The filed record
2112-2114 Yonge Street (Hillsdale Avenue West) - Construction Staging Area Time Extension
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2023-01-26 · Toronto and East York Community Council · adopted
As filed
The Toronto and East York Community Council: 1. Authorized the continuation of the closure of the south sidewalk and a 5.2-metre-wide portion of the eastbound curb lane on Hillsdale Avenue West, between Yonge Street and a point 46 metres west, from January 27, 2023 to December 31, 2023. 2. Directed the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.
Show the rest of As filed, 1,985 more characters as filed
3. Directed the applicant to continue to ensure that the existing sidewalks and/or any proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 4. Directed the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications. 5. Directed the applicant to continue to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 6. Directed the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 7. Directed the applicant to continue to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 8. Directed the applicant to continue to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 9. Directed the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 10. Directed that Hillsdale Avenue West and Yonge Street be returned to their pre-construction traffic and parking regulations when the project is complete.
On the agenda
As the city filed it
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. 2114 Yonge Street Incorporated, is constructing a 10-storey residential condominium building with ground floor retail at 2112 -2114 Yonge Street. The site is located on the southwest corner of Yonge Street and Hillsdale Avenue West. The south sidewalk and a 5.2-metre-wide portion of the eastbound curb lane on Hillsdale Avenue West, between Yonge Street and a point 46 metres west, are currently closed for construction staging operations.
Show the rest of As the city filed it, 600 more characters as filed
Toronto and East York Community Council, at its meeting on May 10, 2021, approved the subject construction staging area on Hillsdale Avenue West from May 20, 2021 to December 31, 2022. The developer has requested an extension of the duration of the construction staging area on Hillsdale Avenue West, due to delays caused by issues with the high water table during underground work. Transportation Services is requesting authorization to extend the duration of the construction staging areas from January 27, 2023 to December 31, 2023 to allow for the construction of the development to be completed.
Staff recommended
The Director, Traffic Management, Transportation Services, recommends that: 1. Toronto and East York Community Council authorize the continuation of the closure of the south sidewalk and a 5.2-metre-wide portion of the eastbound curb lane on Hillsdale Avenue West, between Yonge Street and a point 46 metres west, from January 27, 2023 to December 31, 2023. 2. Toronto and East York Community Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.
Show the rest of Staff recommended, 2,281 more characters as filed
3. Toronto and East York Community Council direct the applicant to continue to ensure that the existing sidewalks and/or any proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 4. Toronto and East York Community Council direct the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 5. Toronto and East York Community Council direct the applicant to continue to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 6. Toronto and East York Community Council direct the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 7. Toronto and East York Community Council direct the applicant to continue to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 8. Toronto and East York Community Council direct the applicant to continue to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 9. Toronto and East York Community Council direct the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 10. Toronto and East York Community Council direct that Hillsdale Avenue West and Yonge Street be returned to their pre-construction traffic and parking regulations when the project is complete.
On the record
More from this meeting
- 17 St. Andrew Street - Zoning Amendment Application - Decision Report - ApprovalFiled record
- 22-32 Scollard Street and 21-25 Davenport Road - Zoning By-law Amendment Application - Decision Report - RefusalFiled record
- 69 Yorkville Avenue - Official Plan and Zoning By-law Amendment Application - Decision Report - RefusalFiled record
- 39-47 Camden Street - Zoning Amendment Application - Appeal ReportFiled record
- 45 The Esplanade - Official Plan and Zoning By-law Amendment Applications - Appeal ReportFiled record
- 1-11 Bloor Street West and 768-784 Yonge Street - Zoning By-Law Amendment Application - Appeal ReportFiled record