Report Back on Metrolinx's Ontario Line Construction within the Toronto and East York District
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2023-06-14 · Toronto City Council · adopted
As filed
City Council on June 14 and 15, 2023, adopted the following: 1. City Council request that prior to Metrolinx accessing Jimmie Simpson Park to remove the retaining wall that the City receive a formal written undertaking for replacement of the wading pool, replacement of the playscape and without the public release of the planned replacement wall. 2. City Council direct the Deputy City Manager, Community and Social Services to report to the July 5, 2023 meeting of the Planning and Housing Committee on the current issues faced by Fontbonne Ministries and the tenants related to the construction of the above ground Ontario Line, and replacement of rooming houses and low income tenants facing eviction with the construction of the Ontario Line.
Show the rest of As filed, 390 more characters as filed
3. City Council request the Deputy City Manager, Infrastructure and Development Services to report back to the July 6, 2023 meeting of the Economic and Community Development Committee on how a formal project labour agreement for the Ontario Line can be secured to create measurable construction hour targets for apprentices and pre-apprentices from groups previously identified by the City.
On the agenda
As the city filed it
Metrolinx's Ontario Line will be approximately 15.6 kilometres in length and will include 15 stations along its route. The Ontario Line will connect to other higher-order transit options including the Eglinton Crosstown LRT, Line 1, Line 2, and to the GO network, in addition to numerous TTC streetcar and bus routes. The purpose of this report is to provide additional information requested by the Subcommittee on Metrolinx's
Show the rest of As the city filed it, 739 more characters as filed
Ontario Line Construction within the boundaries of Toronto and East York Community Council (TEYCC), including details on: - costs of awarded contracts and the companies that make up the consortiums delivering the work; - federal funding; - provincial plans for community benefits; - engagement with Business Improvement Areas and available supports for businesses along the alignment; - ongoing activities to manage traffic congestion, including traffic management plans and permit conditions, and other construction impacts; - noise and vibration levels; - plans for tree retention and to approaches to mitigate impacts to parks during construction; and - details of affordable housing plans and impacts to housing, amongst other matters.
Staff recommended
The Executive Director, Transit Expansion Division recommends that: 1. Toronto and East York Community Council receive this report for information.
Considered
2023-05-24 · Toronto and East York Community Council · amended
Decision as filed
The Toronto and East York Community Council recommends that: 1. City Council request that prior to Metrolinx accessing Jimmie Simpson Park to remove the retaining wall that the City receive a formal written undertaking for replacement of the wading pool, replacement of the playscape and without the public release of the planned replacement wall. 2. City Council direct the Deputy City Manager, Community and Social Services to report to the July 5, 2023 meeting of the Planning and Housing Committee on the current issues faced by Fontbonne Ministries and the tenants related to the construction of the above ground Ontario Line, and replacement of rooming houses and low income tenants facing eviction with the construction of the Ontario Line.
Show the rest of Decision as filed, 390 more characters as filed
3. City Council request the Deputy City Manager, Infrastructure and Development Services to report back to the July 6, 2023 meeting of the Economic and Community Development Committee on how a formal project labour agreement for the Ontario Line can be secured to create measurable construction hour targets for apprentices and pre-apprentices from groups previously identified by the City.
2023-06-14 · Toronto City Council · adopted
On the record
More from this meeting
- Naming of an existing Public Lane South of Hallam Street extending between Delaware Avenue and Concord AvenueFiled record
- 35, 41, 95 High Park Avenue, 66, 102-116 Pacific Avenue - Zoning By-law Amendment Application - Removal of Holding Symbol ("H") - Decision Report - ApprovalFiled record
- 3239-3251 Dundas Street West - Zoning By-law Amendment and Rental Housing Demolition Application - Decision Report - ApprovalFiled record
- 31-37 Gladstone Avenue - Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 124 Bedford Road - Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 555 Davenport Road - Official Plan and Zoning By-law Amendment Application - Decision Report - ApprovalFiled record