The filed record
Adjustments to Capital Budget, Carry Forward Funding and Future Year Commitments
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2025-05-21 · Toronto City Council · adopted
As filed
City Council on May 21 and 22, 2025, adopted the following: 1. City Council approve the adjustments to carry-forward funding of an additional $250.3 million from unspent capital projects funding as detailed in Appendices 1a and 1b to the report (April 29, 2025) from the Chief Financial Officer and Treasurer, in order to continue work on previously approved capital projects in 2025 and beyond, and that the 2025-2034 Tax and Rate Supported Capital Budget and Plan for respective City Programs and Agencies be adjusted accordingly.
Show the rest of As filed, 286 more characters as filed
2. City Council approve in-year budget adjustments to the 2024 and future year cash flow commitments, as well as reallocations of funding sources for prior Approved Capital Budgets, as detailed in Appendix 2 to the report (April 29, 2025) from the Chief Financial Officer and Treasurer.
On the agenda
As the city filed it
As part of the 2025 Budget process, the 2025-2034 Capital Budget and Plan included $1.438 billion of previously approved unspent funding for capital projects to be carried forward to 2025-2034. This carry forward amount was based on an initial estimate of projected spending available at the time of the budget development, which is prior to the 2024 year-end closing. With the 2024 fiscal year close in February 2025, City Programs and Agencies have finalized the 2024 actual project spending as well as the total carry-forward needed.
Show the rest of As the city filed it, 882 more characters as filed
The purpose of this report is to seek Council's approval for an additional $250.3 million in carry-forward funding for the 2025-2034 period. With the incremental carry-forward request, the total capital carry-forward funding from 2024 to the 2025-2034 Capital Budget and Plan will be $1.689 billion, and the total adjusted 2025 Tax and Rate Supported Capital Budget including previously approved carry forward amount will be $6.098 billion. The revised total carry-forward funding is equivalent to 27.7% of the total 2025 Tax and Rate Supported Capital Budget. This report also brings forward in-year capital budget adjustment requests for previously approved budget and future year commitments, taking into account the recommended incremental carry-forward. Approval of these requests is needed to provide the necessary spending authority to continue with capital project delivery.
Staff recommended
The Chief Financial Officer and Treasurer recommends that: 1. City Council approve the adjustments to carry-forward funding of an additional $250.3 million from unspent capital projects funding as detailed in Appendices 1a and 1b, in order to continue work on previously approved capital projects in 2025 and beyond, and that the 2025-2034 Tax and Rate Supported Capital Budget and Plan for respective City Programs and Agencies be adjusted accordingly.
Show the rest of Staff recommended, 208 more characters as filed
2. City Council approve in-year budget adjustments to the 2024 and future year cash flow commitments, as well as reallocations of funding sources for prior Approved Capital Budgets, as detailed in Appendix 2.
Considered
2025-05-13 · Executive Committee · adopted
Decision as filed
The Executive Committee recommends that: 1. City Council approve the adjustments to carry-forward funding of an additional $250.3 million from unspent capital projects funding as detailed in Appendices 1a and 1b to the report (April 29, 2025) from the Chief Financial Officer and Treasurer, in order to continue work on previously approved capital projects in 2025 and beyond, and that the 2025-2034 Tax and Rate Supported Capital Budget and Plan for respective City Programs and Agencies be adjusted accordingly.
Show the rest of Decision as filed, 286 more characters as filed
2. City Council approve in-year budget adjustments to the 2024 and future year cash flow commitments, as well as reallocations of funding sources for prior Approved Capital Budgets, as detailed in Appendix 2 to the report (April 29, 2025) from the Chief Financial Officer and Treasurer.
2025-05-21 · Toronto City Council · adopted
On the record
More from this meeting
- Improved Active Transportation and Water Access to Toronto Island ParkFiled record
- Ontario-Toronto New Deal - Advancing the Delivery of Transit Oriented Communities along the Eglinton Crosstown West ExtensionFiled record
- Metrolinx Ontario Line - Lower Don Bridge and Minton Place Portal - Temporary Lane Closures on the Don Valley Parkway and F.G. Gardiner Expressway and Temporary Delegation of AuthorityFiled record
- Management Update: Auditor General Recommendations on 9-1-1 Operations and Responses to Calls for Service by the Toronto Police ServiceFiled record
- 2025 Update on SafeTO ImplementationFiled record
- 150 Eighth Street - Education Development Charges ComplaintFiled record