The decision
2023-06-14 · Toronto City Council · adopted
As filed
City Council on June 14 and 15, 2023, adopted the following: 1. City Council direct the City Solicitor, and appropriate City staff, to attend the Ontario Land Tribunal in opposition to the current Application regarding the Official Plan and Zoning By-law Amendment appeal for the lands at 774, 776, 778, 780 and 782 Marlee Avenue and to continue discussions with the Applicant in an attempt to resolve outstanding issues.
Show the rest of As filed, 4,352 more characters as filed
2. In the event that the Ontario Land Tribunal allows the appeals in whole or in part, City Council authorize the City Solicitor to request that the issuance of any final Orders be withheld until such time as the City Solicitor advises that: a. the final form and content of the draft Official Plan and Zoning By-laws are to the satisfaction of the City Solicitor and the Chief Planner and Executive Director, City Planning; i. provisions for a holding By-law pursuant to Section 36 of the Planning Act regarding the provision of an acceptable sanitary system solution constructed and operational as determined by the Chief Engineer and Executive Director, Engineering and Construction Services which may include the applicant obtaining Ministry of the Environment, Conservation and Parks Environmental Compliance Approval and upgrading the existing municipal infrastructure off site. b. the Owner has satisfactorily addressed the Transportation Services and Engineering and Construction Services matters in the Engineering and Construction Services Memorandum dated May 31, 2022, and any outstanding issues arising from the ongoing technical review (including provision of acceptable reports and studies), as they relate to the Official Plan and Zoning By-law Amendment application to the satisfaction of the General Manager, Transportation Services and the Chief Engineer and Executive Director, Engineering and Construction Services; c. submit to the Chief Engineer and Executive Director, Engineering and Construction Services for review and acceptance, prior to approval of the rezoning application, a Functional Servicing Report to determine the storm water runoff, sanitary flow and water supply demand resulting from this development and whether there is adequate capacity in the existing municipal infrastructure to accommodate the proposed development; d. make satisfactory arrangements with Engineering and Construction Services and enter into the appropriate agreement with the City for the design and construction of any improvements to the municipal infrastructure, should it be determined that upgrades are required to the infrastructure to support this development, according to the accepted Functional Servicing Report accepted by the Chief Engineer and Executive Director, Engineering and Construction Services; e. the Owner has provided financial securities for any upgrades or required improvements to the existing municipal infrastructure identified in the acceptable Functional Servicing Report and Stormwater Management Report, to support the development, all to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services, and the General Manager, Toronto Water, where it has been determined that improvements or upgrades are required to support the development; in requiring any off site municipal infrastructure upgrades, the owner is to make satisfactory arrangements with Engineering and Construction Services for Work on the City's Right-of-Way; f. provide space within the development for installation of maintenance access holes and sampling ports on the private side, as close to the property line as possible, for both the storm and sanitary service connections, in accordance with Section 681-10 of Municipal Code Chapter 681, Sewers; g. the Owner has submitted a Housing Issues Report and tenant relocation and assistance plan to the satisfaction of the Chief Planner and Executive Director, City Planning and the City Solicitor in accordance with Official Plan Policy 3.2.1.12; h. the Owner has submitted an updated complete Toronto Green Standards Checklist and Statistics Template, to the satisfaction of the Chief Planner and Executive Director, City Planning; i. the Owner has submitted a revised Travel Demand Management Plan acceptable to, and to the satisfaction of, the Chief Planner and Executive Director, City Planning and the General Manager, Transportation Services; and j. the Owner has addressed all outstanding issues raised by Urban Forestry, Tree Protection and Plan Review as they relate to the Zoning By-law Amendment application, to the satisfaction of the General Manager, Parks, Forestry and Recreation and the City Solicitor. 3. City Council authorize the City Solicitor and City staff to take any necessary steps to implement City Council's decision.
On the agenda
As the city filed it
On December 23, 2021, an Official Plan and Zoning By-law Amendment application was submitted to permit a 12 storey (40.7 metres including mechanical penthouse) residential building with 301 residential units. The application was deemed complete on February 11, 2022. On October 18, 2022, the Applicant appealed the application to the Ontario Land Tribunal due to Council not making a decision within the 120-day time frame in the Planning Act.
