2020 Basement Flooding Protection Program Update
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2020-11-25 · Toronto City Council · amended
As filed
City Council on November 25 and 26, 2020, adopted the following: 1. City Council direct that projects identified through completed Basement Flooding studies proceed to detailed design and construction, if the cost per benefitting property, as determined during the preliminary design phase, is less than $68,000. 2. City Council direct that Basement Flooding Protection Program projects that exceed the threshold of $68,000 per benefitting property, at the preliminary design phase, be sequenced in accordance with the principle of implementing projects that achieve the greatest impact, with the greatest impact to be determined considering the following criteria: a.
Show the rest of As filed, 1,313 more characters as filed
hazard, projects that mitigate a greater extent of flooding and/or a higher probability of flooding; b. exposure, projects that are more likely to have residential basements and/or other critical infrastructure; c. vulnerability, where consideration is given to the Ontario Marginalization Index; and d. project capital cost that considers a lower cost per benefitting property. 3. City Council direct that Basement Flooding Protection Program projects that meet the $68,000 per benefitting property threshold be scheduled for implementation first and that projects that exceed the $68,000 per benefitting property threshold be scheduled for implementation after the Basement Flooding studies for the 67 study areas have been substantially completed. 4. City Council request the Chief Financial Officer and Treasurer, the Deputy City Manager, Infrastructure and Development Services, and the General Manager, Toronto Water, in consultation with the City Solicitor, to request the Ontario Ministry of Finance to amend insurance regulations to preclude the denial of insurance coverage by insurance providers in the event that homeowners are able to establish that flooding incidents they experienced occurred through no fault of their own and that they have taken all reasonable efforts to prevent future flooding.
The vote
Amend Item (Additional) · Carried, 24-0
The whole record, all 25 members
- Ana BailãoFor
- Anthony PerruzzaFor
- Brad BradfordFor
- Cynthia LaiFor
- Denzil Minnan-WongFor
- Frances NunziataFor
- Gary CrawfordFor
- Gord PerksFor
- James PasternakFor
- Jaye RobinsonFor
- Jennifer McKelvieFor
- Joe CressyFor
- John FilionFor
- John ToryAbsent
- Josh MatlowFor
- Kristyn Wong-TamFor
- Mark GrimesFor
- Michael FordFor
- Michael ThompsonFor
- Mike ColleFor
- Mike LaytonFor
- Paul AinslieFor
- Paula FletcherFor
- Shelley CarrollFor
- Stephen HolydayFor
Every name opens that member’s record.
On the agenda
As the city filed it
This report provides an update on the Basement Flooding Protection Program including a review of the prioritization approach and rules for recommended Basement Flooding Protection Program infrastructure improvement projects to proceed to implementation. This report also responds to Council direction concerning intergovernmental funding for the Basement Flooding Protection Program, the state of good repair program, and the feasibility of a localized Basement Flooding study in the sewer catchment area near the Humber River Hospital.
Show the rest of As the city filed it, 1,361 more characters as filed
Since its inception in 2006, the Basement Flooding Protection Program has made tremendous progress in completing Basement Flooding studies across the city. These studies have identified a significant number of sewer system improvement projects required to help reduce urban flooding risks. While many recommended Basement Flooding Protection Program projects have been implemented, many more projects have not proceeded to design and/or construction because they have not met the Council adopted prioritization rules for Basement Flooding Protection Program project implementation. Due to the large number, cost, and scale of the Basement Flooding improvement projects, it will take several decades to implement all the recommended projects. While the current $32,000 cost per benefitting property threshold has become a constraint in advancing recommended projects to implementation, a prioritization approach for implementation remains a critical requirement due to the large number of projects that remain to be implemented. This report recommends that the cost per benefitting property threshold be increased to $68,000. Also recommended is a further prioritization approach, for the time after the cost per benefitting property threshold has been applied across the whole City, which will sequence projects for implementation based on the project's impact.
Staff recommended
The General Manager, Toronto Water, recommends that: 1. City Council direct that projects identified through completed Basement Flooding studies proceed to detailed design and construction, if the cost per benefitting property, as determined during the preliminary design phase, is less than $68,000. 2. City Council direct that Basement Flooding Protection Program projects that exceed the threshold of $68,000 per benefitting property, at the preliminary design phase, be sequenced in accordance with the principle of implementing projects that achieve the greatest impact, with the greatest impact to be determined considering the following criteria: a.
Show the rest of Staff recommended, 752 more characters as filed
hazard, projects that mitigate a greater extent of flooding and/or a higher probability of flooding; b. exposure, projects that are more likely to have residential basements and/or other critical infrastructure; c. vulnerability, where consideration is given to the Ontario Marginalization Index, and; d. project capital cost that considers a lower cost per benefitting property. 3. City Council direct that Basement Flooding Protection Program projects that meet the $68,000 per benefitting property threshold be scheduled for implementation first, and that projects that exceed the $68,000 per benefitting property threshold be scheduled for implementation after the Basement Flooding studies for the 67 study areas have been substantially completed.
Considered
2020-11-05 · Infrastructure and Environment Committee · adopted
Decision as filed
The Infrastructure and Environment Committee recommends that: 1. City Council direct that projects identified through completed Basement Flooding studies proceed to detailed design and construction, if the cost per benefitting property, as determined during the preliminary design phase, is less than $68,000. 2. City Council direct that Basement Flooding Protection Program projects that exceed the threshold of $68,000 per benefitting property, at the preliminary design phase, be sequenced in accordance with the principle of implementing projects that achieve the greatest impact, with the greatest impact to be determined considering the following criteria: a.
Show the rest of Decision as filed, 751 more characters as filed
hazard, projects that mitigate a greater extent of flooding and/or a higher probability of flooding; b. exposure, projects that are more likely to have residential basements and/or other critical infrastructure; c. vulnerability, where consideration is given to the Ontario Marginalization Index; and d. project capital cost that considers a lower cost per benefitting property. 3. City Council direct that Basement Flooding Protection Program projects that meet the $68,000 per benefitting property threshold be scheduled for implementation first, and that projects that exceed the $68,000 per benefitting property threshold be scheduled for implementation after the Basement Flooding studies for the 67 study areas have been substantially completed.
2020-11-25 · Toronto City Council · amended
On the record
More from this meeting
- Amendment to Purchase Order Number 6048827 for the Western Beaches Tunnel - Sewer Chamber Modifications and Other Alterations Project and Amendment to Purchase Order Number 6046087 for Contract Administration ServicesFiled record
- Amendment to Purchase Order Number 6050585 with Grascan Construction Limited/Torbridge Construction Limited, for the Rehabilitation of the Bathurst Street Bridge, South of Front Street WestFiled record
- Reducing the State of Good Repair Backlog and Enhancing Cycling Lane MaintenanceFiled record
- Updates on Improvements to the Bike Lanes on Dundas Street East and Other By-Law AmendmentsFiled record
- MoveTO 2021-25 - Congestion Management Interim Action Plan and Non-Competitive Contract for Smart SignalsFiled record
- Clearing the Path Towards a Safe and Accessible WinterFiled record