Toronto and East York Community Council · 2023-05-24 · 2023.TE5.46

The filed record

Report Back on Metrolinx's Ontario Line Construction within the Toronto and East York District

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2023-06-14 · Toronto City Council · adopted

As filed

City Council on June 14 and 15, 2023, adopted the following: 1. City Council request that prior to Metrolinx accessing Jimmie Simpson Park to remove the retaining wall that the City receive a formal written undertaking for replacement of the wading pool, replacement of the playscape and without the public release of the planned replacement wall. 2. City Council direct the Deputy City Manager, Community and Social Services to report to the July 5, 2023 meeting of the Planning and Housing Committee on the current issues faced by Fontbonne Ministries and the tenants related to the construction of the above ground Ontario Line, and replacement of rooming houses and low income tenants facing eviction with the construction of the Ontario Line.

Show the rest of As filed, 390 more characters as filed

3. City Council request the Deputy City Manager, Infrastructure and Development Services to report back to the July 6, 2023 meeting of the Economic and Community Development Committee on how a formal project labour agreement for the Ontario Line can be secured to create measurable construction hour targets for apprentices and pre-apprentices from groups previously identified by the City.

On the agenda

As the city filed it

Metrolinx's Ontario Line will be approximately 15.6 kilometres in length and will include 15 stations along its route. The Ontario Line will connect to other higher-order transit options including the Eglinton Crosstown LRT, Line 1, Line 2, and to the GO network, in addition to numerous TTC streetcar and bus routes. The purpose of this report is to provide additional information requested by the Subcommittee on Metrolinx's

Show the rest of As the city filed it, 739 more characters as filed

Ontario Line Construction within the boundaries of Toronto and East York Community Council (TEYCC), including details on: - costs of awarded contracts and the companies that make up the consortiums delivering the work; - federal funding; - provincial plans for community benefits; - engagement with Business Improvement Areas and available supports for businesses along the alignment; - ongoing activities to manage traffic congestion, including traffic management plans and permit conditions, and other construction impacts; - noise and vibration levels; - plans for tree retention and to approaches to mitigate impacts to parks during construction; and - details of affordable housing plans and impacts to housing, amongst other matters.

Staff recommended

The Executive Director, Transit Expansion Division recommends that: 1. Toronto and East York Community Council receive this report for information.

Considered

  • 2023-05-24 · Toronto and East York Community Council · amended

    Decision as filed

    The Toronto and East York Community Council recommends that: 1. City Council request that prior to Metrolinx accessing Jimmie Simpson Park to remove the retaining wall that the City receive a formal written undertaking for replacement of the wading pool, replacement of the playscape and without the public release of the planned replacement wall. 2. City Council direct the Deputy City Manager, Community and Social Services to report to the July 5, 2023 meeting of the Planning and Housing Committee on the current issues faced by Fontbonne Ministries and the tenants related to the construction of the above ground Ontario Line, and replacement of rooming houses and low income tenants facing eviction with the construction of the Ontario Line.

    Show the rest of Decision as filed, 390 more characters as filed

    3. City Council request the Deputy City Manager, Infrastructure and Development Services to report back to the July 6, 2023 meeting of the Economic and Community Development Committee on how a formal project labour agreement for the Ontario Line can be secured to create measurable construction hour targets for apprentices and pre-apprentices from groups previously identified by the City.

  • 2023-06-14 · Toronto City Council · adopted