest of As the city filed it, 269 more characters as filed

This report recommends that City Council instruct the City Solicitor with the appropriate City staff to attend the Ontario Land Tribunal hearing and oppose the application in its current form and to continue discussions with the Applicant to resolve outstanding issues.

Staff recommended

The Director, Community Planning, North York District recommends that: 1. City Council direct the City Solicitor and appropriate City staff to attend the Ontario Land Tribunal in opposition to the current Application regarding the Zoning By-law Amendment appeal for the lands at 2 - 20 Glazebrook Avenue. 2. In the event that the Ontario Land Tribunal allows the appeals in whole or in part, City Council authorize the City Solicitor to request that the issuance of any final Orders be withheld until such time as the City Solicitor advises that: a.

Show the rest of Staff recommended, 2,660 more characters as filed

the final form and content of the draft Zoning By-law is to the satisfaction of the City Solicitor and the Chief Planner and Executive Director, City Planning; b. the owner has satisfactorily addressed the Engineering and Construction Services matters in the Engineering and Construction Services Memorandum dated September 7, 2022, or as may be updated, in response to further submissions filed by the Owner, all to the satisfaction of the Chief Engineer; c. the owner has submitted a revised Travel Demand Management Plan acceptable to, and to the satisfaction of the Chief Planner and Executive Director, City Planning and the General Manager, Transportation Services and that such matters arising from such study be secured if required; d. the owner has submitted a Methane Gas Investigation Report acceptable to, and to the satisfaction of the Chief Engineer, and that such matters arising from such study be secured if required; e. the owner has satisfactorily addressed matters from the Urban Forestry memorandum dated September 13, 2022, including the submission of a Public Utilities Plan and Soil Volumes Plan, or as may be updated, in response to further submissions filed by the Owner, all to the satisfaction of Urban Forestry; and f. the owner has submitted an updated complete Toronto Green Standards Checklist and Statistics Template, to the satisfaction of the Chief Planner and Executive Director, City Planning. 3. Should it be determined that upgrades are required to the infrastructure to support the development according to the accepted Functional Servicing Report and / or the Transportation Impact Study or that mitigation is required per the Subsurface Investigation, City Council direct the City Solicitor and appropriate City staff to request that a Holding provision (H) be included in the final form of the site-specific Zoning By-law Amendment, not to be lifted until such time as the owner has made satisfactory arrangements, including entering into appropriate agreement(s) with the City for required mitigation, as well as the design and construction of any improvements to the municipal infrastructure and the provision of financial securities to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services and General Manager, Transportation Services; 4. City Council authorize the City Solicitor and appropriate City staff to continue discussions with the applicant to address outstanding issues, including but not limited to those outlined in this report. 5. City Council authorize the City Solicitor and City staff to take any necessary steps to implement City Council's decision.

Considered

  • 2023-02-22 · North York Community Council · adopted

    Decision as filed

    North York Community Council recommends that: 1. City Council direct the City Solicitor and appropriate City staff to attend the Ontario Land Tribunal in opposition to the current Application regarding the Zoning By-law Amendment appeal for the lands at 2 - 20 Glazebrook Avenue. 2. In the event that the Ontario Land Tribunal allows the appeals in whole or in part, City Council authorize the City Solicitor to request that the issuance of any final Orders be withheld until such time as the City Solicitor advises that: a.

    Show the rest of Decision as filed, 2,660 more characters as filed

    the final form and content of the draft Zoning By-law is to the satisfaction of the City Solicitor and the Chief Planner and Executive Director, City Planning; b. the owner has satisfactorily addressed the Engineering and Construction Services matters in the Engineering and Construction Services Memorandum dated September 7, 2022, or as may be updated, in response to further submissions filed by the Owner, all to the satisfaction of the Chief Engineer; c. the owner has submitted a revised Travel Demand Management Plan acceptable to, and to the satisfaction of the Chief Planner and Executive Director, City Planning and the General Manager, Transportation Services and that such matters arising from such study be secured if required; d. the owner has submitted a Methane Gas Investigation Report acceptable to, and to the satisfaction of the Chief Engineer, and that such matters arising from such study be secured if required; e. the owner has satisfactorily addressed matters from the Urban Forestry memorandum dated September 13, 2022, including the submission of a Public Utilities Plan and Soil Volumes Plan, or as may be updated, in response to further submissions filed by the Owner, all to the satisfaction of Urban Forestry; and f. the owner has submitted an updated complete Toronto Green Standards Checklist and Statistics Template, to the satisfaction of the Chief Planner and Executive Director, City Planning. 3. Should it be determined that upgrades are required to the infrastructure to support the development according to the accepted Functional Servicing Report and / or the Transportation Impact Study or that mitigation is required per the Subsurface Investigation, City Council direct the City Solicitor and appropriate City staff to request that a Holding provision (H) be included in the final form of the site-specific Zoning By-law Amendment, not to be lifted until such time as the owner has made satisfactory arrangements, including entering into appropriate agreement(s) with the City for required mitigation, as well as the design and construction of any improvements to the municipal infrastructure and the provision of financial securities to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services and General Manager, Transportation Services; 4. City Council authorize the City Solicitor and appropriate City staff to continue discussions with the applicant to address outstanding issues, including but not limited to those outlined in this report. 5. City Council authorize the City Solicitor and City staff to take any necessary steps to implement City Council's decision.

  • 2023-03-29 · Toronto City Council · adopted

On the record

The item as the City filed it

More from this meeting

The whole meeting