Re-Open TE14.38 - Construction Staging Area - 112 College Street
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2020-12-16 · Toronto City Council · adopted
As filed
City Council on December 16, 17 and 18, 2020, adopted the following: 1. City Council amend Parts 1 and 2 of City Council's decision on TE14.38 by deleting "January 31, 2021" and replacing it with "August 31, 2021" so that the Parts now read as follows: 1. City Council authorize the closure of the north sidewalk on College Street, between a point 57 metres east of University Avenue and a point 66 metres further east, from July 1, 2020 to August 31, 2021.
Show the rest of As filed, 278 more characters as filed
2. City Council authorize the continuation of the closure of the bike lane and a portion of the westbound curb lane on the north side of College Street, between a point 50 metres east of University Avenue and a point 86 metres further east, from July 1, 2021 to August 31, 2021.
On the agenda
As the city filed it
EllisDon Corporation is constructing a 13-storey institutional building (the new University of Toronto Schwartz Reisman Innovation Centre) at 112 College Street. The site is located on the north side of College Street, east of University Avenue. The north sidewalk and a portion of the westbound curb lane on College Street, abutting the site, is currently closed for construction staging operations. Toronto City Council at its meeting on June 29 and 30, 2020 authorized the subject construction staging area on College Street from July 1, 2020 to January 31, 2021.
Show the rest of As the city filed it, 543 more characters as filed
The developer has requested an extension of the duration of the construction staging area on College Street, as the site has experienced a number of construction delays due to issues arising from COVID-19. EllisDon Cooperation is requesting to extend the duration of the construction staging area on College Street for an additional seven months (i.e. from February 1, 2021 to August 31, 2021), to allow for the construction of the development to be completed. Transportation Services has been consulted and have no objections to the proposal.
Staff recommended
Councillor Layton recommends that Toronto and East York Community Council recommend: 1. City Council re-open Item TE14.38 entitled "Construction Staging Area - 112 College Street" only with respect to Parts 1 and 2 of its decision. 2. That City Council amend City Council recommendation 1 and 2 by deleting January 31, 2021 and inserting August 31, 2021 so that they now read as follows: 1. City Council authorize the closure of the north sidewalk on College Street, between a point 57 metres east of University Avenue and a point 66 metres further east, from July 1, 2020 to August 31, 2021.
Show the rest of Staff recommended, 277 more characters as filed
2. City Council authorize the continuation of the closure of the bike lane and a portion of the westbound curb lane on the north side of College Street, between a point 50 metres east of University Avenue and a point 86 metres further east, from July 1, 2021 to August 31, 2021
Considered
2020-12-02 · Toronto and East York Community Council · adopted
Decision as filed
The Toronto and East York Community Council recommends that: 1. City Council re-open Item TE14.38 entitled "Construction Staging Area - 112 College Street" only with respect to Parts 1 and 2 of its decision. 2. City Council amend City Council Recommendations 1 and 2 by deleting "January 31, 2021" and replacing it with "August 31, 2021" so that the recommendations now read: 1. City Council authorize the closure of the north sidewalk on College Street, between a point 57 metres east of University Avenue and a point 66 metres further east, from July 1, 2020 to August 31, 2021.
Show the rest of Decision as filed, 278 more characters as filed
2. City Council authorize the continuation of the closure of the bike lane and a portion of the westbound curb lane on the north side of College Street, between a point 50 metres east of University Avenue and a point 86 metres further east, from July 1, 2021 to August 31, 2021.
2020-12-16 · Toronto City Council · adopted
Clerk’s note
City Council re-opened Item 2020.TE14.38, only as it pertained to Parts 1 and 2 of City Council's decision.
On the record
More from this meeting
- City-initiated Official Plan Amendment - Lower Don Flood Protection - Final ReportFiled record
- City-initiated Official Plan Amendment - Central Waterfront Secondary Plan Schedule 'A' - Proposed Rights of Way - Final ReportFiled record
- 466-468 Dovercourt Road - Official Plan Amendment and Zoning Amendment Application - Final ReportFiled record
- 15 Devonshire Place and 6 Hoskin Avenue - Zoning By-law Amendment Application - Final ReportFiled record
- 145-155 Balmoral Avenue - Official Plan and Zoning By-law Amendment Application - Final ReportFiled record
- 1637-1645 Bathurst Street - Zoning By-law Amendment and Rental Housing Demolition Application - Final ReportFiled record