Show the rest of As the city filed it, 311 more characters as filed
The first Case Management Conference was held on February 10, 2023. This report recommends that the City Solicitor with the appropriate City staff attend the Ontario Land Tribunal hearing to oppose the application in its current form and to continue discussions with the Applicant to resolve outstanding issues.
Staff recommended
The Director, Community Planning, North York recommends that: 1. City Council direct the City Solicitor and appropriate City staff to attend the Ontario Land Tribunal in opposition to the current Application regarding the Official Plan and Zoning By-law Amendment appeal for the lands at 774, 776, 778, 780 and 782 Marlee Avenue and to continue discussions with the Applicant in an attempt to resolve outstanding issues. 2.
Show the rest of Staff recommended, 4,324 more characters as filed
In the event that the Ontario Land Tribunal allows the appeals in whole or in part, City Council authorize the City Solicitor to request that the issuance of any final Orders be withheld until such time as the City Solicitor advises that: a. the final form and content of the draft Official Plan and Zoning By-laws are to the satisfaction of the City Solicitor and the Chief Planner and Executive Director, City Planning; i. provisions for a holding by-law pursuant to Section 36 of the Planning Act regarding the provision of an acceptable sanitary system solution constructed and operational as determined by the Chief Engineer and Executive Director, Engineering and Construction Services which may include the applicant obtaining Ministry of the Environment, Conservation and Parks Environmental Compliance Approval and upgrading the existing municipal infrastructure off site; b. the owner has satisfactorily addressed the Transportation Services and Engineering and Construction Services matters in the Engineering and Construction Services Memorandum dated May 31, 2022, and any outstanding issues arising from the ongoing technical review (including provision of acceptable reports and studies), as they relate to the Official Plan and Zoning By-law Amendment application to the satisfaction of the General Manager, Transportation Services and Chief Engineer and Executive Director, Engineering and Construction Services; c. submit to the Chief Engineer and Executive Director of Engineering and Construction Services for review and acceptance, prior to approval of the rezoning application, a Functional Servicing Report to determine the storm water runoff, sanitary flow and water supply demand resulting from this development and whether there is adequate capacity in the existing municipal infrastructure to accommodate the proposed development; d. make satisfactory arrangements with Engineering and Construction Services and enter into the appropriate agreement with the City for the design and construction of any improvements to the municipal infrastructure, should it be determined that upgrades are required to the infrastructure to support this development, according to the accepted Functional Servicing Report accepted by the Chief Engineer and Executive Director of Engineering and Construction Services; e. the owner has provided financial securities for any upgrades or required improvements to the existing municipal infrastructure identified in the acceptable Functional Servicing Report and Stormwater Management Report, to support the development, all to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services, and General Manager, Toronto Water, where it has been determined that improvements or upgrades are required to support the development. In requiring any off site municipal infrastructure upgrades, the owner is to make satisfactory arrangements with Engineering & Construction Services for Work on the City's Right-of-Way; f. provide space within the development for installation of maintenance access holes and sampling ports on the private side, as close to the property line as possible, for both the storm and sanitary service connections, in accordance with the Sewers By-law Chapter 681.10; g. the owner has submitted a Housing Issues Report and tenant relocation and assistance plan to the satisfaction of the Chief Planner and Executive Director, City Planning and the City Solicitor in accordance with Official Plan Policy 3.2.1.12; h. the owner has submitted an updated complete Toronto Green Standards Checklist and Statistics Template, to the satisfaction of the Chief Planner and Executive Director, City Planning; i. the owner has submitted a revised Travel Demand Management Plan acceptable to, and to the satisfaction of, the Chief Planner and Executive Director, City Planning and the General Manager, Transportation Services; and j. the owner has addressed all outstanding issues raised by Urban Forestry, Tree Protection and Plan Review as they relate to the Zoning By-law Amendment application, to the satisfaction of the General Manager, Parks, Forestry and Recreation and the City Solicitor. 3. City Council authorizes the City Solicitor and City staff to take any necessary steps to implement City Council's decision.
Considered
2023-05-16 · North York Community Council · amended
Decision as filed
North York Community Council recommends that: 1. City Council direct the City Solicitor and appropriate City staff to attend the Ontario Land Tribunal in opposition to the current Application regarding the Official Plan and Zoning By-law Amendment appeal for the lands at 774, 776, 778, 780 and 782 Marlee Avenue and to continue discussions with the Applicant in an attempt to resolve outstanding issues. 2. In the event that the Ontario Land Tribunal allows the appeals in whole or in part, City Council authorize the City Solicitor to request that the issuance of any final Orders be withheld until such time as the City Solicitor advises that: a.
