Update on Electric Ferries Shoreside Infrastructure and Ferry Terminal Improvement Projects
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2025-03-26 · Toronto City Council · amended
As filed
City Council on March 26 and 27, 2025, adopted the following: 1. City Council authorize the City Manager and their designate, as appropriate, to increase the upset limit of the Delivery Agreement for the Shoreside Infrastructure Project, with Toronto Port Lands Company by an additional $10,323,635 net of all applicable taxes and charges ($10,485,091 net of Harmonized Sales Tax recoveries), revising the current Delivery
Show the rest of As filed, 2,000 more characters as filed
Agreement upset limit from $41,800,000 net of all applicable taxes and charges ($42,535,680 net of Harmonized Sales Tax recoveries) to $52,123,635 net of all applicable taxes and charges ($53,020,771 net of Harmonized Sales Tax recoveries), representing an increase of $7,573,945 net of all applicable taxes and charges ($7,687,006 net of Harmonized Sales Tax recoveries) for the charging and docking improvements to be delivered through the Project and an increase of $2,749,690 net of applicable taxes and charges ($2,798,085 net of Harmonized Sales Tax recoveries) for necessary dock wall repairs and modifications at Jack Layton Ferry Terminal. 2. City Council direct the Toronto Port Lands Company, in consultation with relevant City Divisions and Waterfront Toronto to deliver on the City's behalf the project management, design, construction and other necessary components of the Interim Terminal Improvements Project, consistent with the docking and terminal plan from the 2015 winning team of the Jack Layton Ferry Terminal Innovative Design Competition, pursuant to the Delivery Agreement, dated November 28, 2024, between the City of Toronto and the Toronto Port Lands Company for the Shoreside Infrastructure Project, in the budgeted amount of $4,500,000 net of applicable taxes and charges ($4,579,200 net of Harmonized Sales Tax recoveries) and, conditional on approval by the City Manager, direct that Toronto Port Lands Company negotiate, enter into and execute any agreements as necessary with Waterfront Toronto to support the delivery of the Interim Terminal Improvements Project. 3. City Council amend Parks and Recreation's 2025 Capital Budget and 2026-2034 Capital Plan for the Ferry Fleet Replacement and Shoreside sub-project (account CPR126-45-08) in the Special Facilities project, in the amount of $2,687,006 gross and $0 debt, increasing project cost and cash flow commitments in 2027, fully funded by Development Charges (XR2114) for the Shoreside Infrastructure Project.
The vote
Amend Item · Carried, 20-4
The whole record, all 26 members
- Alejandra BravoFor
- Amber MorleyFor
- Anthony PerruzzaAgainst
- Ausma MalikFor
- Brad BradfordAgainst
- Chris MoiseFor
- Dianne SaxeFor
- Frances NunziataFor
- Gord PerksFor
- Jamaal MyersFor
- James PasternakFor
- Jennifer McKelvieAbsent
- Jon BurnsideFor
- Josh MatlowFor
- Lily ChengFor
- Michael ThompsonAbsent
- Mike ColleAgainst
- Nick MantasFor
- Olivia ChowFor
- Parthi KandavelFor
- Paul AinslieFor
- Paula FletcherFor
- Rachel Chernos LinFor
- Shelley CarrollFor
- Stephen HolydayAgainst
- Vincent CrisantiFor
Every name opens that member’s record.
On the agenda
As the city filed it
The purpose of this report is to advise that the City Manager will be submitting a report that provides an update on the Electric Ferries Shoreside Infrastructure and Jack Layton Ferry Terminal improvement projects to City Council for its meeting on March 26, 27 and 28, 2025.
Staff recommended
The City Manager recommends that: 1. City Council receive this report for information.
On the record
More from this meeting
- Introduction of General Bills and Confirming BillsFiled record
- Authority to Negotiate Agreements Related to Queen’s Park North Through Philanthropic Partnerships in Alignment with City of Toronto PrioritiesFiled record
- 40-60 St. Lawrence Avenue - Ontario Land Tribunal Hearing - Request for DirectionsFiled record
- The Growing Crisis of Public Safety in the City of Toronto and the Urgent Need to Seek Clarity on the Date City Staff will Present Long Overdue “Bubble Zone” By-laws to Toronto City Council and Protect the Charter Rights of Those Trying to Access Faith-Based and Other Vulnerable InstitutionsFiled record
- Amending Item 2021.TE26.4 - 33-49 Avenue Road and 136-148 Yorkville Avenue and Creation of New Park at 819 Yonge Street - by Councillor Dianne Saxe, seconded by Councillor Jamaal MyersFiled record
- Call to OrderFiled record