40-58 Widmer Street - Construction Staging Area Time Extension

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2023-01-26 · Toronto and East York Community Council · adopted

As filed

The Toronto and East York Community Council: 1. Authorized the continuation of the closure of the west sidewalk and a 1.5 metre wide portion of the most westerly curb lane on Widmer Street, between a point 45 metres north of Adelaide Street West and a point 66 metres further north from January 27, 2023 to May 31, 2023. 2. Directed the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.

Show the rest of As filed, 2,095 more characters as filed

3. Directed the applicant to continue to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 4. Directed the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications. 5. Directed the applicant to continue to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 6. Directed the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 7. Directed the applicant to continue to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 8. Directed the applicant to continue to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 9. Directed the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 10. Directed the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 11. Directed that Widmer Street be returned to its pre-construction traffic and parking regulations when the project is complete.

On the agenda

As the city filed it

This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Concord Widmer Limited is constructing a 47-storey residential condominium building at 40-58 Widmer Street. The site is located on the west side Widmer Street between Adelaide Street West and Richmond Street West. The west sidewalk and a 1.5 metre wide portion of the most westerly curb lane on Widmer Street, between a point 45 metres north of Adelaide Street West and a point 66 metres further north, are currently closed for construction staging operations.

Show the rest of As the city filed it, 571 more characters as filed

Toronto and East York Community Council, at its meeting on September 16, 2020, approved the subject construction staging area on Widmer Street from September 16, 2020 to June 30, 2022. The developer has requested an extension of the duration of the construction staging area on Widmer Street, as the site has experienced COVID-19 related construction delays. Transportation Services is requesting authorization to extend the duration of the construction staging areas from January 27, 2023 to May 31, 2023 to allow for the construction of the development to be completed.

Staff recommended

The Director, Traffic Management, Transportation Services, recommends that: 1. Toronto and East York Community Council authorize the continuation of the closure of the west sidewalk and a 1.5 metre wide portion of the most westerly curb lane on Widmer Street, between a point 45 metres north of Adelaide Street West and a point 66 metres further north from January 27, 2023 to May 31, 2023. 2. Toronto and East York Community Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.

Show the rest of Staff recommended, 2,429 more characters as filed

3. Toronto and East York Community Council direct the applicant to continue to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 4. Toronto and East York Community Council direct the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 5. Toronto and East York Community Council direct the applicant to continue to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 6. Toronto and East York Community Council direct the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 7. Toronto and East York Community Council direct the applicant to continue to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 8. Toronto and East York Community Council direct the applicant to continue to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 9. Toronto and East York Community Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 10. Toronto and East York Community Council direct the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 11. Toronto and East York Community Council direct that Widmer Street be returned to its pre-construction traffic and parking regulations when the project is complete.