The decision

2024-05-22 · Toronto City Council · adopted

As filed

City Council on May 22 and 23, 2024, adopted the following: 1. City Council affirm its decision to state its intention to designate the property at 505 University Avenue (including entrance address at 136 Edward Street) under Part IV, Section 29 of the Ontario Heritage Act as set out in Council's decision in Item 2024.PH9.1 on February 6, 2024. 2. City Council authorize the City Solicitor to introduce the Bill in City Council designating the property under Part IV, Section 29 of the Ontario Heritage Act.

On the agenda

As the city filed it

This report recommends that Council affirm its decision of February 6, 2024 (Item PH9.1) stating its intention to designate the property at 505 University Avenue (including entrance address at 136 Edward Street) under Part IV, Section 29 of the Ontario Heritage Act. The City has received an objection on behalf of the property owner to the Notice of Intention to Designate within the statutory timeline. Located on the northeast corner of University Avenue and Edward Street, the property at 505 University Avenue contains the Shell Oil Building designed by the prominent architectural firm of Marani & Morris.

Show the rest of As the city filed it, 1,256 more characters as filed

Originally intended to be constructed to a height of 20-storeys, the building was erected in two phases, with the first 13 storeys completed in 1958 and the uppermost 7 storeys added in 1966. Commissioned by Shell Oil, the building served as the global firm's Canadian headquarters from 1958 to 1983. City Council has until June 9, 2024, 90 days from the date of the end of the objection period, or 120 days from the issuance of the Notice of Intention to Designate, to make a decision on this objection as per the timeline under the Ontario Heritage Act. Staff have reviewed the objections raised by the owner and are of the opinion that despite these objections, the property meets Ontario Regulation 9/06, the criteria prescribed for municipal designation under Part IV, Section 29 of the Ontario Heritage Act, under 6 of 9 possible criteria for its design/physical, historical/associative, and contextual values. As the property has cultural heritage value or interest and meets the prescribed criteria pursuant to Part IV, Section 29 of the Ontario Heritage Act, this property should be designated. Designation enables Council to review proposed alterations for the property, enforce heritage property standards and maintenance, and refuse demolition.

Staff recommended

The Interim Chief Planner and Executive Director, City Planning recommends that: 1. City Council affirm its decision to state its intention to designate the property at 505 University Avenue (Including entrance address at 136 Edward Street) under Part IV, Section 29 of the Ontario Heritage Act as set out in Council Decision PH9.1 on February 6, 2024. 2. City Council authorize the City Solicitor to introduce the Bill in Council designating the property under Part IV, Section 29 of the Ontario Heritage Act.