2024-07-10 · Toronto and East York Community Council · amended
As filed
The Toronto and East York Community Council: 1. Authorized the continuation of the closure of the north side sidewalk and a 3.6 metre wide portion of the eastbound lane's north side on Prince Arthur Avenue, between a point 60.6 metres west of Avenue Road and a point 36.5 metres further west and provision of a temporary pedestrian walkway within the closed portion of Prince Arthur Avenue, from July 31, 2024 to September 30, 2024 inclusive.
Show the rest of As filed, 1,629 more characters as filed
2. Rescinded the existing permit parking in effect from 12:01 a.m. to 7:00 a.m. daily, on the odd side of Prince Arthur Avenue, between a point 60.6 metres west of Avenue Road and a point 36.5 metres further west. 3. Rescinded the existing parking machine regulation on the south side of Prince Arthur Avenue, between a point 60.6 metres west of Avenue Road and a point 36.5 metres further west, from 8:00 a.m. to 9:00 p.m., Monday to Saturday and from 1:00 p.m. to 9:00 p.m. Sunday, for a maximum period of three hours and at a rate of $3.00 per hour. 4. Prohibited stopping at all times on both sides of Prince Arthur Avenue, between a point 60.6 metres west of Avenue Road and a point 36.5 metres further west. 5. Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 6. Directed the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 7. Directed that Prince Arthur Avenue be returned to its pre-construction traffic regulations when the project is completed. 8. Directed the applicant to provide monthly updates on the progress of construction and potential impacts to all nearby property owners on Prince Arthur Avenue. 9. Directed the applicant to ensure one-way eastbound traffic operations and access to all driveways/laneways are maintained at all times.
On the agenda
As the city filed it
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Accel Construction Management Inc. is constructing a 7-storey residential condominium building at 10 Prince Arthur Avenue. Currently, the north side sidewalk and a 3.6 metre wide portion of the eastbound lane on Prince Arthur Avenue, between a point 60.6 metres west of Avenue Road and a point 36.5 metres further west is closed to accommodate a construction staging area.
Show the rest of As the city filed it, 712 more characters as filed
Toronto and East York Community Council, at its meeting on June 22, 2023, approved the subject construction staging area on Prince Arthur Avenue from June 23, 2023 to June 30, 2024. The developer has requested an extension of the duration of the construction staging area on Prince Arthur Avenue, as the site has experienced a number of delays due to inclement weather, unforeseen issues with the heritage component, and delays in civil services. Transportation Services is requesting authorization to extend the duration of the construction staging area on Prince Arthur Avenue for an additional 5 months, from July 31, 2024 to December 31, 2024 to allow for the construction of the development to be completed.
Staff recommended
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council authorize the continuation of the closure of the north side sidewalk and a 3.6 metre wide portion of the eastbound lane's north side on Prince Arthur Avenue, between a point 60.6 metres west of Avenue Road and a point 36.5 metres further west and provision of a temporary pedestrian walkway within the closed portion of Prince Arthur Avenue, from July 31, 2024 to December 31, 2024 inclusive.
Show the rest of Staff recommended, 1,591 more characters as filed
2. Toronto and East York Community Council continue to rescind the existing permit parking in effect from 12:01 a.m. to 7:00 a.m. daily, on the odd side of Prince Arthur Avenue, between a point 60.6 metres west of Avenue Road and a point 36.5 metres further west. 3. Toronto and East York Community Council continue to rescind the existing parking machine regulation on the south side of Prince Arthur Avenue, between a point 60.6 metres west of Avenue Road and a point 36.5 metres further west, from 8:00 a.m. to 9:00 p.m., Monday to Saturday and from 1:00 p.m. to 9:00 p.m. Sunday, for a maximum period of three hours and at a rate of $3.00 per hour. 4. Toronto and East York Community Council continue to prohibit stopping at all times on both sides of Prince Arthur Avenue, between a point 60.6 metres west of Avenue Road and a point 36.5 metres further west. 5. Toronto and East York Community Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 6. Toronto and East York Community Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor 7. Toronto and East York Community Council direct that Prince Arthur Avenue be returned to its pre-construction traffic regulations when the project is completed.
On the record
More from this meeting
- Naming of a Public Lane East of Caroline Avenue, Extending Northerly from Eastern AvenueFiled record
- 1337-1355 King Street West - Official Plan and Zoning By-law Amendment, and Rental Housing Demolition Applications - Decision Report - ApprovalFiled record
- 1113-1125 Dundas Street West - Official Plan and Zoning By-law Amendment - Decision Report - ApprovalFiled record
- 61-85 Hanna Avenue and 120 Lynn Williams Street - Draft Plan of Subdivision Application - Decision Report - ApprovalFiled record
- 257-259 and 291 Lake Shore Boulevard East, 2 Small Street and 200 Queens Quay East (Quayside Blocks 1 and 2) - Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 29-39 Pleasant Boulevard - Zoning Amendment Application - Decision Report - ApprovalFiled record