Show the rest of Decision as filed, 4,082 more characters as filed
the final form and content of the draft Official Plan and Zoning By-laws are to the satisfaction of the City Solicitor and the Chief Planner and Executive Director, City Planning; 1. provisions for a holding by-law pursuant to Section 36 of the Planning Act regarding the provision of an acceptable sanitary system solution constructed and operational as determined by the Chief Engineer and Executive Director, Engineering and Construction Services which may include the applicant obtaining Ministry of the Environment, Conservation and Parks Environmental Compliance Approval and upgrading the existing municipal infrastructure off site; b. the owner has satisfactorily addressed the Transportation Services and Engineering and Construction Services matters in the Engineering and Construction Services Memorandum dated May 31, 2022, and any outstanding issues arising from the ongoing technical review (including provision of acceptable reports and studies), as they relate to the Official Plan and Zoning By-law Amendment application to the satisfaction of the General Manager, Transportation Services and Chief Engineer and Executive Director, Engineering and Construction Services; c. submit to the Chief Engineer and Executive Director of Engineering and Construction Services for review and acceptance, prior to approval of the rezoning application, a Functional Servicing Report to determine the storm water runoff, sanitary flow and water supply demand resulting from this development and whether there is adequate capacity in the existing municipal infrastructure to accommodate the proposed development; d. make satisfactory arrangements with Engineering and Construction Services and enter into the appropriate agreement with the City for the design and construction of any improvements to the municipal infrastructure, should it be determined that upgrades are required to the infrastructure to support this development, according to the accepted Functional Servicing Report accepted by the Chief Engineer and Executive Director of Engineering and Construction Services; e. the owner has provided financial securities for any upgrades or required improvements to the existing municipal infrastructure identified in the acceptable Functional Servicing Report and Stormwater Management Report, to support the development, all to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services, and General Manager, Toronto Water, where it has been determined that improvements or upgrades are required to support the development. In requiring any off site municipal infrastructure upgrades, the owner is to make satisfactory arrangements with Engineering & Construction Services for Work on the City's Right-of-Way; f. provide space within the development for installation of maintenance access holes and sampling ports on the private side, as close to the property line as possible, for both the storm and sanitary service connections, in accordance with the Sewers By-law Chapter 681.10; g. the owner has submitted a Housing Issues Report and tenant relocation and assistance plan to the satisfaction of the Chief Planner and Executive Director, City Planning and the City Solicitor in accordance with Official Plan Policy 3.2.1.12; h. the owner has submitted an updated complete Toronto Green Standards Checklist and Statistics Template, to the satisfaction of the Chief Planner and Executive Director, City Planning; i. the owner has submitted a revised Travel Demand Management Plan acceptable to, and to the satisfaction of, the Chief Planner and Executive Director, City Planning and the General Manager, Transportation Services; and j. the owner has addressed all outstanding issues raised by Urban Forestry, Tree Protection and Plan Review as they relate to the Zoning By-law Amendment application, to the satisfaction of the General Manager, Parks, Forestry and Recreation and the City Solicitor. 3. City Council authorizes the City Solicitor and City staff to take any necessary steps to implement City Council's decision.
Clerk’s note
North York Community Council: 1. Requested the Chief Planner and Executive Director, City Planning, in consultation with the City Clerk, to require the applicant to include a notice to the City Planning Development Sign at 774, 776, 778, 780 and 782 Marlee Avenue to indicate that the application has been appealed to the Ontario Land Tribunal and include the contact information for the Tribunal.
2023-06-14 · Toronto City Council · adopted
On the record
More from this meeting
- 295 Woburn Avenue - Application to Remove a Private TreeFiled record
- 23 Laurentia Crescent - Request for a Fence ExemptionFiled record
- 16 Clematis Road - Application to Remove a Private TreeFiled record
- 206 Dunforest Avenue - Application to Remove a Private TreeFiled record
- 5830 Bathurst Street - Application under Funeral, Burial and Cremation Services Act, 2002 - Decision Report - ApprovalFiled record
- 128, 130 and 132 Gorman Park Road and 795, 797, 799 Sheppard Avenue West Application to Lift the Holding Provisions (H) - Decision Report - ApprovalFiled record