109 Erskine Avenue - Construction Staging Area
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2024-12-03 · North York Community Council · amended
As filed
North York Community Council: 1. Authorized the closure of the south sidewalk and a 2.4 metre wide portion of the eastbound curb lane on Erskine Avenue, between a point 27 metres west of Redpath Avenue and a point 30 metres further west, and a provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane, from December 4, 2024 to September 30, 2025. 2. Prohibited stopping at all times on the south side of Erskine Avenue, between a point 27 metres west of Redpath Avenue and a point 30 metres further west.
Show the rest of As filed, 3,322 more characters as filed
3. Directed the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed and to be cleared of any construction debris and made safe. 4. Directed the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the City engineer and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act (AODA). 5. Directed the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 6. Directed the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 7. Directed the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 8. Directed the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 9. Directed the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 10. Directed the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 11. Directed the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 12. Directed the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 13. Directed the applicant, in consultation with Transportation Services, to maintain any bicycle lanes, and install appropriate signage to inform drivers and cyclists of any changes to the bicycle lanes. 14. Directed that Erskine Avenue be returned to its pre-construction traffic and parking regulations when the project is complete. 15. Directed the applicant to cooperate with and provide all necessary assistance to the City Engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure with the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work. 16. Directed the applicant to provide monthly community meetings, to discuss any concerns raised by the community.
On the agenda
As the city filed it
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. LCG Residential Builders Ltd., is constructing a 22-storey residential building at 109 Erskine Avenue. The site is located on the south side of Erskine Avenue, approximately 350 metres east of Yonge Street and one parcel west of the southwest corner of Erskine Avenue and Redpath Avenue. Transportation Services is requesting authorization to temporarily close a portion of the eastbound curb lane and the south sidewalk on Erskine Avenue for a period of 17 months, from December 4, 2024 to April 30, 2026, in order to enable construction staging operations for the development.
Show the rest of As the city filed it, 296 more characters as filed
Pedestrians will be redirected into a 1.7 metre covered and protected walkway within the closed portion of the eastbound lane on the south side of Erskine Avenue. It should be noted that construction of the development is currently in progress, operating under a monthly Street Occupation Permit.
Staff recommended
The Director, Traffic Management, Transportation Services, recommends that: 1. North York Community Council authorize the closure of the south sidewalk and a 2.4 metre wide portion of the eastbound curb lane on Erskine Avenue, between a point 27 metres west of Redpath Avenue and a point 30 metres further west, and a provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane, from December 4, 2024 to April 30, 2026 inclusive.
Show the rest of Staff recommended, 3,885 more characters as filed
2. North York Community Council prohibit stopping at all times on the south side of Erskine Avenue, between a point 27 metres west of Redpath Avenue and a point 30 metres further west. 3. North York Community Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed and to be cleared of any construction debris and made safe. 4. North York Community Council direct the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the City engineer and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act (AODA). 5. North York Community Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 6. North York Community Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 7. North York Community Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 8. North York Community Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 9. North York Community Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 10. North York Community Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 11. North York Community Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 12. North York Community Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 13. North York Community Council direct the applicant, in consultation with Transportation Services, to maintain any bicycle lanes, and install appropriate signage to inform drivers and cyclists of any changes to the bicycle lanes. 14. North York Community Council direct that Erskine Avenue be returned to its pre-construction traffic and parking regulations when the project is complete. 15. North York Community Council direct the applicant to cooperate with and provide all necessary assistance to the City Engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure with the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work. 16. North York Community Council direct the applicant to provide monthly community meetings, to discuss any concerns raised by the community.
On the record
More from this meeting
- Wilson Heights Boulevard and Joel Swirsky Boulevard - Traffic Control Signals - Reopened from NY15.32Filed record
- 124 Sandringham Drive - Application to Remove a Tree in a Ravine - Protected AreaFiled record
- 849 Eglinton Avenue East - Official Plan Amendment, Zoning Amendment, and Subdivision Applications - Appeal ReportFiled record
- Lawrence Park Transportation PlanFiled record
- Lawrence Avenue East and Wanless Crescent - Traffic Control SignalsFiled record
- 37 York Ridge Road - Fence ExemptionFiled record