2025-2034 Capital Budget
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2024-10-02 · Toronto Zoo · adopted
As filed
The Board of Management of the Toronto Zoo: 1. Approved the 2025-2034 Capital Budget as shown in Attachment 1 to the report (September 12, 2024) from the Director, Finance, Technology and Innovation, Toronto Zoo. 2. Authorized the Director, Finance, Technology and Innovation to withdraw up to $13.3 million in unrestricted donation funding held by the Toronto Foundation on behalf of the Board for the purposes of funding the 2025-2034 capital budget.
Show the rest of As filed, 644 more characters as filed
3. Approved an increase in total construction costs to be tendered under the construction management contract for the Community Conservation Centre (Welcome Area) from $57.4 million up to $61.0 million in accordance with the approved 2024-2033 capital budget. 4. Authorized the Director, Facilities & Infrastructure or their designate to negotiate and enter into any necessary amendments to the construction management contract for the Community Conservation Centre (Welcome Area) as a result of the adoption of Recommendation 3, on terms acceptable to the Director, Facilities & Infrastructure and in a form satisfactory to the City Solicitor.
On the agenda
As the city filed it
This report submits the Toronto Zoo 2025-2034 Capital Budget of the Toronto Zoo for approval. The Policy & Finance Committee reviewed the 2025-2034 Capital Budget on 2024-09-12 and recommended it for approval by the Board.
Staff recommended
The Director, Finance, Technology and Innovation recommends that: 1. The Board of Management of the Toronto Zoo approve the 2025-2034 Capital Budget as shown in Attachment 1. 2. The Board of Management of the Toronto Zoo authorize the Director, Finance, Technology and Innovation to withdraw up to $13.3 million in unrestricted donation funding held by the Toronto Foundation on behalf of the Board for the purposes of funding the 2025-2034 capital budget.
Show the rest of Staff recommended, 729 more characters as filed
3. The Board of Management of the Toronto Zoo approves an increase in total construction costs to be tendered under the construction management contract for the Community Conservation Centre (Welcome Area) from $57.4 million up to $61.0 million in accordance with the approved 2024-2033 capital budget. 4. The Board of Management of the Toronto Zoo authorize the Director, Facilities & Infrastructure or their designate to negotiate and enter into any necessary amendments to the construction management contract for the Community Conservation Centre (Welcome Area) as a result of the adoption of Recommendation 3, on terms acceptable to the Director, Facilities & Infrastructure and in a form satisfactory to the City Solicitor.
On the record
More from this meeting
- Guardians of Wild - Strategic Plan PresentationFiled record
- Toronto Zoo Operational UpdateFiled record
- 2025-2027 Toronto Zoo Strategic PlanFiled record
- 2025 Operating Plan and BudgetFiled record
- Attendance and Revenue Report - August 2024Filed record
- Toronto Zoo Indigenous Relations - Update on 2024 ActivitiesFiled record