The decision
2023-06-14 · Toronto City Council · adopted
As filed
City Council on June 14 and 15, 2023, adopted the following: 1. City Council authorize the closure of the north side sidewalk and westbound curb lane on Bloor Street West, between Indian Road and a point 77.0 metres west, and provision of a temporary pedestrian walkway within the closed portion of the westbound curb lane, from June 15, 2023 to November 30, 2025. 2. City Council authorize the closure of the west sidewalk and a 1.6 metre wide portion of the southbound curb lane on Indian Road, between Bloor Street West and a point 54.0 metres north of Bloor Street West, and provision of a temporary pedestrian walkway within the closed portion of the southbound curb lane, from June 15, 2023 to November 30, 2025.
Show the rest of As filed, 3,912 more characters as filed
3. City Council rescind the existing parking machine regulation on the north side of Bloor Street West, between Indian Road and a point 77 metres west, from 8:00 a.m. to 6:00 p.m., Monday to Saturday, for a maximum period of three hours and at a rate of $2.00 per hour. 4. City Council rescind the existing no stopping prohibition on the north side of Bloor Street West, between a point 51.0 metres west of Indian Road and a point 83 metres east of Indian Road. 5. City Council prohibit stopping at all times on the north side of Bloor Street West, between a point 77 metres west of Indian Road and a point 83.0 metres east of Indian Road. 6. City Council rescind the existing no parking prohibition in effect during all times on both sides of Indian Road, between Bloor Street West and a point 54 metres north. 7. City Council prohibit stopping at all times on both sides of Indian Road, between Bloor Street West and a point 54 metres north. 8. City Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 9. City Council direct the applicant to construct (as per the City's Engineer approved specifications) and maintain a fully covered, protected and unobstructed walkway, compliant with the Accessibility for Ontarians with Disabilities Act , for all pedestrians, including for those with mobility devices for the entire duration of the construction staging area permit 10. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 11. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications. 12. City Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 13. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 14. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 15. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 16. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 17. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 18. City Council direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes. 19. City Council direct that Bloor Street West and Indian Road be returned to its pre-construction traffic and parking regulations when the project is complete.
On the agenda
As the city filed it
As the Toronto Transit Commission (TTC) operates a transit service on Bloor Street West, City Council approval of this report is required. Mattamy (Bloor) Limited is constructing a 13-storey residential building at 1660 Bloor Street West. The site is located at the north-west corner of Bloor Street West and Indian Road. Transportation Services is requesting approval to temporarily close the north sidewalk and a portion of the westbound curb lane on Bloor Street West, and temporarily close the west sidewalk and a portion of the southbound curb lane on Indian Road, for a period of 30 months from June 15, 2023 to November 30, 2025, to facilitate construction staging operations.
Show the rest of As the city filed it, 352 more characters as filed
Pedestrian movements will be maintained on the north side of Bloor Street West and the west side of Indian Road abutting the site. The bike lane on the north side of Bloor Street West will also be maintained. The construction staging area will result in the temporary loss of two on-street parking machine spaces on the north side of Bloor Street West.
Staff recommended
The Director, Traffic Management, Transportation Services, recommends that: 1. City Council authorize the closure of the north side sidewalk and westbound curb lane on Bloor Street West, between Indian Road and a point 77.0 west, and provision of a temporary pedestrian walkway within the closed portion of the westbound curb lane, from June 15, 2023 to November 30, 2025. 2. City Council authorize the closure of the west sidewalk and a 1.6 metre wide portion of the southbound curb lane on Indian Road, between Bloor Street West and a point 54.0 metres north of Bloor Street west, and provision of a temporary pedestrian walkway within the closed portion of the southbound curb lane, from June 15, 2023 to November 30, 2025.
