1-25 Defries Street - Construction Staging Area Time Extension
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2023-01-26 · Toronto and East York Community Council · adopted
As filed
The Toronto and East York Community Council: 1. Authorized the continuation of the closure of a 3.2 metre-wide portion of the northbound curb lane on Defries Street, between Labatt Avenue and Mark Street, from January 27, 2023 to December 31, 2023. 2. Directed the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.
Show the rest of As filed, 2,040 more characters as filed
3. Directed the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications. 4. Directed the applicant to continue to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 5. Directed the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 6. Directed the applicant to continue to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 7. Directed the applicant to continue to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 8. Directed the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 9. Directed the applicant to continue to establish a Construction Management Working Group that meets monthly and invite local stakeholders including Transportation Services, Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours and local resident groups. 10. Directed that Defries Street and Mark Street be returned to their pre-construction traffic and parking regulations when the project is complete.
On the agenda
As the city filed it
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Broccolini is constructing a 37-storey condominium with 580 residential units, at 1-25 Defries Street. The site is bounded by Mark Street to the north, Bayview Avenue to the east, Labatt Avenue to the south and Defries Street to the west. A 3.2 metre-wide portion of the northbound curb lane on Defries Street, between Labatt Avenue and Mark Street, is currently closed for construction staging operations.
Show the rest of As the city filed it, 759 more characters as filed
Toronto and East York Community Council, at its meeting on April 21, 2021, approved the subject construction staging area from April 22, 2021 to April 30, 2022. At the time, the developer indicated they would require the staging area for a total of 24 months, from April 22, 2021 to April 30, 2023. As the previous permit was only approved for a 12-month period, and as the site has experienced COVID-19 related construction delays and labour issues, the developer has requested an extension of the duration of the construction staging area. Transportation Services is requesting authorization to extend the duration of the construction staging area from January 27, 2023 to December 31, 2023, to allow for the construction of the development to be completed.
Staff recommended
The Director, Traffic Management, Transportation Services, recommends that: 1. Toronto and East York Community Council authorize the continuation of the closure of a 3.2 metre-wide portion of the northbound curb lane on Defries Street, between Labatt Avenue and Mark Street, from January 27, 2023 to December 31, 2023. 2. Toronto and East York Community Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.
Show the rest of Staff recommended, 2,337 more characters as filed
3. Toronto and East York Community Council direct the applicant to continue to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 4. Toronto and East York Community Council direct the applicant to continue to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 5. Toronto and East York Community Council direct the applicant to continue to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 6. Toronto and East York Community Council direct the applicant to continue to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 7. Toronto and East York Community Council direct the applicant to continue to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 8. Toronto and East York Community Council direct the applicant to continue to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 9. Toronto and East York Community Council direct the applicant to continue to establish a construction management working group that meets monthly and invite local stakeholders including Transportation Services, Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours, and local resident groups. 10. Toronto and East York Community Council direct that Defries Street and Mark Street be returned to their pre-construction traffic and parking regulations when the project is complete.
On the record
More from this meeting
- 17 St. Andrew Street - Zoning Amendment Application - Decision Report - ApprovalFiled record
- 22-32 Scollard Street and 21-25 Davenport Road - Zoning By-law Amendment Application - Decision Report - RefusalFiled record
- 69 Yorkville Avenue - Official Plan and Zoning By-law Amendment Application - Decision Report - RefusalFiled record
- 39-47 Camden Street - Zoning Amendment Application - Appeal ReportFiled record
- 45 The Esplanade - Official Plan and Zoning By-law Amendment Applications - Appeal ReportFiled record
- 1-11 Bloor Street West and 768-784 Yonge Street - Zoning By-Law Amendment Application - Appeal ReportFiled record