The filed record
90-104 Queen Street East and 3 Mutual Street - Construction Staging Area
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2023-02-23 · Toronto and East York Community Council · amended
As filed
The Toronto and East York Community Council: 1. Authorized the closure of the east side sidewalk and an 8.2 metre wide portion of the northbound curb lane on Mutual Street, between Queen Street East and Richard Bigley Lane, and provision of a temporary pedestrian walkway within the closed portion of Mutual Street, from February 24, 2023 to March 1, 2024. 2. Designated Mutual Street, between Queen Street East and Richard Bigley Lane, as one-way for northbound traffic only.
Show the rest of As filed, 4,535 more characters as filed
3. Prohibited westbound left turns anytime, from Richard Bigley Lane onto Mutual Street. 4. Rescinded the existing parking machine regulation in effect from 8:00 a.m. to 9:00 p.m., Monday to Saturday; and 1:00 p.m. to 9:00 p.m. Sunday, on the east side of Mutual Street, between Queen Street East and Richard Bigley Lane. 5. Prohibited stopping at all times on the east side of Mutual Street, between Queen Street East and Richard Bigley Lane. 6. Directed the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 7. Directed the applicant to construct (as per the City's engineer approved specifications) and maintain a fully covered, protected and unobstructed walkway, compliant with the Accessibility for Ontarians with Disabilities Act, for all pedestrians, including for those with mobility devices for the entire duration of the construction staging area permit 8. Directed the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 9. Directed the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications. 10. Directed the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 11. Directed the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 12. Directed the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 13. Directed the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 14. Directed the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 15. Directed the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 16. Directed the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes. 17. Directed that Yorkville Avenue and Cumberland Street be returned to its pre-construction traffic and parking regulations when the project is complete. 18. Directed the applicant to establish a construction management working group that meets monthly and invite local stakeholders including Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours, local resident groups, local Business Improvement Areas and local school administration. 19. Directed that the occupation permit for construction staging on Mutual Street be conditional, subject to there being no conflicts with Metrolinx transit project construction. 20. Directed that Mutual Street be returned to its pre-construction traffic and parking regulations when the project is complete. 21. Directed the applicant to create a publicly accessible website with regular construction updates and post the website address on the construction site hoarding, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 22. Directed the applicant to mitigate light pollution by installing a shield/barrier on any lighting standards in close proximity to adjacent residential properties, such as cranes. 23. Directed the applicant to email monthly construction progress reports to the local Councillor, local residents' association and the Business Improvement Area Board of Management.
On the agenda
As the city filed it
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Citi-Core Construction Management Ltd is constructing a 34-storey mixed-use residential building with ground floor retail space at 90-104 Queen Street East and 3 Mutual Street. The site is located at the north-east corner of Queen Street East and Mutual Street. Transportation Services is requesting
Show the rest of As the city filed it, 319 more characters as filed
approval to temporarily close the east sidewalk and a portion of the northbound curb lane on Mutual Street, and temporarily designate a section of Mutual Street abutting the site as one-way northbound, for a period of 34 months from February 24, 2023 to November 30, 2025, to facilitate construction staging operations.
Staff recommended
The Director, Traffic Management, Transportation Services, recommends that: 1. Toronto and East York Community Council authorize the closure of the east side sidewalk and an 8.2 metre wide portion of the northbound curb lane on Mutual Street, between Queen Street East and Richard Bigley Lane, and provision of a temporary pedestrian walkway within the closed portion of Mutual Street, from February 24, 2023 to November 30, 2025.
Show the rest of Staff recommended, 4,541 more characters as filed
2. Toronto and East York Community Council designate Mutual Street, between Queen Street East and Richard Bigley Lane, as one-way for northbound traffic only. 3. Toronto and East York Community Council prohibit westbound left turns anytime, from Richard Bigley Lane onto Mutual Street. 4. Toronto and East York Community Council rescind the existing parking machine regulation in effect from 8:00 a.m. to 9:00 p.m., Monday to Saturday; and 1:00 p.m. to 9:00 p.m. Sunday, on the east side of Mutual Street, between Queen Street East and Richard Bigley Lane. 5. Toronto and East York Community Council prohibit stopping at all times on the east side of Mutual Street, between Queen Street East and Richard Bigley Lane. 6. Toronto and East York Community Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 7. Toronto and East York Community Council direct the applicant to construct (as per the City's engineer approved specifications) and maintain a fully covered, protected and unobstructed walkway, compliant with the Accessibility for Ontarians with Disabilities Act, for all pedestrians, including for those with mobility devices for the entire duration of the construction staging area permit 8. Toronto and East York Community Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 9. Toronto and East York Community Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 10. Toronto and East York Community Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 11. Toronto and East York Community Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 12. Toronto and East York Community Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 13. Toronto and East York Community Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 14. Toronto and East York Community Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 15. Toronto and East York Community Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 16. Toronto and East York Community Council direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes. 17. Toronto and East York Community Council direct that Yorkville Avenue and Cumberland Street be returned to its pre-construction traffic and parking regulations when the project is complete. 18. Toronto and East York Community Council direct the applicant to provide monthly community meetings, to discuss any concerns raised by the community. 19. Toronto and East York Community Council direct that the occupation permit for construction staging on Mutual Street be conditional, subject to there being no conflicts with Metrolinx transit project construction. 20. Toronto and East York Community Council direct that Mutual Street be returned to its pre-construction traffic and parking regulations when the project is complete.
On the record
More from this meeting
- Naming of a Public Lane South of Innes Avenue extending westerly from Caledonia Road to Gilbert AvenueFiled record
- Naming of an existing Public Lane south of Queen Street East, extending between Morse Street and Carlaw AvenueFiled record
- 820 Church Street - Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 1235-1255 Bay Street - Official Plan and Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 234-250 King Street East and 162 Princess Street - Zoning By-law Amendment Application - Removal of Holding Symbol ("h") - Decision Report - ApprovalFiled record
- 975 Danforth Avenue - Zoning By-law Amendment Application - Appeal ReportFiled record