The Public GalleryToronto

General Government Committee · 2025-05-12 · 2025.GG21.15

The filed record

Expropriation of Portions of Properties at the Rear of Jolly Way and the Rear East Side of Jenkinson Way for the Scarborough Rapid Transit Bus Replacement - Stage 2

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2025-05-21 · Toronto City Council · adopted

As filed

City Council on May 21 and 22, 2025, adopted the following: 1. City Council, as approving authority under the Expropriations Act, approve the expropriation of the property interests set out in Appendix A to the revised report (May 7, 2025) from the Executive Director, Corporate Real Estate Management, and as identified on the reference plans attached as Appendix B to the revised report (May 7, 2025) from the Executive Director, Corporate Real Estate Management.

Show the rest of As filed, 2,000 more characters as filed

2. City Council authorize the City, as expropriating authority under the Expropriations Act, to take all necessary steps to comply with the Act, including but not limited to the preparation and registration of Expropriation Plans, and service of Notices of Expropriation, Notices of Election and Notices of Possession, as may be required. 3. City Council authorize severally each of the Executive Director, Corporate Real Estate Management and the Director, Real Estate Services to prepare, execute and serve Offers of Compensation based on a report appraising the market value of the Property Requirements in accordance with the requirements of the Expropriations Act. 4. City Council direct that Confidential Attachment 1 to the revised report (May 7, 2025) from the Executive Director, Corporate Real Estate Management remain confidential until such time as all property transactions related to the Project have been completed and there has been a final determination of the compensation payable in connection with expropriation claims relative to the Project, and authorize the public release of Confidential Attachment 1 to the revised report (May 7, 2025) from the Executive Director, Corporate Real Estate Management, thereafter in consultation with the City Solicitor. Confidential Attachment 1 to the revised report (May 7, 2025) from the Executive Director, Corporate Real Estate Management remains confidential in accordance with the provisions of the City of Toronto Act, 2006, as it pertains to a proposed or pending land acquisition or disposition of land by the City of Toronto, until such time as all property transactions related to the Project have been completed and there has been a final determination of the compensation payable in connection with expropriation claims relative to the Project. Confidential Attachment 1 to the revised report (May 7, 2025) from the Executive Director, Corporate Real Estate Management will be made public at the discretion of the City Solicitor.

On the agenda

As the city filed it

On July 24, 2024, City Council authorized the initiation of expropriation proceedings for temporary easement interests in part of the properties at the rear of Jolly Way and the rear east side of Jenkinson Way for the purpose of accommodating the construction of a dedicated bus roadway (the "Project"). The Project forms part of the Toronto Transit Commission's ("TTC") Scarborough Rapid Transit Bus Replacement and Busway program.

Show the rest of As the city filed it, 870 more characters as filed

This report relates to the second stage of the expropriation process. During the first stage and in accordance with the Expropriations Act, Notices of Application for Approval to Expropriate were served on all applicable "registered owners," and published in the newspaper. Parties with affected interests in the land had 30 days to request an inquiry into whether the proposed taking is fair, sound, and reasonably necessary. No requests were received within the 30-day period, and City Council may now approve the expropriation by this Stage 2 report. If authorized, Expropriation Plans will be registered, and associated notices served. Statutory Offers of Compensation must be served prior to the City taking possession of the expropriated properties. The property requirements are set out in Appendix A and shown on the draft reference plans attached as Appendix B.

Staff recommended

The Executive Director, Corporate Real Estate Management recommends that: 1. City Council, as approving authority under the Expropriations Act (the "Act"), approve the expropriation of the property interests set out in Appendix A (the "Property Requirements") and as identified on the reference plans attached as Appendix B. 2. City Council authorize the City, as expropriating authority under the Act, to take all necessary steps to comply with the Act, including but not limited to the preparation and registration of Expropriation Plans, and service of Notices of Expropriation, Notices of Election and Notices of Possession, as may be required.

Show the rest of Staff recommended, 726 more characters as filed

3. City Council authorize severally each of the Executive Director, Corporate Real Estate Management, and the Director, Real Estate Services to prepare, execute and serve Offers of Compensation based on a report appraising the market value of the Property Requirements in accordance with the requirements of the Act. 4. City Council direct that Confidential Attachment 1 remain confidential until such time as all property transactions related to the Project have been completed and there has been a final determination of the compensation payable in connection with expropriation claims relative to the Project, and authorize the public release of Confidential Attachment 1 thereafter in consultation with the City Solicitor.

Considered

  • 2025-05-12 · General Government Committee · adopted

    Decision as filed

    The General Government Committee recommends that: 1. City Council, as approving authority under the Expropriations Act (the "Act"), approve the expropriation of the property interests set out in Appendix A (the "Property Requirements") to the revised report (May 7, 2025) from the Executive Director, Corporate Real Estate Management, and as identified on the reference plans attached as Appendix B to the revised report (May 7, 2025) from the Executive Director, Corporate Real Estate Management.

    Show the rest of Decision as filed, 1,248 more characters as filed

    2. City Council authorize the City, as expropriating authority under the Act, to take all necessary steps to comply with the Act, including but not limited to the preparation and registration of Expropriation Plans, and service of Notices of Expropriation, Notices of Election and Notices of Possession, as may be required. 3. City Council authorize severally each of the Executive Director, Corporate Real Estate Management, and the Director, Real Estate Services to prepare, execute and serve Offers of Compensation based on a report appraising the market value of the Property Requirements in accordance with the requirements of the Act. 4. City Council direct that Confidential Attachment 1 to the revised report (May 7, 2025) from the Executive Director, Corporate Real Estate Management, remain confidential until such time as all property transactions related to the Project have been completed and there has been a final determination of the compensation payable in connection with expropriation claims relative to the Project, and authorize the public release of Confidential Attachment 1 to the revised report (May 7, 2025) from the Executive Director, Corporate Real Estate Management, thereafter in consultation with the City Solicitor.

  • 2025-05-21 · Toronto City Council · adopted

On the record

The item as the City filed it

More from this meeting

The whole meeting