Construction Staging Area - Richmond Street East and Ontario Street (261-285 Queen Street East, 384-410 Richmond Street East and 90 Ontario Street)
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2024-06-26 · Toronto City Council · adopted
As filed
City Council on June 26 and 27, 2024, adopted the following: 1. City Council authorize the closure of the west sidewalk and a 2.2 metre wide portion of the southbound lane on Ontario Street, between Queen Street East and a point 81.2 metres south, from June 27, 2024 to December 31, 2025, inclusive. 2. City Council authorize the closure of the north sidewalk and a 2.1 metre wide portion of the north cycle track on Richmond Street East, between Ontario Street and a point 109.4 metres, and a provision for a temporary 2.1 metre wide walkway and 1.5 metre wide cycle track in the adjacent eastbound traffic lane, from June 27, 2024 to December 31, 2025, inclusive.
Show the rest of As filed, 6,494 more characters as filed
3. City Council rescind the existing parking prohibition in effect at all times on the west side of Ontario Street, between Queen Street East and a point 81.2 metres south, from June 27, 2024 to December 31, 2025, inclusive. 4. City Council rescind the existing parking prohibition in effect at all times on the east side of Ontario Street, between Queen Street East and a point 49.4 metres south, from June 27, 2024 to December 31, 2025, inclusive. 5. City Council prohibit stopping at all times on the west side of Ontario Street, between Queen Street East and a point 81.2 metres south. 6. City Council prohibit stopping at all times on the east side of Ontario Street, between Queen Street East and a point 49.4 metres south. 7. City Council rescind the existing stopping prohibition from 4:00 p.m. to 6:00 p.m., Monday to Friday, on the south side of Queen Street East, between a point 79.6 metres west of Ontario Street and a point 9.1 metres further west. 8. City Council prohibit stopping at all times on the south side of Queen Street East, between a point 79.6 metres west of Ontario Street and a point 9.1 metres further west. 9. City Council rescind the existing parking machine regulation in effect from 8:00 a.m. to 4:00 p.m., 6:00 p.m. to 9:00 p.m., Monday to Friday; 8:00 a.m. to 9:00 p.m., Saturday; 1:00 p.m. to 9:00 p.m., Sunday, at a rate of $2.75 per hour for a maximum period of three hours, on the south side of Queen Street East, between a point 79.6 metres west of Ontario Street and a point 9.1 metres further west. 10. City Council direct the applicant to sweep the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 11. City Council direct the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act. 12. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 13. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas, resident associations and local school administration in advance of any physical road modifications. 14. City Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 15. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 16. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 17. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 18. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 19. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 20. City Council direct the applicant, in consultation with Transportation Services, to maintain any bicycle lanes and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes. 21. City Council direct that Queen Street East, Ontario Street and Richmond Street East be returned to its pre-construction traffic and parking regulations when the project is complete. 22. City Council direct the applicant to cooperate with and provide all necessary assistance to the Chief Engineer and Executive Director, Engineering and Construction Services, staff and representatives carrying out operation, maintenance and construction activities to municipal infrastructure with the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work. 23. City Council direct that the occupation permit for construction staging on Queen Street East, Ontario Street and Richmond Street East be conditional subject to there being no conflicts with Metrolinx transit project construction. 24. City Council direct the applicant to create a publicly accessible website with regular construction updates and post the website address on the construction site hoarding, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 25. City Council direct the applicant to pressure wash the construction site, adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 26. City Council direct the applicant to mitigate light pollution by installing a shield/barrier on any lighting standards in close proximity to adjacent residential properties, such as cranes. 27. City Council direct the applicant to establish a Construction Management Working Group that meets monthly and invite local stakeholders including Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours, local resident groups, local Business Improvement Area Board of Management and local school administration. 28. City Council direct the applicant to email monthly construction progress reports to the local Councillor, local residents' association and Business Improvement Area Board of Management.
