Making Old Mill Station Accessible
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2025-01-27 · Toronto Transit Commission Board · adopted
As filed
The TTC Board: 1. Authorized the award of Contract W45-8, Old Mill Station - Easier Access III to Maystar General Contractors Inc. in the amount of $25,690,748.88, inclusive of all taxes, on the basis of the lowest-priced acceptable bid. 2. Approved a reallocation of $8.5 million of permanent savings from the SRT Life Extension project and increase the total project cost for the Easier Access III program to fund the Contract award.
Show the rest of As filed, 660 more characters as filed
3. Subject to recommendation 2 above, authorized the recommended budget adjustments to the TTC's 2025-2034 Capital Budget and Plan to be included in the TTC's Capital Variance Report submission to the City of Toronto for the four months ended April 30, 2025, for City Council consideration and approval. 4. Approved the recommendation contained in the Confidential Attachment 1 and authorized that the information in the Confidential Attachment remains confidential as it contains information about a position, plan, procedure, criteria or instruction to be applied to any negotiations carried on or to be carried on by or on behalf of the City or local board.
On the agenda
As the city filed it
The purpose of this report is to obtain authorization for the award of Contract W45-8, Old Mill Station Easier Access III (EAIII), to Maystar General Contractors Inc. in the amount of $25,690,748.88, inclusive of all taxes, on the basis of the lowest-priced acceptable bid. The contract work provides services for the construction of two elevators at Old Mill Station from street level to each side platform, new tactile attention tiles, station power upgrade, associated signage, mechanical and electrical upgrades and other associated elements to provide a barrier-free path throughout the station.
Show the rest of As the city filed it, 75 more characters as filed
The construction phase of the contract is scheduled to commence in Q2 2025.
Staff recommended
It is recommended that the TTC Board: 1. Authorize the award of Contract W45-8, Old Mill Station - Easier Access III to Maystar General Contractors Inc. in the amount of $25,690,748.88, inclusive of all taxes, on the basis of the lowest-priced acceptable bid. 2. Approve a reallocation of $8.5 million of permanent savings from the SRT Life Extension project and increase the total project cost for the Easier Access III program to fund the Contract award.
Show the rest of Staff recommended, 657 more characters as filed
3. Subject to recommendation 2 above, authorize the recommended budget adjustments to the TTC's 2025-2034 Capital Budget and Plan to be included in the TTC's Capital Variance Report submission to the City of Toronto for the four months ended April 30, 2025, for City Council consideration and approval. 4. Approve the recommendation contained in the Confidential Attachment 1 and authorize that the information in the Confidential Attachment remains confidential as it contains information about a position, plan, procedure, criteria or instruction to be applied to any negotiations carried on or to be carried on by or on behalf of the City or local board.
On the record
More from this meeting
- Chief Executive Officer’s Report - January 2025Filed record
- Subway and Streetcar State of Good Repair, Expansion and Modernization - 2024 Review and 2025/2026 ForecastFiled record
- 2025 Annual Service PlanFiled record
- Proposed Interim Wayfinding StrategyFiled record
- TTC Corporate Plan 2024 - 2028: Progress UpdateFiled record
- Fare Collection UpdateFiled record