The decision
2019-05-22 · Toronto and East York Community Council · amended
As filed
The Toronto and East York Community Council: 1. Approved the closure of the north sidewalk and a 5.2 metre wide portion of the westbound curb lane on the north side of Temperance Street, between a point 29.5 metres east of Bay Street and a point 97 metres further east and provision of a temporary pedestrian walkway within the closed portion of the westbound curb lane, from May 29, 2019 to September 30, 2021. 2. Designated Temperance Street, between Bay Street and a point 39 metres west of Yonge Street, as one-way for westbound traffic only.
Show the rest of As filed, 3,101 more characters as filed
3. Rescinded the existing parking machine regulation in effect from 8:00 a.m. to 9:00 p.m., Monday to Saturday; and 1:00 p.m. to 9:00 p.m., Sunday, on the north side of Temperance Street, between a point 15 metres east of Bay Street and a point 108 metres further east. 4. Rescinded the existing standing prohibition in effect at all times on the south side of Temperance Street, between Bay Street and a point 116.5 metres east. 5. Prohibited stopping at all times on the north side of Temperance Street, between Bay Street and a point 123 metres east. 6. Prohibited stopping at all times on the south side of Temperance Street, between Bay Street and a point 116.5 metres east. 7. Directed the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 8. Directed the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 9. Directed the applicant to sweep the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe. 10. Directed the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 11. Directed the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night. 12. Directed the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 13. Directed the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 14. Directed that Temperance Street be returned to pre-construction traffic and parking regulations when the project is complete. 15. Directed the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes. 16. In areas where no cycling lanes exist, direct the applicant, in consultation with Transportation Services, to install sharrow markings onto the roadway and display appropriate signage on the hoarding board to inform motorists and cyclist to safely share the road. 17. Directed the applicant to establish a construction management working group that meets monthly and invite local stakeholders including Transportation Services, Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours, local resident groups, and local BIAs. 18. Directed the applicant to create a publicly accessible website with regular construction updates and post the website address on the site.
On the agenda
As the city filed it
This staff report is about a matter that Community Council has delegated authority to make a final decision, provided that it is not amended so that it varies with City Policy or by-laws. Multiplex Global Canada Ltd. is constructing a 33-storey mixed-use office building with a 10-storey podium. The site is bounded by Richmond Street West to the north, Cloud Gardens Park to the east, Temperance Street to the south, and existing commercial uses (353-359 Bay Street) to the west.
Show the rest of As the city filed it, 321 more characters as filed
Transportation Services is requesting approval to close the north sidewalk and a portion of the westbound curb lane on Temperance Street for a period of 28 months (i.e. May 29, 2019 to September 30, 2021) to accommodate the construction staging area. Pedestrian movements will be accommodated within the closed curb lane.
Staff recommended
The Acting Director, Traffic Management, Transportation Services, recommends that: 1. Toronto and East York Community Council approve the closure of the north sidewalk and a 5.2 metre wide portion of the westbound curb lane on the north side of Temperance Street, between a point 29.5 metres east of Bay Street and a point 97 metres further east and provision of a temporary pedestrian walkway within the closed portion of the westbound curb lane, from May 29, 2019 to September 30, 2021.
Show the rest of Staff recommended, 2,840 more characters as filed
2. Toronto and East York Community Council designate Temperance Street, between Bay Street and a point 39 metres west of Yonge Street, as one-way for westbound traffic only. 3. Toronto and East York Community Council rescind the existing parking machine regulation in effect from 8:00 a.m. to 9:00 p.m., Monday to Saturday; and 1:00 p.m. to 9:00 p.m., Sunday, on the north side of Temperance Street, between a point 15 metres east of Bay Street and a point 108 metres further east. 4. Toronto and East York Community Council rescind the existing standing prohibition in effect at all times on the south side of Temperance Street, between Bay Street and a point 116.5 metres east. 5. Toronto and East York Community Council prohibit stopping at all times on the north side of Temperance Street, between Bay Street and a point 123 metres east. 6. Toronto and East York Community Council prohibit stopping at all times on the south side of Temperance Street, between Bay Street and a point 116.5 metres east. 7. Toronto and East York Community Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 8. Toronto and East York Community Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 9. Toronto and East York Community Council direct the applicant to sweep the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe. 10. Toronto and East York Community Council direct the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 11. Toronto and East York Community Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night. 12. Toronto and East York Community Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 13. Toronto and East York Community Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 14. Toronto and East York Community Council direct that Temperance Street be returned to pre-construction traffic and parking regulations when the project is complete.
On the record
More from this meeting
- Permanent Closure of the L-Shaped Public Lane Adjacent to and East of 1095-1105 Yonge Street, South of 5 Scrivener Square, and North of 8-10 Price StreetFiled record
- 871-899 College Street Zoning Amendment Application and Rental Housing Demolition Applications - Final ReportFiled record
- 321-333 King Street West - Zoning Amendment Application - Revised Request for Direction and Rental Housing Demolition Application ReportFiled record
- 348 Davenport Road - City Initiated Zoning Amendment - Final ReportFiled record
- 8 Elm Street and 348-356 Yonge Street - Zoning Amendment Application - Request for Direction ReportFiled record
- Demolition of a Heritage Building and Repeal of By-law 500-2015 for 327 - 333 - King Street West and Authority to Amend the Heritage Easement Agreement for 321-327 - 333 - King Street WestFiled record