On the agenda
As the city filed it
As Richmond Street East is classified as a major arterial street, City Council approval of this report is required. Tricon Residential is constructing a 24-storey and 33-storey buildings at 261-285 Queen Street East, 384-410 Richmond Street East and 90 Ontario Street, respectively. The site is bounded by Queen Street East to the north, Ontario Street to the east, Richmond Street East to the south and existing condominium buildings to the west.
Show the rest of As the city filed it, 629 more characters as filed
Transportation Services is requesting authorization to temporarily close a portion of the southbound curb lane on Ontario Street and a portion of the uni-directional cycle track on north side on Richmond Street East for a period of 19 months, from June 27, 2024 to December 31, 2025 to accommodate construction staging operations. It should be noted that the construction staging area has been installed and is operating under a monthly Street Occupation Permit. Pedestrian operations are accommodated within the closed curb lane on Ontario Street. The dedicated uni-directional cycle track on Richmond Street East is maintained.
Staff recommended
The Director, Traffic Management, Transportation Services, recommends that: 1. City Council authorize the closure of the west sidewalk and a 2.2 metre wide portion of the southbound lane on Ontario Street, between Queen Street East and a point 81.2 metres south, from June 27, 2024 to December 31, 2025, inclusive. 2. City Council authorize the closure of the north sidewalk and a 2.1 metre wide portion of the north cycle track on Richmond Street East, between Ontario Street and a point 109.4 metres, and a provision for a temporary 2.1 metre wide walkway and 1.5 metre wide cycle track in the adjacent eastbound traffic lane, from June 27, 2024 to December 31, 2025, inclusive.
Show the rest of Staff recommended, 5,137 more characters as filed
3. City Council rescind the existing parking prohibition in effect at all times on the west side of Ontario Street, between Queen Street East and a point 81.2 metres south, from June 27, 2024 to December 31, 2025, inclusive. 4. City Council rescind the existing parking prohibition in effect at all times on the east side of Ontario Street, between Queen Street East and a point 49.4 metres south, from June 27, 2024 to December 31, 2025, inclusive. 5. City Council prohibit stopping at all times on the west side of Ontario Street, between Queen Street East and a point 81.2 metres south. 6. City Council prohibit stopping at all times on the east side of Ontario Street, between Queen Street East and a point 49.4 metres south. 7. City Council rescind the existing stopping prohibition from 4:00 p.m. to 6:00 p.m., Monday to Friday, on the south side of Queen Street East, between a point 79.6 metres west of Ontario Street and a point 9.1 metres further west. 8. City Council prohibit stopping at all times on the south side of Queen Street East, between a point 79.6 metres west of Ontario Street and a point 9.1 metres further west. 9. City Council rescind the existing parking machine regulation in effect from 8:00 a.m. to 4:00 p.m., 6:00 p.m. to 9:00 p.m., Monday to Friday; 8:00 a.m. to 9:00 p.m., Saturday; 1:00 p.m. to 9:00 p.m., Sunday, at a rate of $2.75 per hour for a maximum period of three hours, on the south side of Queen Street East, between a point 79.6 metres west of Ontario Street and a point 9.1 metres further west. 10. City Council direct the applicant to sweep the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 11. City Council direct the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the City engineer and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act (AODA). 12. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 13. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 14. City Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 15. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 16. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 17. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 18. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 19. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 20. City Council direct the applicant, in consultation with Transportation Services, to maintain any bicycle lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes. 21. City Council direct that Queen Street East, Ontario Street, and Richmond Street East be returned to its pre-construction traffic and parking regulations when the project is complete. 22. City Council direct the applicant to cooperate with and provide all necessary assistance to the City Engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure with the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work. 23. City Council direct that the occupation permit for construction staging on Queen Street East, Ontario Street, and Richmond Street East be conditional subject to there being no conflicts with Metrolinx transit project construction.
