The decision
2020-01-29 · Toronto City Council · adopted
As filed
City Council on January 29, 2020, adopted the following: 1. City Council amend City of Toronto Municipal Code Chapter 937, Temporary Closing of Highways, to delegate to the General Manager, Transportation Services, until December 31, 2030, inclusive, the authority to temporarily close to pedestrian and vehicular traffic highways or portions of highways for a period up to and including 365 consecutive days but ending no
Show the rest of As filed, 1,580 more characters as filed
later than December 31, 2030 inclusive, with the exception of those highways listed in Section 937-4 of Chapter 937, as required for the purpose of the construction of the Line 2 Scarborough Subway Extension and City Council exempt the General Manager, Transportation Services, in carrying out this delegated authority from Section 937-5 of Chapter 937, that being the requirement to notify the local Ward Councillor of the pending closure and the requirement to report on the proposed closure if so requested by the local Ward Councillor. 2. City Council amend City of Toronto Municipal Code Chapter 27, Council Procedures, to provide that the current delegation to Community Council to temporarily close local roads, collector roads, and minor arterial roads does not include closures delegated to the General Manager, Transportation Services, in carrying out the authority in Part 1 above. 3. City Council direct the General Manager, Transportation Services, to request Metrolinx to expand its use of a 24 hour, 7 days a week hotline to accept and track complaints and reports of issues associated with the Line 2 Scarborough Subway Extension. 4. City Council direct the General Manager, Transportation Services, to work with Metrolinx to provide details of long-term road occupancy permits to the public on project websites, consistent with current practices deployed within the Eglinton Crosstown Light Rail Transit, Finch West Light Rail Transit and GO Expansion projects. 5. City Council direct that the traffic lanes and sidewalks be reopened when the project is complete.
The vote
Adopt Item · Carried, 22-1
The whole record, all 26 members
- Ana BailãoFor
- Anthony PerruzzaFor
- Brad BradfordFor
- Cynthia LaiFor
- Denzil Minnan-WongFor
- Frances NunziataFor
- Gary CrawfordFor
- Gord PerksFor
- James PasternakFor
- Jaye RobinsonAbsent
- Jennifer McKelvieFor
- Jim KarygiannisFor
- Joe CressyFor
- John FilionFor
- John ToryFor
- Josh MatlowAgainst
- Kristyn Wong-TamAbsent
- Mark GrimesFor
- Michael FordFor
- Michael ThompsonFor
- Mike ColleFor
- Mike LaytonFor
- Paul AinslieFor
- Paula FletcherAbsent
- Shelley CarrollFor
- Stephen HolydayFor
Every name opens that member’s record.
On the agenda
As the city filed it
The purpose of this report is to seek approval to authorize the General Manager, Transportation Services until December 31, 2030 to temporarily close to pedestrian and vehicular traffic highways or portions of highways for a period up to and including 365 consecutive days, but ending no later than December 31, 2030, inclusive, as required for the purpose of construction of the Line 2 Scarborough Subway Extension. This recommended delegation is similar to authority previously granted to the General Manager, Transportation Services in relation to the Eglinton Crosstown Light Rail Transit, Finch West Light Rail Transit and GO Expansion projects.
Show the rest of As the city filed it, 532 more characters as filed
This authority is necessary as the scope of Line 2 Scarborough Subway Extension necessitates numerous concurrent and consecutive lane closures that will extend beyond thirty days during a multi-year construction period. Delegation minimizes the chance of project delay and significantly reduces the administrative burden on City of Toronto staff, enabling them to focus on working with Metrolinx, contractors, local ward Councillors, and the community to maximize the effectiveness of traffic management and construction scheduling.
Staff recommended
The General Manager, Transportation Services recommends that: 1. City Council amend City of Toronto Municipal Code Chapter 937, Temporary Closing of Highways, to delegate to the General Manager, Transportation Services, until December 31, 2030, inclusive, the authority to temporarily close to pedestrian and vehicular traffic highways or portions of highways for a period up to and including 365 consecutive days but ending
Show the rest of Staff recommended, 1,570 more characters as filed
no later than December 31, 2030 inclusive, with the exception of those highways listed in Section 937-4 of Chapter 937, as required for the purpose of the construction of the Line 2 Scarborough Subway Extension and exempt the General Manager, Transportation Services, in carrying out this delegated authority from Section 937-5 of Chapter 937, that being the requirement to notify the local Ward Councillor of the pending closure and the requirement to report on the proposed closure if so requested by the local Ward Councillor. 2. City Council amend City of Toronto Municipal Code Chapter 27, Council Procedures, to provide that the current delegation to Community Council to temporarily close local roads, collector roads, and minor arterial roads does not include closures delegated to the General Manager, Transportation Services, in carrying out the authority in Part 1 above. 3. City Council direct the General Manager, Transportation Services, to request Metrolinx to expand its use of a 24 hour, 7 days a week hotline to accept and track complaints and reports of issues associated with the Line 2 Scarborough Subway Extension. 4. City Council direct the General Manager, Transportation Services, to work with Metrolinx to provide details of long-term road occupancy permits to the public on project websites, consistent with current practices deployed within the Eglinton Crosstown Light Rail Transit, Finch West Light Rail Transit and GO Expansion projects. 5. City Council direct that the traffic lanes and sidewalks be reopened when the project is complete.
Considered
2020-01-09 · Infrastructure and Environment Committee · adopted
Decision as filed
The Infrastructure and Environment recommend that: 1. City Council amend City of Toronto Municipal Code Chapter 937, Temporary Closing of Highways, to delegate to the General Manager, Transportation Services, until December 31, 2030, inclusive, the authority to temporarily close to pedestrian and vehicular traffic highways or portions of highways for a period up to and including 365 consecutive days but ending no later
Show the rest of Decision as filed, 1,561 more characters as filed
than December 31, 2030 inclusive, with the exception of those highways listed in Section 937-4 of Chapter 937, as required for the purpose of the construction of the Line 2 Scarborough Subway Extension and exempt the General Manager, Transportation Services, in carrying out this delegated authority from Section 937-5 of Chapter 937, that being the requirement to notify the local Ward Councillor of the pending closure and the requirement to report on the proposed closure if so requested by the local Ward Councillor. 2. City Council amend City of Toronto Municipal Code Chapter 27, Council Procedures, to provide that the current delegation to Community Council to temporarily close local roads, collector roads, and minor arterial roads does not include closures delegated to the General Manager, Transportation Services, in carrying out the authority in Part 1 above. 3. City Council direct the General Manager, Transportation Services, to request Metrolinx to expand its use of a 24 hour, 7 days a week hotline to accept and track complaints and reports of issues associated with the Line 2 Scarborough Subway Extension. 4. City Council direct the General Manager, Transportation Services, to work with Metrolinx to provide details of long-term road occupancy permits to the public on project websites, consistent with current practices deployed within the Eglinton Crosstown Light Rail Transit, Finch West Light Rail Transit and GO Expansion projects. 5. City Council direct that the traffic lanes and sidewalks be reopened when the project is complete.
2020-01-29 · Toronto City Council · adopted
On the record
More from this meeting
- 2018 Tree Canopy StudyFiled record
- Enforcement of Tree ProtectionFiled record
- Federal Funding for Tree Planting in the City of TorontoFiled record
- Contract Award for Tender Call No. 249-2019 for the Rehabilitation of the Wilket Creek Sanitary Trunk Sewer and North York Storm Trunk SewerFiled record
- A Review of the City's Road Work Warranty RequirementsFiled record
- Agreements with Transit Agencies for Water and Sewer InstallationsFiled record