The filed record
Winter Accessibility - Tiger Boardwalk and Habitat Expansion Project - Additional Work
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2024-03-28 · Toronto Zoo · adopted
As filed
The Board of Management of the Toronto Zoo: 1. Authorized the Director, Facilities and Infrastructure, Toronto Zoo, or their designate, to negotiate and amend the Construction Agreement for PO0100379 - Tiger Boardwalk and Habitat Project up to the amount of $4,800,000.00, excluding applicable taxes.
On the agenda
As the city filed it
This report recommends amending the Construction Agreement for PO0100379 - Tiger Boardwalk and Habitat Project in order to complete additional work.
Staff recommended
The Director, Facilities and Infrastructure, Toronto Zoo recommends that: 1. The Board of Management of the Toronto Zoo authorize the Director, Facilities and Infrastructure, Toronto Zoo, or their designate, to negotiate and amend the Construction Agreement for PO0100379 - Tiger Boardwalk and Habitat Project up to the amount of $4,800,000.00, excluding applicable taxes.
On the record
More from this meeting
- 2024 Events PresentationFiled record
- Toronto Zoo Operational UpdateFiled record
- Design and Contract Administration - African Savanna Indoor Viewing and HoldingFiled record
- Attendance and Revenue Report - February 2024Filed record
- 2023 Year-End Health and Safety Status ReportFiled record
- 2023 Year-End Guest Safety ReportFiled record