The decision
2023-01-26 · Toronto and East York Community Council · adopted
As filed
The Toronto and East York Community Council: 1. Authorized the continuation of the closure of the north sidewalk and westbound curb lane on Front Street West, between Spadina Avenue and Draper Street, from January 27, 2023 to October 31, 2023. 2. Directed the applicant to continue to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
Show the rest of As filed, 1,898 more characters as filed
3. Directed the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 4. Directed the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 5. Directed the applicant to ensure that the existing sidewalks and/or any proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 6. Directed the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications. 7. Directed the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 8. Directed the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 9. Directed the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 10. Directed that Front Street West be returned to its pre-construction traffic and parking regulations when the project is complete.
On the agenda
As the city filed it
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Deltera Incorporated and EllisDon Corporation are developing the lands bounded by Wellington Street West to the north, Spadina Avenue to the east, Front Street West to the south and Draper Street to the west. The development will consist of seven high-rise buildings of various heights containing office, retail and residential uses.
Show the rest of As the city filed it, 1,204 more characters as filed
Deltera Incorporated will develop six out of seven buildings and EllisDon Corporation will develop the remaining one building to be located in the north-west corner of Front Street West and Spadina Avenue. The north sidewalk and a 3.3 metre-wide portion of the westbound curb lane on Front Street West, between Spadina Avenue and Draper Street, are currently closed for construction staging operations. Toronto and East York Community Council, at its meeting on January 16, 2018, approved the subject construction staging area on Front Street West, from Spadina Avenue to a point 61.5 metres west from March 1, 2018 to December 31, 2020, and from a point 61.5 metres west of Spadina Avenue to Draper Street from March 1, 2018 to June 30, 2022. The developer has requested an extension of the duration of the construction staging area on Front Street West, due to delays caused by: COVID-19 delays (including material delays and shortages), labour issues and inclement weather conditions. Transportation Services is requesting authorization to extend the duration of the construction staging areas from January 27, 2023 to October 31, 2023 to allow for the construction of the development to be completed.
Staff recommended
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council authorize the continuation of the closure of the north sidewalk and westbound curb lane on Front Street West, between Spadina Avenue and Draper Street, from January 27, 2023 to October 31, 2023. 2. Toronto and East York Community Council direct the applicant to continue to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
Show the rest of Staff recommended, 2,194 more characters as filed
3. Toronto and East York Community Council direct the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 4. Toronto and East York Community Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 5. Toronto and East York Community Council direct the applicant to ensure that the existing sidewalks and/or any proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 6. Toronto and East York Community Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 7. Toronto and East York Community Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 8. Toronto and East York Community Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 9. Toronto and East York Community Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 10. Toronto and East York Community Council direct that Front Street West be returned to its pre-construction traffic and parking regulations when the project is complete.
On the record
More from this meeting
- 17 St. Andrew Street - Zoning Amendment Application - Decision Report - ApprovalFiled record
- 22-32 Scollard Street and 21-25 Davenport Road - Zoning By-law Amendment Application - Decision Report - RefusalFiled record
- 69 Yorkville Avenue - Official Plan and Zoning By-law Amendment Application - Decision Report - RefusalFiled record
- 39-47 Camden Street - Zoning Amendment Application - Appeal ReportFiled record
- 45 The Esplanade - Official Plan and Zoning By-law Amendment Applications - Appeal ReportFiled record
- 1-11 Bloor Street West and 768-784 Yonge Street - Zoning By-Law Amendment Application - Appeal ReportFiled record