Considered
2024-06-11 · Toronto and East York Community Council · amended
Decision as filed
The Toronto and East York Community Council recommends that: 1. City Council authorize the closure of the west sidewalk and a 2.2 metre wide portion of the southbound lane on Ontario Street, between Queen Street East and a point 81.2 metres south, from June 27, 2024 to December 31, 2025, inclusive. 2. City Council authorize the closure of the north sidewalk and a 2.1 metre wide portion of the north cycle track on Richmond Street East, between Ontario Street and a point 109.4 metres, and a provision for a temporary 2.1 metre wide walkway and 1.5 metre wide cycle track in the adjacent eastbound traffic lane, from June 27, 2024 to December 31, 2025, inclusive.
Show the rest of Decision as filed, 6,494 more characters as filed
3. City Council rescind the existing parking prohibition in effect at all times on the west side of Ontario Street, between Queen Street East and a point 81.2 metres south, from June 27, 2024 to December 31, 2025, inclusive. 4. City Council rescind the existing parking prohibition in effect at all times on the east side of Ontario Street, between Queen Street East and a point 49.4 metres south, from June 27, 2024 to December 31, 2025, inclusive. 5. City Council prohibit stopping at all times on the west side of Ontario Street, between Queen Street East and a point 81.2 metres south. 6. City Council prohibit stopping at all times on the east side of Ontario Street, between Queen Street East and a point 49.4 metres south. 7. City Council rescind the existing stopping prohibition from 4:00 p.m. to 6:00 p.m., Monday to Friday, on the south side of Queen Street East, between a point 79.6 metres west of Ontario Street and a point 9.1 metres further west. 8. City Council prohibit stopping at all times on the south side of Queen Street East, between a point 79.6 metres west of Ontario Street and a point 9.1 metres further west. 9. City Council rescind the existing parking machine regulation in effect from 8:00 a.m. to 4:00 p.m., 6:00 p.m. to 9:00 p.m., Monday to Friday; 8:00 a.m. to 9:00 p.m., Saturday; 1:00 p.m. to 9:00 p.m., Sunday, at a rate of $2.75 per hour for a maximum period of three hours, on the south side of Queen Street East, between a point 79.6 metres west of Ontario Street and a point 9.1 metres further west. 10. City Council direct the applicant to sweep the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 11. City Council direct the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act. 12. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 13. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas, resident associations and local school administration in advance of any physical road modifications. 14. City Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 15. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 16. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 17. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 18. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 19. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 20. City Council direct the applicant, in consultation with Transportation Services, to maintain any bicycle lanes and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes. 21. City Council direct that Queen Street East, Ontario Street and Richmond Street East be returned to its pre-construction traffic and parking regulations when the project is complete. 22. City Council direct the applicant to cooperate with and provide all necessary assistance to the Chief Engineer and Executive Director, Engineering and Construction Services, staff and representatives carrying out operation, maintenance and construction activities to municipal infrastructure with the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work. 23. City Council direct that the occupation permit for construction staging on Queen Street East, Ontario Street and Richmond Street East be conditional subject to there being no conflicts with Metrolinx transit project construction. 24. City Council direct the applicant to create a publicly accessible website with regular construction updates and post the website address on the construction site hoarding, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 25. City Council direct the applicant to pressure wash the construction site, adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 26. City Council direct the applicant to mitigate light pollution by installing a shield/barrier on any lighting standards in close proximity to adjacent residential properties, such as cranes. 27. City Council direct the applicant to establish a Construction Management Working Group that meets monthly and invite local stakeholders including Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours, local resident groups, local Business Improvement Area Board of Management and local school administration. 28. City Council direct the applicant to email monthly construction progress reports to the local Councillor, local residents' association and Business Improvement Area Board of Management.
2024-06-26 · Toronto City Council · adopted
On the record
More from this meeting
- Naming of an existing Public Lane south of Dupont Street, extending east of Manning AvenueFiled record
- Naming of an existing Public Lane west of Glasgow Street north of Cecil StreetFiled record
- Naming of an existing Public Lane west of Spadina Avenue, extending between Oxford Street and Nassau StreetFiled record
- 10-22 Pauline Avenue - Official Plan and Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 245-247 Davenport Road - Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 180-200 Dundas Street West, 123 Edward Street and 65 Centre Avenue - Official Plan and Zoning By-law Amendment Application - Decision Report - ApprovalFiled record