Show the rest of Staff recommended, 3,903 more characters as filed
3. City Council rescind the existing parking machine regulation on the north side of Bloor Street West, between Indian Road and a point 77 metres west, from 8:00 a.m. to 6:00 p.m., Monday to Saturday, for a maximum period of three hours and at a rate of $2.00 per hour. 4. City Council rescind the existing no stopping prohibition on the north side of Bloor Street West, between a point 51.0 metres west of Indian Road and a point 83 metres east of Indian Road. 5. City Council prohibit stopping at all times on the north side of Bloor Street West, between a point 77 metres west of Indian Road and a point 83.0 metres east of Indian Road. 6. City Council rescind the existing no parking prohibition in effect during all times on both sides of Indian Road, between Bloor Street West and a point 54 metres north. 7. City Council prohibit stopping at all times on both sides of Indian Road, between Bloor Street West and a point 54 metres north. 8. City Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 9. City Council direct the applicant to construct (as per the City's engineer approved specifications) and maintain a fully covered, protected and unobstructed walkway, compliant with the Accessibility for Ontarians with Disabilities Act, for all pedestrians, including for those with mobility devices for the entire duration of the construction staging area permit 10. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 11. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 12. City Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 13. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 14. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 15. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 16. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 17. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 18. City Council direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes. 19. City Council direct that Bloor Street West and Indian Road be returned to its pre-construction traffic and parking regulations when the project is complete.
Considered
2023-05-24 · Toronto and East York Community Council · adopted
Decision as filed
The Toronto and East York Community Council recommends that: 1. City Council authorize the closure of the north side sidewalk and westbound curb lane on Bloor Street West, between Indian Road and a point 77.0 west, and provision of a temporary pedestrian walkway within the closed portion of the westbound curb lane, from June 15, 2023 to November 30, 2025. 2. City Council authorize the closure of the west sidewalk and a 1.6 metre wide portion of the southbound curb lane on Indian Road, between Bloor Street West and a point 54.0 metres north of Bloor Street west, and provision of a temporary pedestrian walkway within the closed portion of the southbound curb lane, from June 15, 2023 to November 30, 2025.
Show the rest of Decision as filed, 3,911 more characters as filed
3. City Council rescind the existing parking machine regulation on the north side of Bloor Street West, between Indian Road and a point 77 metres west, from 8:00 a.m. to 6:00 p.m., Monday to Saturday, for a maximum period of three hours and at a rate of $2.00 per hour. 4. City Council rescind the existing no stopping prohibition on the north side of Bloor Street West, between a point 51.0 metres west of Indian Road and a point 83 metres east of Indian Road. 5. City Council prohibit stopping at all times on the north side of Bloor Street West, between a point 77 metres west of Indian Road and a point 83.0 metres east of Indian Road. 6. City Council rescind the existing no parking prohibition in effect during all times on both sides of Indian Road, between Bloor Street West and a point 54 metres north. 7. City Council prohibit stopping at all times on both sides of Indian Road, between Bloor Street West and a point 54 metres north. 8. City Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 9. City Council direct the applicant to construct (as per the City's Engineer approved specifications) and maintain a fully covered, protected and unobstructed walkway, compliant with the Accessibility for Ontarians with Disabilities Act, for all pedestrians, including for those with mobility devices for the entire duration of the construction staging area permit 10. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 11. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications. 12. City Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 13. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 14. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 15. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 16. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 17. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 18. City Council direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes. 19. City Council direct that Bloor Street West and Indian Road be returned to its pre-construction traffic and parking regulations when the project is complete.
2023-06-14 · Toronto City Council · adopted
On the record
More from this meeting
- Naming of an existing Public Lane South of Hallam Street extending between Delaware Avenue and Concord AvenueFiled record
- 35, 41, 95 High Park Avenue, 66, 102-116 Pacific Avenue - Zoning By-law Amendment Application - Removal of Holding Symbol ("H") - Decision Report - ApprovalFiled record
- 3239-3251 Dundas Street West - Zoning By-law Amendment and Rental Housing Demolition Application - Decision Report - ApprovalFiled record
- 31-37 Gladstone Avenue - Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 124 Bedford Road - Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 555 Davenport Road - Official Plan and Zoning By-law Amendment Application - Decision Report - ApprovalFiled record