The decision
2026-05-20 · Toronto City Council · amended
As filed
City Council on May 20 and 21, 2026, adopted the following: 1. City Council amend Toronto Municipal Code Chapter 681, Sewers, §681-4.J. Table 2 - Limits for Storm Sewer Discharge, by deleting "0.05" for the Manganese (total) limit and replacing it with "2.0". 2. City Council authorize the City Solicitor, in consultation with the General Manager, Toronto Water, to prepare the necessary bill required to give effect to City Council's decision and to make such clarification, minor modifications, technical or stylistic refinements as may be identified by the City Solicitor.
Show the rest of As filed, 1,518 more characters as filed
3. City Council direct the General Manager, Toronto Water, to permit development applications submitted after January 1, 2026, and which are ready and eligible to apply for above-grade building permits before October 1, 2026, to be exempt from the existing Storm Sewer Quality Limit for Manganese in Toronto Municipal Code Chapter 681, Sewers, and to instead be subject to the updated Storm Sewer Quality Limit for Manganese, where appropriate. 4. City Council request the General Manager, Toronto Water to report back to the Infrastructure and Environment Committee in the first quarter of 2027 with publicly accessible City-wide maps to reflect coverage of storm sewers and combined sewers, including areas with storm sewers in combined sewer sheds which outlet to rivers or lake Ontario, to demonstrate the geographical distribution of site impacts from the proposed Foundation Drainage Policy amendments contained in the report (April 22, 2026) from the General Manager, Toronto Water. 5. City Council request the General Manager, Toronto Water to report to the Infrastructure and Environment Committee in the first quarter of 2027 on the feasibility of amending the existing exemptions to the Foundation Drainage Policy to allow controlled, site-specific discharge to the combined sewer system in practical, limited circumstances where no other technically feasible alternative is available, while remaining compliant with the intent and purpose of the City's objective of reducing combined sewer overflow events.
The vote
Adopt Item as Amended · Carried, 21-1
The whole record, all 26 members
- Alejandra BravoFor
- Amber MorleyFor
- Anthony PerruzzaFor
- Ausma MalikFor
- Brad BradfordFor
- Chris MoiseAbsent
- Dianne SaxeFor
- Frances NunziataFor
- Gord PerksFor
- Jamaal MyersFor
- James PasternakFor
- Jon BurnsideFor
- Josh MatlowFor
- Lily ChengAbsent
- Michael ThompsonFor
- Mike ColleFor
- Neethan ShanFor
- Nick MantasAbsent
- Olivia ChowFor
- Parthi KandavelFor
- Paul AinslieAbsent
- Paula FletcherFor
- Rachel Chernos LinFor
- Shelley CarrollFor
- Stephen HolydayAgainst
- Vincent CrisantiFor
Every name opens that member’s record.
On the agenda
As the city filed it
This report responds to City Council direction for Toronto Water and Development Review to review the Foundation Drainage Policy and the feasibility of revising the manganese quality limit for storm sewer discharge in the Sewers By-law (Toronto Municipal Code, Chapter 681). The objective of this review was to identify opportunities to support the City's priority of encouraging new housing starts while ensuring that sewer system capacity is not compromised.
Show the rest of As the city filed it, 2,271 more characters as filed
Developments cannot proceed without adequate servicing infrastructure. Accordingly, the Foundation Drainage Policy prohibits groundwater discharges to the City's sewer systems to preserve the capacity required to support Toronto's continued growth and intensification. The policy amendments proposed in this report strike a balance between introducing greater flexibility to facilitate new housing development and maintaining the Foundation Drainage Policy's core objective of protecting sewer system capacity. Following stakeholder consultations, hydraulic capacity analyses of the sewer system and background research, effective October 1, 2026, Foundation Drainage Policy amendments will allow a limited quantity of foundation drainage containing groundwater to be discharged into the City's storm sewers, under the following conditions: - Foundation drainage flows meet the quality limits for storm sewer discharge in the Sewers By-law; - The storm sewer to which the foundation drain connects will discharge directly to a watercourse or Lake Ontario without interacting with the combined sewer system (i.e., there is no interaction with any flow control structures); - The maximum dry-weather discharge rate from foundation drainage is 3 Litres per second per hectare for sites > 0.7 hectare, and 2 Litres per second for sites ≤ 0.7 hectare; and - The total discharge rate under wet-weather conditions to the storm sewer from the site (i.e., both foundation drainage and stormwater) complies with all stormwater management targets per the City's Wet Weather Flow Management Guidelines. Staff also recommend an increase to the manganese quality limit for discharges to the storm sewer system from 0.05 milligrams per litre to 2.0 milligrams per litre, which will exclude higher concentrations associated with non-natural manganese sources (e.g., brownfield properties). Toronto Water staff consider the health and environmental risks associated with this recommendation to be low because anticipated groundwater discharge volumes will be limited, and because manganese levels in most groundwater samples naturally cluster around low concentrations. This report was developed in consultation with Development Review, who agree with the findings and recommendations.
Staff recommended
The General Manager, Toronto Water recommends that: 1. City Council amend Toronto Municipal Code, Chapter 681 ("Sewers"), §681-4.J. Table 2 - Limits for Storm Sewer Discharge, by deleting "0.05" for the Manganese (total) limit and replacing it with "2.0". 2. City Council authorize the City Solicitor, in consultation with the General Manager, Toronto Water to prepare the necessary bill required to give effect to City
Show the rest of Staff recommended, 150 more characters as filed
Council's decision and to make such clarification, minor modifications, technical or stylistic refinements as may be identified by the City Solicitor.
Considered
2026-05-06 · Infrastructure and Environment Committee · amended
Decision as filed
The Infrastructure and Environment Committee recommends that: 1. City Council amend Toronto Municipal Code, Chapter 681 ("Sewers"), §681-4.J. Table 2 - Limits for Storm Sewer Discharge, by deleting "0.05" for the Manganese (total) limit and replacing it with "2.0". 2. City Council authorize the City Solicitor, in consultation with the General Manager, Toronto Water to prepare the necessary bill required to give effect to City Council's decision and to make such clarification, minor modifications, technical or stylistic refinements as may be identified by the City Solicitor.
Show the rest of Decision as filed, 435 more characters as filed
3. City Council direct the General Manager, Toronto Water, to permit development applications submitted after January 1, 2026 and which are ready and eligible to apply for above-grade building permits before October 1, 2026, to be exempt from the existing Storm Sewer Quality Limit for Manganese in Toronto Municipal Code Chapter 681, and to instead be subject to the updated Storm Sewer Quality Limit for Manganese, where appropriate.
2026-05-20 · Toronto City Council · amended
On the record
More from this meeting
- 2025-2026 Annual Winter Maintenance Report and Amendment to Blanket Contracts C78, C87, C88 and C89 with Rafat General Contractor Inc., for the Non-Exclusive Supply of All Labour, Equipment and Material Necessary to Provide Single, Tandem and Tri Axle Dump Trucks with Operators for Trucking ServicesFiled record
- Forensic Audit of the 2021 Winter Maintenance ProcurementFiled record
- Transition of the Blue Box Program to Extended Producer Responsibility: First Quarter 2026 Post-Transition Implementation UpdateFiled record
- 2026 Annual Strategic Capital Coordination Report and Progress Update on Enhancing Capital Construction DeliveryFiled record
- 2026 Road Classification AmendmentsFiled record
- Feasibility of Requiring Side Guards on Contractor Commercial Vehicles Operating in the City of TorontoFiled record